• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/19

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

19 Cards in this Set

  • Front
  • Back
PERT Expected Activity Duration (EAD)
(P+4M+O)/4
Standard Deviation of an activity (SD)
(P-O)/6
Variance of a activity
((P-O)/6)^2
SD^2
Standard Deviation squared
Range of an activity duration
EAD +/- SD
Total Float
LS-ES or LF-EF
Cost Variance (CV)
EV-AC
Schedule variance (SV)
EV-PV
Cost Performance Index (CPI) or CPI(c)
EV/AC of EV(c)/AC(c)
Schedule Performance Index (SPI)
EV/PV
Estimate at Completion (EAC)
AC+ Bottom up ETC
Estimate at Completion (EAC)
BAC/CPI(c)
Estimate at Completion (EAC)
AC + (BAC - EV)
Estimate at Completion (EAC)
AC + (BAC - EV)/(CPI(c) * SPI(c)
To Complete Performance Index (TCPI)
(BAC - EV)/(BAC - AC)
Estimate at Completion (ETC)
EAC - AC
Variance at Completion (VAC)
BAC - EAC
Communication Channels
N *(N-1)/2
Expected Monetary Value (EMV)
P * I
Probability * Impact(in $)
Point of Total Assumption (PTA)
(Ceiling Price - Target Price)/Buyer's share ratio +Target Cost