• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/19

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

19 Cards in this Set

  • Front
  • Back
PERT expected activity duration (EAD)
(P + 4M + O) / 6
Standard deviation of an activity (SD)
(P - O) / 6
Variance of an activity
SD squared
Range of an activity duration
EAD +/- SD
Total float
LS - ES or LF - EF
Cost variance (CV)
EV - AC
Schedule variance
EV - PV
Cost Performance Index (CPI)
EV / AC
Schedule Performance Index (CPI)
EV / PV
Estimate at Completion (EAC)
AC + bottom-up ETC
Estimate at Completion (EAC)
BAC / CPIc
Estimate at Completion (EAC)
AC + (BAC - EV)
Estimate at Completion (EAC)
AC + (BAC - EV) / (CPIc x SPIc)
To Complete Performance Index
(BAC - EV) / (BAC - AC)
Estimate to Complete
EAC - AC
Variance at Completion
BAC - EAC
Communication channels
N (N - 1) / 2
Expected monetary value (EMV)
Probability x Impact
Point of Total Assumption (PTA)
( (Ceiling price - Target price) / Buyer's share ratio ) + Target Cost