Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
11 Cards in this Set
- Front
- Back
BAC = ____ ? |
BAC = Σ (PV ) (Balance at Completion) |
|
EV = |
EV = % Complete of BAC Earned Value is a percentage of the Balance at Completion |
|
AV = |
AV = EV- AC Actual Variance = (Earned Value) - (Actual Costs) |
|
CV |
CV = EV - AC Cost Variance is equal to Earned Value minus Actual Costs. * Negative variance is cost overrun |
|
SV |
SV = EV - PV Scheduled Variance is equal to Earned Value minus Planned Value * Negative variance is behind schedule |
|
CPI |
CPI = EV / AC Cost Performance Index is equal to Earned Value/Actual Costs * Less than one is cost overrun. |
|
SPI |
SPI = EV / PV Schedule Performance Index is equal to Earned Value/Planned Value. * Less than one is behind schedule. |
|
AC |
AC=CV / (CPI-1) Actual Costs is equal to Cost Variance / (Cost Performance Index - 1) |
|
PV |
PV=SV / (SPI-1)Planned Value is equal to Schedule Variance / (Schedule Performance Index - 1) |
|
ETC |
ETC = EAC - AC Estimation to Completion = (Estimate at Completion) - (Actual Costs) |
|
VAC |
VAC = BAC - EAC Variance at Completion = (Balance at Completion) - (Estimate at Completion) |