EV
(budgeting) |
EV = % complete x BAC
Budgeted cost of the work performed so far. Used to track overall completion of a project. EV is a calculated value, not the actual expense. |
|
Planned Value (a.k.a. what)
|
Budgeted cost for the work scheduled to be completed on an activity or a work breakdown structure component. also referred to as the Budgeted Cost of Work Scheduled (BCWS)
|
|
SV
|
SV = (EV - PV)
Schedule Variance Measures schedule variance in $ (how many $ are you ahead / behind schedule). |
|
Budget At Completion
|
Sum of all the budget values established for work to be performed on a project; total planned value for the project
|
|
AC
|
Actual Cost
|
|
Earned Value (a.k.a. what?)
|
Also referred to as the
Budgeted Cost of Work Performed (BCWP). Budgeted amount for the work actually completed on the schedule activity or a work breakdown structure component. Formula: EV = BAC * %Comp |
|
CPI
|
CPI = EV / AC
Cost Performance Index Measures cost variance as a % |
|
Actual Cost (a.k.a. what?)
|
Also referred to as the Actual Cost of Work Performed (ACWP). Total cost of accomplishing the work on a schedule activity or a work breakdown structure component
|
|
SPI
|
SPI = EV / PV
Schedule Performance Index Measures schedule variance as a % |
|
Cost Variance
|
A measure of cost performance on a project
Formula: CV = EV - AC |
|
RTD
|
RTD = BD / SPI
Revised Total Duration The projected duration based on how the project is actually going, schedule-wise. |
|
Schedule Variance
|
A measure of schedule performance on a project
Formula: SV = EV - PV |
|
BAC
|
Budgeted At Completion
The end point of the PV curve; the total budget. |
|
Cost Variance %
|
Tells you what percentage cost varies for the work performed to date
Formula: CV % = CV / EV |
|
BD
|
Baseline Duration
The planned duration of the project. |
|
Schedule Variance %
|
Tells you what percentage schedule varies from what had been planned to date
Formula: SV % = SV / PV |
|
EAC
|
EAC = BAC / CPI
Estimate At Completion What the project will cost, based on how the project is going, cost-wise. |
|
Cost Performance Index
|
A measure of cost efficiency on a project
Formula: CPI = EV / AC |
|
CV
|
CV = EV - AC
Cost Variance Measures cost variance in $ |
|
Schedule Performance Index
|
A measure of schedule efficiency on a project
Formula: SPI = EV / PV |
|
PV
|
Planned Value
The line that shows how much is budgeted over the life of the project. |
|
To-Complete Performance Index
|
Denotes, from a point in time, the efficiency that must be achieved in order to complete the remaining work with the expected remaining
money Formula: TCPI = (BAC – EV) / (BAC – AC) |
|
Float
|
Forward pass = ls - es
Backward pass = lf - ef |
|
Percent Complete
|
An estimate, expressed as a percent, of the amount of work that has been completed on an activity or a work breakdown structure component
Formula: % Comp = EV / BAC |
|
Early Finish (of project)
|
(Early Start + Duration) - 1
|
|
Percent Spent
|
An estimate, expressed as a percent, of the money that has been spent
Formula: % Spent = AC / BAC |
|
Late Start (of project)
|
Early Start + Float
|
|
Estimate At Completion
|
Expected total cost of a schedule activity, a work breakdown structure component, or the project
Formulas: EAC = BAC / CPI or EAC = AC / % Comp |
|
Late Finish (of project)
|
(Late Start + Duration) - 1
|
|
Estimate To Complete
|
Expected cost needed to complete all the remaining work for a schedule activity, work breakdown structure component, or the project
Formula: ETC = EAC - AC or ETC = (BAC - EV) / CPI |
|
PERT
|
(P + 4ML + O) / 6
|
|
Variance At Completion
|
Difference between the total budget assigned to a project, budget at completion (BAC), and the total cost estimate at completion (EAC)
Formula: VAC = BAC - EAC |
|
Triangulation Estimate (beta estimate)
|
(P + M + O) / 3
|
|
Standard Deviation Estimate
|
(P - O) / 6
|