• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/30

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

30 Cards in this Set

  • Front
  • Back
Name the Processes (5)
Initiation
Planning
Execution
Monitor and Control
Closing
What are the Knowledge Areas (10)
I S T C Q H C P R P
Integration
Scope Management
Time Management
Cost Management 
Quality Management
HR management
Communications Management
Procurement Management
Risk Management
Professional Responsibility
Integration
Scope Management
Time Management
Cost Management
Quality Management
HR management
Communications Management
Procurement Management
Risk Management
Professional Responsibility
BAC
Budget at Completion
EV = ?
Acutal % * BAC
Planned Value = ?
Planned % * BAC
AC = ?
Sum of all incurred costs
CV =?
EV - AC
CPI = ?
EV/AC
When is the CPI over Budget
CPI < 1
When is the CPI under Budget
CPI > 1
SPI = ?
EV/PV
When is the SPI behind schedule
SPI < 1
When is the SPI ahead of schedule
SPI > 1
EAC= (Equation 1)
BAC/CPI
EAC=(Equation 2)
AC+ETC
EAC=(Equation 3)
AC+(BAC+EV)/CPI
ETC=
EAC-AC
VAC=
BAC-EAC
BCWS=
PV
BCWP=
EV
ACWP=
AC
Tip 1
Negative bad
TIP 2
Positive Good
If Variance
EV-Something
If Index
EV/Something
If Cost use
AC
If Time use
PV
80 Hour Rule
Max size of work packages
80/20 Rule
Pareto's Law 20% of causes responsible for 80% of problems
0/50/100
Work package completion. No credit until 50% complete. No additonal credit until 100% complete