The 100% rule relates to________.
|
THe next level decomposition of a WBS element must represent 100%
|
|
2.An activiity being analyzed under PERT was judged to most likely have a duration of 40 days.20 days 50 days. The estimates Pert duration of that activity is
|
38.33 days
|
|
3.Adding resources to an activity to shorten the critical path is called
|
crashing
|
|
4.The amount of time an activity can be delayed before affecting the project deadline is _______.
|
slack
|
|
5.______are rules of thumb used to estimate the current project based on prior project experience
|
Heuristics
|
|
6.______ are the processes of conducting risk management planning, identification, analysis, response planning, and monitoring and control on a project.
|
Project risk management
|
|
7.______can be useful for tracking and monitoring project progress b/c they are simply and straightforward.
|
Gantt Charts
|
|
8.______can help manage the critical path by providing information about which activities can be delayed without affecting the deadline target date
|
Project Network Diagram
|
|
9.completing activities in parallel is called _____
|
fast tracking
|
|
10.The cost of labor for using a resource are _______
|
Direct costs
|
|
11.Critical CHain Project management is based on the idea
|
that people often inflate or add cushioning to their estimates
|
|
12.The critical path is
|
the longest path in the project network
|
|
13.An estimation technique characterized by the allocation of timeframe for a specified activity. e.g. a team as two weeks to complete a task and at the end of two weeks work on that task ceases.
|
time boxing
|
|
14.An estimation technique characterized by the dividing the project into smaller modules and then directly estimating the time and effort in terms of person-hours, person-weeks
|
bottom-up estimating
|
|
15.An estimation technique characterized by the recruitment of multiple experts who provide rounds of estimates until a conses estimate emerges.
|
Delphi Technique
|
|
16.The estimation technique may be driven by an upper management mandate.
|
Top-down estimating
|
|
17._______ focuses on root cause analysis and determining the cause of risks, as well as the effects of risks on the project
|
cause and effect diagrams
|
|
18.Gaining consensus from a group of experts would be most closely associated with
|
Delphi Technique
|
|
19.Identifying what you know, what you think you know, and things you need to find out would be activities most closely associated with
|
Learning cycles
|
|
20.In project communications Managements, ensuring that clear, consistent, and timely communication satisifes the information needs and that prooject stakeholder issues are resolved is_____.
|
Identify stakeholders.
|
|
21._________involves deciding which risks can impact the project.
|
Identify risks
|
|
22._______ involves determining the likelihood and project impact of risk.
|
risk assesment
|
|
23.______ involves developing a probablisitic model for understanding and responding to identified risks.
|
Perform quantitative Risk Analysis
|
|
24.______involves developing procedures and techniques to reduce the threat of risks and enhance the liklihood of oppurtunities
|
Plan Risk Responses
|
|
25.______is an uncertain event that, if it occurs, has a positive or negative effect on project objectives.
|
Project risk
|
|
26.A _____ is a structured tool that identifies risks that have occured in the past.
|
Checklist
|
|
27._____is considered the most useful and widely used project management tool.
|
Gantt Charts
|
|
28._____ is ensuring that project resources are not overallocated.
|
Resource management
|
|
29.______ is the core layer in the IT project Risk Identification Framework.
|
Measurable Organizational Value
|
|
30.________is the most common, real-world method of estimating projects.
|
Bottom-up Estimating
|
|
31._______ is well suited for developing simulations where the project manager can conduct sensitivity analysis for schedule planning and risk analysis.
|
PERT
|
|
32.The IT project risk management Processes include all of the following except
|
Risk Eliminiation
|
|
33.Once the project schedule and project budget are approved they become the
|
Baseline plan
|
|
34.Project success will be determined in large part by __________.
|
Thinking carefully through activities and estimating their durations
|
|
35._____provides an early warning system to monitor identified risks and any new risks.
|
Monitor and control risks
|
|
36._______provide valuable information about the logical sequence and dependencies among the various activities and tasks
|
project network diagram
|
|
37.Recieving a much larger than usual gas utility bill because of an early spring cold spell is an example of what type of risk?
|
known-unkown risk
|
|
38.______refers to a broad range of measurements for objectively evaluating computer software.
|
Metrics
|
|
39.________requires determining the true proble, or cause, of the risk.
|
Risk identificaiton
|
|
40.A significant event or achievement that provides evidence that a deliverable is complete is called a _____
|
milestone
|
|
41.Starting the next task before the first task is complete is _______.
|
lead
|
|
42.A structured technique for identifying risks which requires participants to rank prioritize ideas in round robin fashion is most closely associated with
|
Nominal Group Technique
|
|
43.The technique used to find the sequence of tasks with zero slack is most closely associated with
|
Critical Path analysis
|
|
44.To be effective, each project phase should provide at least ____ deliverable.
|
one
|
|
45.Too much detail in the WBS can lead to __________.
|
Micromanagement
|
|
46.Under the PDM, the situation which occurs when two activities can start at different itmes, have different durations
|
Finish to Finish
|
|
47.Under the precedence Diagramming method the most common relationship between two activities which implies a logical sequence is called
|
Finish to Start
|
|
48.Under the Precedence Diagramming Method, the situation which occurs when a relationship between two tasks that can or must start at the same time is called
|
Start to Finish
|
|
49.Waiting to leave your shift until another person shows up is an example of
|
Start to finish
|
|
50.Which of the following statements about the work breakdown structure is not true?
|
The WBS should be developed only by the project manager
|