PERT Expected Activity Duration (EAD)
|
(P+4M+O)/4
|
|
Standard Deviation of an activity (SD)
|
(P-O)/6
|
|
Variance of a activity
|
((P-O)/6)^2
SD^2 Standard Deviation squared |
|
Range of an activity duration
|
EAD +/- SD
|
|
Total Float
|
LS-ES or LF-EF
|
|
Cost Variance (CV)
|
EV-AC
|
|
Schedule variance (SV)
|
EV-PV
|
|
Cost Performance Index (CPI) or CPI(c)
|
EV/AC of EV(c)/AC(c)
|
|
Schedule Performance Index (SPI)
|
EV/PV
|
|
Estimate at Completion (EAC)
|
AC+ Bottom up ETC
|
|
Estimate at Completion (EAC)
|
BAC/CPI(c)
|
|
Estimate at Completion (EAC)
|
AC + (BAC - EV)
|
|
Estimate at Completion (EAC)
|
AC + (BAC - EV)/(CPI(c) * SPI(c)
|
|
To Complete Performance Index (TCPI)
|
(BAC - EV)/(BAC - AC)
|
|
Estimate at Completion (ETC)
|
EAC - AC
|
|
Variance at Completion (VAC)
|
BAC - EAC
|
|
Communication Channels
|
N *(N-1)/2
|
|
Expected Monetary Value (EMV)
|
P * I
Probability * Impact(in $) |
|
Point of Total Assumption (PTA)
|
(Ceiling Price - Target Price)/Buyer's share ratio +Target Cost
|