20 Cards in this Set

  • Front
  • Back
Which of the following processes of project time management involves identifying and documenting the relationships between project activities?
a. activity definition
*b. activity sequencing
c. activity resource estimating
d. activity duration estimating
Activity resource requirements, a resource breakdown structure, requested changes, and updates to the activity attributes and resource calendars are the main outputs of ________.
a. activity duration estimating
*b. activity resource estimating
c. activity sequencing
d. activity definition
Which of the following processes of project time management involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables?
a. activity sequencing
b. activity duration estimating
c. activity resource estimating
*d. activity definition
Which of the following processes of project time management involves estimating the number of work periods that are needed to complete individual activities?
*a. activity duration estimating
b. activity sequencing
c. activity definition
d. activity resource estimating
A(n) ________ on a project is a significant event that normally has no duration.
a. dependency
*b. milestone
c. activity attribute
d. activity list
A project team might follow good practice and not start the detailed design of a new information system until the users sign off on all of the analysis work. This is an example of a(n) ________ dependency.
a. finish-to-finish
b. mandatory
c. external
*d. discretionary
A(n) ________ dependency is inherent in the nature of the work being performed on a project and is sometimes referred to as hard logic.
a. discretionary
*b. mandatory
c. finish-to-finish
d. external
A _______ is a schematic display of the logical relationships among, or sequencing of, project activities.
a. tracking Gantt chart
*b. network diagram
c. Gantt chart
d. critical path
Which of the following describes a relationship where the "from" activity must be finished before the "to" activity can be finished?
a. start-to-finish
b. start-to-start
c. finish-to-start
*d. finish-to-finish
On several information technology projects, a group of activities all start simultaneously, such as the many tasks that occur when a new system goes live. This is an example of which type of relationship?
*a. start-to-start
b. start-to-finish
c. finish-to-start
d. finish-to-finish
A ________ is a hierarchical structure that identifies the project's resources by category and type.
a. work breakdown structure
b. tracking Gantt chart
c. schedule baseline
*d. resource breakdown structure
The planned schedule dates for activities are called the ________.
*a. baseline dates
b. schedule baselines
c. nodes
d. milestones
________ is a network diagramming technique used to predict total project duration.
*a. Critical path method (CPM)
b. Activity sequencing
c. Critical chain scheduling
d. Arrow diagramming method (ADM)
________ describes the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.
a. Fast tracking
*b. Free slack
c. Total slack
d. Crashing
In critical path analysis, a ________ determines the early start and early finish dates for each activity.
*a. forward pass
b. late start date
c. late finish date
d. backward pass
Which of the following involves doing activities in parallel that you would normally do in sequence?
a. crashing
b. multitasking
*c. fast tracking
d. bursting
________ is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.
*a. Critical chain scheduling
b. Activity duration estimating
c. Program Evaluation and Review Technique (PERT)
d. Precedence Diagramming Method (PDM)
There are many issues involved in controlling changes to project schedules. It is important first to ensure that the project schedule is ________.
a. reliable
b. flexible
*c. realistic
d. detailed and specific
________ states that work expands to fill the time allowed.
a. Theory of Constraints (TOC)
b. Murphy's Law
*c. Parkinson's Law
d. PERT
________ occurs when a resource works on more than one task at a time.
a. Fast tracking
b. Merging
c. Crashing
*d. Multitasking