• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/15

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

15 Cards in this Set

  • Front
  • Back
Delaying noncritical activities to lower peak demand on resources is known as resource
A) Shifting
B) Effectiveness
C) Manipulating
D) Smoothing
E) Allocation
D
If resources are not adequate to meet peak demands, the resulting reschedule is termed
A) Resource-constrained scheduling
B) Time-constrained scheduling
C) Mandatory leveling
D) Project resource adjustment
E) Allocation
A
When developing a new software package, the software must be designed, the code must be written, and the code must be tested. This is an example of a ______ constraint.
A) Physical
B) Technical
C) Resource
D) Schedule
E) Time
B
Sam the project engineer has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of a ______ constraint.
A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time
C
Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a _________ constraint.
A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time
A
All of the following are kinds of resource constraints except
A) Materials
B) People
C) Equipment
D) Information
E) All of the above are resource constraints
D
A special truck that George needs on his project has been scheduled on another project. This is a ______ constraint.
A) Working capital
B) People
C) Equipment
D) Information
E) Materials
C
Regina's boss has told her that her project is very important. If the critical path is delayed, she will be given whatever she needs to get it back on schedule. Her project is ________ constrained.
A) Time
B) Quality
C) Cost
D) Performance
E) Resource
A
Scheduling time-constrained projects focuses on resource
A) Demands
B) Increases
C) Assumptions
D) Utilization
E) All are correct
D
Resource leveling can provide
A) Lower peak demand
B) Reduced resource need over the life of the project
C) Reduced fluctuations in resource demand
D) Both A and B are correct
E) A, B, and C are all correct
E
In a resource-constrained project, which of the following is most likely to be changed?
A) The completion date
B) The budget
C) Project quality
D) Both A and B are equally likely
E) A, B, and C are all equally likely
A
In a resource-constrained project the second priority in assigning resources is usually given to activities with the
A) Smallest duration
B) Least slack
C) Most slack
D) Lowest identification number
E) Highest cost
A
plitting an activity creates the following situation:
A) More people working on the same activity
B) There are possible startup and shutdown costs
C) A resource may be moved from one activity to another and then back
D) Both B and C are correct
E) A, B, and C are all correct
14 INCORRECT
D
Which of the following is not one of the more common problems associated with scheduling multiproject resources?
A) Overall schedule slippage
B) Inefficient resource utilization
C) Resource bottlenecks
D) Both A and C are correct
E) A, B, and C are all correct
E
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. Which of the following is true?
A) We are spending less than we should for the project
B) We are doing a good job managing the project
C) We should check to see if all the bills have been paid
D) Both A and B are correct
E) We can't be sure how the project is going
E