• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/26

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

26 Cards in this Set

  • Front
  • Back

Which of the following is not a quality control procedure?

D. None of the above

An assurance report submitted every quarter of the month

CQCA

What is not required in conducting nuclear density test?

Use a calibrated sand

Which of the following is not a responsibility of a materials engineer?

Setting sched for delivery of materials

Where should the Contractor’s Material’s Engineer directly report?

Contractors project engineer

lt means to regulate:

Control

lt means excellence

Quality

Which of the following are documents is prepared by a materials engineer?

Mat. Logbook

compaction of an embankment is 80% which below the required compaction. As a materials engineer, what should you do?

Use rollers with high compactive effort

minimum testing apparatus requirements are necessary for _______ contractors.

AOTA

Which of the following is not the job for a materials engineer?

Survey and measure line and grade at site

During construction of a road project, if all the materials to be used are tested for quality, inspection is no longer required

False

he physical and engineering properties of soils may be improved by:

Both a and b

The density to which a soil can be compacted is related to

Aota

As a Materials Engineer, what will you do with major honey-combed area that is considered as defective work?

Remove and replace at the expense of the contractor

lf the strength of control specimen does not meet the requirement Materials Engineer what will be your decision?

Remove and replace

Specifies the minimum number of tests required for an item of work which corresponds to the quantities stated in the approved Program of Work of a project

Quality Control program

Prescribed in each project based on estimated quantities. The requirements specify the kind and number of test for each item of work:


Minimum testing requirements

It shall have at least a minimum dimension of ___ sq. m. for a district laboratory and ____ sq. m. for regional laboratory and shall contain the required testing apparatus/equipment, supplies, furnishings required by the work.


10,20

All samples should be submitted with the corresponding ______

Sample card

Refers to the process of determining the degree of compliance of delivered or constructed materials with the specification

Materials testing

The basis of acceptance or rejection of any construction materials?


Mills certificate

The monthly materials status report is submitted to DPWH on or before:


25th day of the month

A joint which controls the location of transverse crack and permits the slab to contract and expand with changes in temperature?


Contraction joint

Materials shall be obtained from approved materials sources and should be known in advance


True

The accomplishment of Quality control logbook is prepared by:

Materials engineer