Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/37

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

37 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)
How many processes in "Project Time Management"
6
Define Activities
Sequence activities
Estimate Activity Resources
Estimate ACtivity Durations
Develop Schedule
Control Schedule
Project Time Management
What is the process of time management?
Define activities
Sequence activities
Estimate activity resources
Estimate activity durations
Develop schedule
Control schedule
Project Time Management
In which process is the schedule management plan created?
The schedule management plan is created in the integration management process as part of develop project management plan
Project Time Management
What are key outputs of the define activities process?
Activity list
Activity attributes
Milestone list
Project Time Management
What a key outputs of the sequence activities process?
Network diagrams
Project document Updates
Project Time Management
What is a key output of the estimate activity resources process?
Activity resource requirements
Project Time Management
What are key outputs of the control schedule process?
Work performance measurements
Change requests
Updates To Project Management Plan And Project Documents
Project Time Management
Question:
efine Activities
Process Group
Answer:

• Planning
Project Time Management
Question:
Define Activities
Knowledge Area
Answer:

• Project Time Management
Project Time Management
Question:
Define Activities
Inputs
Answer:

• Scope baseline
• Enterprise environmental factors
• OPA
Project Time Management
Question:
Define Activities
Tools & Techniques
Answer:

• Decomposition
• Rolling wave planning
• Templates
• Expert judgement
Project Time Management
Question:
Define Activities
Outputs
Answer:

• Activity list
• Activity attributes
• Milestone list
Project Time Management
Question:
Sequence Activities
Process Group
Answer:

• Planning
Project Time Management
Question:
Sequence Activities
Knowledge Area
Answer:

• Project time management
Project Time Management
Question:
Sequence Activities
Inputs
Answer:

• Activity list
• Activity attributes
• Milestone list
• Project scope statement
• OPA
Project Time Management
Question:
Sequence Activities
Tools & Techniques
Answer:

• Precedence diagraming method (PDM)
• Dependency determination
• Applying leads & lags
• Schedule network templates
Project Time Management
Question:
Sequence Activities
Outputs
Answer:

• Project schedule network diagrams
• Project document updates
Project Time Management
Question:
Estimate Activity Resources
Process Group
Answer:

• Planning
Project Time Management
Question:
Estimate Activity Resources
Knowledge Area
Answer:

• Project Time Management
Project Time Management
Question:
Estimate Activity Resources
Inputs
Answer:

• Activity list
• Activity attributres
• Resource calendars
• Enterprise environmental factors (EEF)
• OPA
Project Time Management
Question:
Estimate Activity Resources
Tools & Techniques
Answer:

• Expert judgement
• Alternatives analysis
• Published estimating data
• Bottom up estimating
• PM software
Project Time Management
Question:
Estimate Activity Resources
Outputs
Answer:

• Activity resource requirements
• Resource breakdown structure
• Project document updates
Project Time Management
Question:
Estimate Activity Durations
Process Group
Answer:

• Planning
Project Time Management
Question:
Estimate Activity Durations
Knowledge Area
Answer:

• Project time management
Project Time Management
Question:
Estimate Activity Durations
Inputs
Answer:

• Activity list
• Activity attributes
• Activity resource requirements
• Resource calendars
• Project scope statement
• EEF
• OPA
Project Time Management
Question:
Estimate Activity Durations
Tools & Techniques
Answer:

• Expert judgement
• Analogous estimating
• Parametric estimating
• 3 point estimates
• Reserve analysis
Project Time Management
Question:
Estimate Activity Durations
Outputs
Answer:

• Activity duration estimates
• Project document updates
Project Time Management
Question:
Develop Schedule
Process Group
Answer:

• Planning
Project Time Management
Question:
Develop Schedule
Knowledge Area
Answer:

• Project time management
Project Time Management
Question:
Develop Schedule
Inputs
Answer:

• Activity list
• Activity attributes
• Project schedule network diagrams
• Activity resource requirements
• Resource calendars
• Activity duration estimates
• PSS
• EEF
• OPA
Project Time Management
Question:
Develop Schedule
Tools & Techniques
Answer:

• Schedule network analysis
• Critical path method
• Critical chain method
• Resource leveling
• What if scenario analysis
• Applying leads & lags
• Schedule compression
• Scheduling tool
Project Time Management
Question:
Develop Schedule
Outputs
Answer:

• Project schedule
• Schedule baseline
• Schedule data
• Project document updates
Project Time Management
Question:
Control Schedule
Process Group
Answer:

• Monitoring & controlling
Project Time Management
Question:
Control Schedule
Knowledge Area
Answer:

• Project Time Management
Project Time Management
Question:
Control Schedule
Inputs
Answer:

• PMP, Project Management Plan
• Project schedule
• Work performance information
• OPA, Organizational Process Assets
Project Time Management
Question:
Control Schedule
Tools & Techniques
Answer:

• Performance reviews
• Variance analysis
• PM software
• Resource leveling
• What if scenario analysis
• Adjusting leads & lags
• Schedule compression
• Scheduling tool
Project Time Management
Question:
Control Schedule
Outputs
Answer:

• Work performance measurements
• OPA updates
• Change requests
• PMP updates
• Project document updates
Project Time Management