• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/18

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

18 Cards in this Set

  • Front
  • Back
EV

(budgeting)
EV = % complete x BAC

Budgeted cost of the work performed so far.

Used to track overall completion of a project.

EV is a calculated value, not the actual expense.
SV
SV = (EV - PV)

Schedule Variance

Measures schedule variance in $ (how many $ are you ahead / behind schedule).
AC
Actual Cost
CPI
CPI = EV / AC

Cost Performance Index

Measures cost variance as a %
SPI
SPI = EV / PV

Schedule Performance Index

Measures schedule variance as a %
RTD
RTD = BD / SPI

Revised Total Duration

The projected duration based on how the project is actually going, schedule-wise.
BAC
Budgeted At Completion

The end point of the PV curve; the total budget.
BD
Baseline Duration

The planned duration of the project.
EAC
EAC = BAC / CPI

Estimate At Completion

What the project will cost, based on how the project is going, cost-wise.
CV
CV = EV - AC

Cost Variance

Measures cost variance in $
PV
Planned Value

The line that shows how much is budgeted over the life of the project.
Float
Forward pass = ls - es

Backward pass = lf - ef
Early Finish (of project)
(Early Start + Duration) - 1
Late Start (of project)
Early Start + Float
Late Finish (of project)
(Late Start + Duration) - 1
PERT
(P + 4M + O) / 6
Triangulation Estimate (beta estimate)
(P + M + O) / 3
Standard Deviation Estimate
(P - O) / 6