• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/37

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

37 Cards in this Set

  • Front
  • Back

What is procurement?

The overall process of acquiring construction work or services
What should be considered when selecting a procurement route?
The specifics of the project
The client objectives regarding cost, time, control, quality and risk

What are the main procurement methods?

Traditional / general contracting



Design and build



Management contracting



Construction management

What is traditional procurement?

The design is completed by the client’s design team before competitive tenders are invited and a main contractor is employed to build what the designers have specified


How does traditional procurement work?


The contractor takes responsibility and financial risk for the construction of the works to the design produced by the client’s design team for the contract sum within the contract period



The client takes the responsibility and risk for the design and design team performance

When might traditional procurement be appropriate?

If the employer has had the design prepared
If the design is substantially completed at time of contractor selection
The client wishes to retain control over the design and specification
Cost certainty at start on site is important
The shortest overall programme is not the client’s main priority

What contracts might be used?

JCT – minor, intermediate, standard with quantities

What are the advantages of traditional procurement?

Competitive fairness and transparent process – increase value for money
Design led – can ensure quality
Price certainty before commencement
Well known procedures
Changes are reasonably easy to arrange and value

What are the disadvantages?

Overall project may have a longer duration than others – sequential process
No contractor design and planning input
Strategy based on price competition – could lead to adversarial relations
Dual point of responsibility – design team for design and contractor for construction
If design not complete at time of tender, cost and time certainty are reduced

What is design and build?

Where the contractor is responsible for the design, planning, organisation, control and construction of the works to the employer’s requirements

How does D&B work?

The employer gives the tenderers the ‘Employer’s Requirements’ and the contractors respond with the ‘Contractor’s Proposals’, which include the price for the works


When might D&B be appropriate?

Where there is a need to make an early start on site – can overlap design and construction
Where the client wishes to minimise their risk – not got responsibility for design
For technically complex projects – benefit of contractor’s expertise
Where the employer does not want to retain control over the design development

What contracts might be used?

JCT DB 11

What are the advantages of design and build?

Single point of responsibility for design and construction
Earlier commencement on site
Early price certainty
Benefit of contractor’s experience harnessed during design

What are the disadvantages of D&B?

Client may find it hard to prepare a sufficiently comprehensive brief
Client has to commit to a concept design early
Variations from the original brief are difficult to arrange and often expensive
Harder to compare tenders – harder to determine if getting value for money
Ease of fabrication may be prioritised above aesthetic quality
May be less real competition due to fewer design and build firms

How much design input will the contractor have under D&B?

This depends on the amount of design work the employer has already had completed at time of tender



Can range from full design to production information and coordination only

Under D&B - who carries out the design for the contractor?


It may be outsourced to a separate design company (contractor retains responsibility)



They may have in-house design capabilities
OR the client’s team may be novated

What is novation?

A new contract that transfers the rights and obligations of one contractual party to a new third party i.e. design rights and obligations of architect transferred to contractor


If the design team is novated, what should the client put in place?

A collateral warranty to the design team to give them remedies for breach of contract

What is management contracting?

A management contractor is employed to contribute their expertise to the design and to manage construction and is paid a fee for doing so

How does management contracting work?

The Management Contractor has direct contractual links with all of the works contractors
They have the responsibility for the construction works without actually carrying them out
Not all of the design need be completed before the first works contractors start work
The MC selects the works contractors through competitive open book tenders
The client reimburses the cost of these packages to the MC plus their fee
The MC’s role is low risk – get prime cost plus a fee

When might management contracting be appropriate?

Where the client does not want cost certainty before commencement



Where an early start on site in a priority

What contract might be used?

JCT – Management Contract 05

What are the advantages of Management Contracting?

Overall project duration is shorter due to overlapping design and construction
There is contractor contribution to the design and planning process
Changes can be accommodated in packages not yet let if they have no further impact
The works are let competitively at current market prices on a firm price basis

What are the disadvantages of Management Contracting?

The price for the works is not received until the last package has been let
Changes to the design of later packages may affect packages already let - expensive
There is little incentive for the MC to reduce costs
May become a ‘post box’ system
In practice, the MC has little legal responsibility for the defaults of the works contractors

What is construction management?

The employer places a direct contract with each of the trade contractors and utilises the expertise of a construction managers who acts as a consultant to coordinate the contracts

How does it construction management work?

The trade contactors carry out the work
The construction managers supervises the construction process and coordinates the design team
The CM has no contractual links with the trade contractors or members of the design team
Their role includes preparation of the programme, determining requirements for site facilities, breaking down the project into suitable works packages, obtaining and evaluating tenders, co-ordinating and supervising the works

When might construction management be appropriate?

On large, complex projects were the advantages of CM can be put to use e.g. upfront buildability knowledge, programme advise, specialist input from trade contractors
Where early start on site is key
Flexibility in design, procurement, construction strategy
Where price certainty before commencement is not key
Where the client is experienced in construction

What contracts might be used for construction management ?

JCT - Construction Management Agreement CM/A AND Construction Management Trade Contract (CM/TC)

What are the advantages of construction management?

Overall project duration reduced by overlapping design and construction
Construction manager can contribute to the design and project planning processes
Roles, risks and relationships for all parties are clear
Changes in design can be accommodated without paying a premium
Prices may be lower due to direct contracts with trade contractors
Client has means of redress to trade contractors through direct contractual links

What are the disadvantages of construction management?

Price certainty not achieved until last trade package is let
Changes to later packages may adversely affect packages already let - expensive
Need an informed, pro active client
Client has a lot of consultants and contractors to deal with – not just one – more fees

What is the difference between management contracting and construction management?

Under construction management the client is in direct contractual relationships with each of the trade contractors and the construction manager isn’t



Under management contracting, the MC is in direct contractual relationships with the trade contractors and the client is in contract with the MC only

How do you identify the client requirements before recommending a procurement route?

Through detailed discussions with the client and design team to identify their priorities in terms of cost, time, quality, risk, control requirements and experience

If the client wishes to start on site asap what procurement route would you recommend?

Depends on their other requirements – such as cost and quality




If time was their overriding priority then CM or MC as they offer the fastest start on site, this is because start on site is not dependent upon a long tender period BUT has consequential disadvantages in terms of cost certainty

What if they wanted an early start but also cost certainty, what procurement route would you recommend?

Then design and build might be the most appropriate
Allows design and construction to be overlapped rather than being sequential
Tenders are based on the provision of all services so the client gets a lump sum price

What is GMP? What does it mean to you?

Guaranteed maximum price



A lump sum contract under which there is no adjustment of tender price unless the SCOPE required by the client changes



The contractor includes the additional risks involved in the design development process in his tender price

What are the advantages of GMP?

Greater price certainty – contractor takes risk of design development and unforeseen occurrences



Greater control of overspending – contractor’s interests to alert the team to expensive items of design development



Quicker settlement of final account

What are the disadvantages of GMP?

The client may pay too much – contractor’s risk allowance may be higher than in reality



Scope changes are likely to be very expensive



Can be adversarial – trying to decide whether changes are design development or scope changes