• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/141

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

141 Cards in this Set

  • Front
  • Back

What are the 3 MPRs?

1) Must be on permanent land


2) Must use reasonable LEED boundary.


3) Must comply with size requirement: BD+C>1000 SF

Neighborhood Development location can earn up to how many points? What other restrictions apply if you go for this credit?

16 points. Cannot attempt other LEED L/T Credits

For Sensitive Land Protection credit, what meets sensitive land criteria? (4 types)

Prime Farmland, Floodplains, home of threatened/endangered species, within 50' of wetlands and 100' of waterbodies

Who determines Prime Farmland

US Department of Agriculture

How close can a site be to wetlands? And water bodies?

50' for wetlands and 100' of water body

What organization determines floodplains?

FEMA

Minor improvements are allowed within wetland and water bodies buffer zone. What does that include? (7)

Brownfield remediation, bike/ped paths <12' wide, restoration of natural habitats, grade changes for public access, a <500SF structure, clearings <500SF, removal of certain tree types

For High Priority Site credit, what are the 3 options of sites and points?

Historic district (1), Priority designation (1), Brownfield (2)

What is infill status for historic districts?

75% of land within 1/2 mile must be previous developed. Required for historic district point.

Priority Designation (for High Priority Site credit) can be defined by which orgs? (3)

EPA National Priorities list, Federal Empowerment Zone, Federal Enterprise Community Site

FAR?

Floor to Area Ratio (non res.)

DU/Acre?

Dwelling Unit per Acre (residential)


For Surrounding Density Credit

Surrounding Density Credit requirement?

Meet certain values of FAR or DU/Acre within 1/4 mile radius of project.

Diverse Uses Credit requirement?

Within 1/2 mile walking, need 4-7 units for 1 pt and 8+ uses for 2 pts. Need 3 out of 5 of categories

What are the categories for Diverse Uses? (5)

Food Retail


Community-Serving Retail


Services


Community and Civic Facilities


Community Anchor Uses (large commercial offices)

Warehouses: Requirements for Surrounding Diversity/Density Credit?


2 Options

Opt 1) Prev dev site, extra point if adj. to industrial site


Opt 2) Meet 2-3 (1 pt) or 4 (2 pt) of following:


- <10 miles driving of logistics hub e.g. airport


-<1 mile from highway on ramp


-<1 mile from freight rail line access pt


-site is served by active freight rail spur

Access to Quality Transit requirement?

1/4 mile walking to bus/rideshare, 1/2 mile walking to rapid transit/rail/ferry,


includes stops planned to start within 2 years

School adaptation of Access to Quality Transit?

No weekend trips required, or can use % of pedestrian access from students homes:


elem/mid: 3/4 mi walking


HS: 1.5 mi walking


50% of students = 1 pt, 60=2, 70=3

Bicycle Network requirements (1 of 3)

Any of following:


-designated on -street bike lanes 5'+ wide


-off street bike path 8' wide for 2-way


-streets with speed 25mph or less

Bicycle Facilities network requirements (4)?

-Bicycle network connecting 10 diverse uses (3 mi)


-bike storage/entry within 200 yards of bike network


-school/employment accessible via bike network if bldg is 50%+ res (3 mi)


-bus stop, train station, or ferry (3 mi)

Bicycle Facilities storage/shower requirements for commercial bldgs?

-short term 2.5% peak, min 4


-long term 5% reg occups, min 4


-1 onsite shower for 1st 100 visitors and addtl per next 150

Bicycle Facilities storage/shower requirements for residential bldgs?

-short term 2.5% peak, min 4


-long term 30% reg occups, min 1 space per res unit

How much parking must be for carpools?

5%

Reduced Parking Footprint requirements?

20% reduction of base ratio if no density/quality transit points


40% reduction if density/quality transit points earned

Green Vehicle

45+ score on ACEEE annual vehicle rating guide

Green vehicle requirement for green vehicle designated parking?

5% designated parking for green vehicles or 20% discount for green vehicles

How many parking spaces must have alternative energy charging?

2%

School adaptation for green vehicles in regards to buses?

NO and Particulate emissions limits for buses

Warehouse adaptation for green vehicles (2 options)

1) purchase an EV fuel yard tractor


2) reduce truck idling by providing electrical connections for 50% of loading dock doors

SS Prereq Constr Act Pollution Prev requires (3)?

2012 EPA Contruction General Permit meeting erosion and sedimentation control (ESC report), stabilization, and pollution prevention

Erosion and Sedimentation Control Plan includes what?

natural buffers and perimeter controls, controlling sediment pile discharges, minimizing dust, preserving topsoil

NPDES is?

National Pollutant Discharge Eliminiation System, works to regulate stormwater discharge from construction sites

What kind of structural controls can help prevent erosion/sedimentation? (5)

sediment trap, earth dike, silt fencing, terraces, rip rap

Environmental Site Assessment Prereq must only be met for what two types of bldgs?

Schools and healthcare

What is the Environmental Site Assessment Prereq?

Phase 1 site assessment. If necessary, phase 2 site assessment as well.



Expires partially at 180 days and fully at 1 year

For Protect/Restore Habitat, there are two options: 1) On Site Restoration (Greenfield and Prev Dev) and 2) Financial Support. What is the requirements for both?

1) Greenfield: 40% preserve


Prev Dev: restore 30%


2) 40 cents/SF of total site area to a land trust (Land Trust Alliance)

For soil restoration, what categories must be met? (5)

Organic Matter, Compaction, Infiltration Rates, Soil Biology function or Soil Chemical characteristics

Open Space requirement and points?

1 point. 30% of site to be open space, 25% of open space to be vegetated

Rainwater Mgmt - Requirements for both options? and Points

Opt 1) Percentile of Rainfall events (over 30 years)


95%=2 pts, 98%=3 pts


Opt 2) Natural Land Cover Conditions


Retain same volume of run off as pre-dev natural hydrologies

How is rainfall events percentiles determined? (the Reference)

EPA Stormwater Mrmt and National Climatic Data Center Website

What helps with rainwater mgmt? (5)

Swales, rain gardens, green roofs, permanent pavement, rain barrels/cisterns

Heat Island Reduction: nonroof measures including material SRs/SRIs

Plants, shade from alt energy sources, open grid paving (50% unbound)


Materials of SRI of 0.33 or 3 year SR of 0.28

Heat Island Reduction: Roof SRI requirements

Low Slope (<2:12) - 82 SRI and 64 3 year


High Slope - 39 SRI or 32 3 year

Heat Island Reduction: Parking Under Cover Reqs? (% of spaces covered and Cover reqs)

Min of 75% spaces under cover not including bicycles.


Cover must have 39 SRI or 32 3 year SRI, veg roof, or be covered in energy recovery systems

What are the two options for Heat Island Reduction (simple)?

Nonroof/Roof measures, Parking under cover

What does BUG stand for?

Backlight, Uplight, Glare

Light Pollution Reduction credit requirements?

Follow BUG when choosing lighting.

For schools using Site Master Plan credit, 4 out of 6 credits must be achieved. What are these 6 credits?

High Priority Site, Open Space, Heat Island, Protect/Restore Habitat, Rainwater Mgmt, and Light Pollution Reduction

For Places of Respite credit, what are the space requirements? How much indoor space is allowed to count?

5% of building area for patients/visitors


2% of building area for staff


30% of area can be indoors

Direct Exterior Access (healthcare) requires how much SF/patient? How many points?

5 SF/patient for 75% of patients 4+hours stay


1 point

Joint Use of Facilities credit requirements (3 options) and points?

1 point


Opt 1) Allow Public Access to bldg space (3+ facilities)


Opt 2) Share Bldg Space (2 dedicated use spaces)


Opt 3) Off campus services for Students


-2/6: Auditorium gym, cafeteria, pool, classroom, or athletic fields

Outdoor Water Use Reduction PREREQ requirements? and the credit?

Rrereq = 30% reduction


Credit = 50%


using EPA WaterSense Budget Tool


How long can temporary irrigation be used for Outdoor Water Use reduction?

2 years

What is the difference between strategies you can use for outdoor water reduction pre-req and the credit?

Prereq is done via plants and efficient irrigation (how much water is consumed in general)


Credit can be achieved by how the water is obtained (e.g. alternative water sources)

How many points for Outdoor Water Use Reduction? (Both no irrig. and reduced irrig.)

2 points for none, and 1 for reduced (50%)

Indoor Water Use Reduction Prereq vs credit (% and strategy difference)

Prereq=20% (efficiency)


Credit=25-50% +1pt/5% (efficiency and alt water sources)


Baselines for toilets, urinals, public BR faucet, private BR faucet, kitchen faucet, and shower head

Toilet = 1.6 gpf


Urinal = 1 gpf


Public BR Faucet = 0.5 gpm


private BR faucet = 2.2 gpm


Kitchen faucet = 2.2 gpm


showerhead = 2.5 gpm

What can be used for all applicances to achieve indoor water use reduction prereq WITHOUT calculations?

WaterSense

Appliance requirements for indoor water use reduction:


Residence clothes washer


Ice Machine


Residence dishwasher


Community dishwasher


Prerinse Spray Valve

Energy Star = res clothes washer, ice machine, res dishwasher


CEE Tier 3A = Comm dishwasher


Prerinse Spray Valve < 1.3 gpm

What is the Building Level Water Metering prereq requirement?

instlal water meters to record TOTAL potable water use for bldg/grounds

Bldg Level Water Metering credit requires measuring what? (6)

Measure 2 subsystems: Irrigation, indoor plumbing, domestic HW, Boilers, Reclaimed water, or other process water

Cooling Tower Water Use credit requirement and points?

1 point


Potable water analysis to optimize CT cycles

What must be measured as part of the potable water analysis of a Cooling Tower? (5)

CA, Alkalinity, SiO2, Cl, Conductivity

Cooling tower water is lost due to...?(3)

Evaporation, blowdown, and drift

Fundamental Cx and Verif Prereq requires what? (4)

OPR, BOD, Cx Plan, O&M Plan

When should Cx Agent be designated by?

Before end of design phase

EA Prereq Min Energy Perf, what are the 3 options?

1) Whole bldg energy simulation


2) ASHRAE 50% Energy Design Guide


3) Advcd Bldgs Core Perf. Guide

For EA energy pre req, what are the % improvement requirements in energy for new construction, major renovation, and core&shell?

New const=5%


Major Renov=3%


Core/shell=2%

ASHRAE 50% Energy Design Guide is applicable for what 4 types of bldgs?

small office (<100k SF), Med/Lg Retail, K-12 schools, and Large Hospitals (>100k)

What is the size limit for using Advanced Bldgs Core Performance Guide? And what credit is this guide used for?

<100k SF, used for energy performance calc

Up to how many points can be earned for new construction for optimize energy perf credit? What is the range of percentages for points?

18 points, 6-50%

What is the requirement for fundamental refrigerant mgmt prereq for new bldgs and for renovations?

zero CFCs for new bldgs


renovs must have a scheduled phase out, but equip <0.5lbs of refrigerant are exempt

What is the requirements for EA Bldg Level Energy Metering credit? (2)

Install meters to measure total bldg energy usage


Share data for 5 years at 1 month or smaller intervals

What are the points and the requirements for Advcd Energy Metering?(2)

1 point


1) Meter whole bldg systems s.a. gas, electricity, propane, ch w, on site renewables


2) Meter any individual uses that are 10% of total building consumption s.a. HVAC, lighting, elevators

What are the requirements and points for Demand Response credit?

2 points


Opt 1) IF DR program available, 1 year enrollment + 10% of estimated peak demand reduction/rescheduling


Opt 2) No DR available, design building to participate in future program

What are the renewable energy systems allowed? (7)

PV, Wind, Solar Thermal, Geothermal, Biofuel Based, Hydroelectric, Wave/Tidal

What percentages earn what points for Renewable Energy Production? (3)

1%=1 pt


5%=2 pt


10%=3pt



Renewable energy cost reduction

What biofuels are ineligible for renewable energy credit? (4)

Burning trash, forest bio mass (except mill residue), painted wood, preserved wood

Green Power and Carbon Offsets credit requirement for how many points?

5 year contract for 50% (1 pt) or 100% (2 pts) of bldg energy for green power or carbon offsets with renewable energy provider

What is Green-E?

Used in purchase of green power/REC certified for Green Power/Carbon Offsets credit

For MR Prereq Storage and Collection of Recyclables, what materials need to be stored (5)? And what also needs to be stored (2/3)?

Mixed paper, cardboard, glass, plastics, metals.


2/3: Batteries, Hg Lamps, or electronic waste

What is the adaptation for MR Prereq Storage and Collection of Recyclables for retail?

Retail must do a waste stream audit and find top 5 waste streams. Must provide dedicated collection areas for top 4 waste streams.

How many materials must be diverted from landfills for the Construction and Demo Waste Mgmt Plan?

5

Construction and Demolition Waste Mgmt Credit, what are the points and requirements for the 'diversion' of material streams option?

50% diversion of 3 material streams = 1 pt


75% diversion of 4 materials streams = 2 pt

Construction and Demolition Waste Mgmt Credit, what are the points and requirements for the 'reduction' of material streams option?

2 points


Max waste of 2.5 lb/SF

What is excluded from waste mgmt plan? (3)

excavated soil, land-clearing debris, and alternative daily cover

What are the options for Bldg Life Cycle Impact Reduction credit? (4)

Historic Bldg Reuse


Renov of abandoned or blighted bldg


Bldg and Material Reuse


LCA Whole Bldg

What is the requirement for the renovation of a blighted or abandoned bldg?

Maintain 50% of SA and 25% of SA may be excluded due to damage.

Building and Material Reuse requires what %s of msmt for points?

25-75% of SURFACE AREA resused, 2-4 points

What does Bldg and Material Reuse NOT include for Bldg Life Cycle Impact Reduction? (2)

Windows, hazardous items (s.a. lead painted walls)

If using LCA option for Bldg Life Cycle Impact Reduction Credit, what is the percent reduction required in how many impact categories?

10% reduction in 3 impact categories

What are the impact categories for LCA? (6)

GWP, ODP, acidification, Eutrophication, O zone, depletion of non-renewables

What is the assumed service life of a bldg in the LCA?

60 years

PCR?

Product Category Rule

For Bldg Prop Optimization and Disclosure credit, how many EPDs are required from how many manufacturers?

20 EPDs from 5 different manufacturers

Point difference between an product specific EPD, Industry-wide generic EPD, and product specific declaration?

1/4= product specific declaration


1/2=industry-wide generic EPD


1= product specific EPD

What mile radius must a product be extracted/manufactured for it to count for double the points?

100 miles

CSR?

Corporate Sustainability Report

For Sourcing of Raw Materials, how many product reports are needed from how many manufs?

20 reports from 5 manufacturers

What are the 4 frameworks used for raw material sourcing reports?

GRI Sustainability Report, OECD Guidelines, UN Global Impact, ISO 26000

EPR

Extended Producer Responbility

Take Back program for EPR?

Manufacturer can take back product at end of life to reuse it in a closed-loop recycling process

For Sourcing of Raw Materials credit using the leadership extraction practices, what is the requirement?

25% of total products by cost that show responsible extraction and sustainable process.

What can manufacturers do that works towards Sourcing of Raw Materials, leadership extraction option? (4) and the percent worth

EPR certified/takeback program - 50% of cost


FSC wood - 100% of cost


Biobased Material - 100%


Recycled Content 100% for post consumer and 50% for pre consumer


Reuse - 100%

What standard must Biobased Material meet?

Sustainable Agricultural Standard

What can be used for Material Ingredient Reporting? (3)

Supply manufacturer inventory, HPD, Cradle-to-Cradle certification

Material Ingredient Reporting option vs Material Ingredient Optimization option?

Reporting - 20 products from 5 manufs


Optimization - 25% by cost of material ingredients meet certain standards (3)

25% by cost of material ingredients must meet what standards? (3)

GreenScreen V1.2 Benchmark


Cradle-to-Cradle


REACH Optimization

PBT?

persstent bioaccumulative and toxic

What are the 4 restricted PBTs?

Lead, Mercury, Cadmium, Copper

What is the minimal chemical content for medical furnishings (amount) and what are the 4 out 5 groups it must apply to?

100 ppm


Formaldehyde, added anti-microbial treatments, heavy metals, chromium, and stain/nonstick treatments

For medical furnishings, how much must apply to chemical content requirements for credit? (1 and 2 points)

1 pt = 30% by cost


2 pt = 40% by cost

What are the 7 strategies you can use for Design for Flexibility credit?

Interstitial space, program for soft space, shell space, horizontal expansion capacity, future parking designation, demountable partitions, movable/modular casework

What standard is used for mech vent in IAQ Performance credit?

ASHRAE 62.1 2010

What standard is used for natural ventilation IAQ?

CISBE App Manual for Naturally Ventilated bldgs

What is ASHRAE 170.8?

Operating Rooms

What are the requirements for Min IAQ performance Prereq? (4)

Follow ASHRAE 62.1 -2010


CO sensors in Residences


Glass doors on fireplaces


Monitor at least 1 of following with 10% range from setpoint and alarm at 15%: EA, Nat Vent Openings, CO2 levels


What are the available enhanced IAQ strategies for mechanical ventilation? (3) (all must comply)

Entryway systems, Interior cross contamination prevention, and filtration

What is the entryway systems requirement for IAQ?

install 10' long entryway with mats, grilles, grates in floor at all regular entrances

What is the internal cross contamination requirements for IAQ? (4)

negative pressure, self closing doors, 0.5 cfm/sf exhaust, deck-to-deck partitions of contamination spaces

What is the filtration requirement?

MERV 13 filters for OA

What are the available enhanced IAQ strategies for natural ventilation? (2) (all must comply)

Entryway systems and design calcs

Natural Ventilation calculations must meet what?

CISBE AM10

For Additional Enhanced IAQ Strategies, what is exterior contamination prevention requirement?

Use CFD or other to show OAI contamination levels are low enough.

For Additional Enhanced IAQ Strategies, what is Increased Ventilation requirement?

Increase 30% over prereq

For Additional Enhanced IAQ Strategies, what is CO2 monitoring requirement? (2)

3-6' above floor, Tied into BMS or alarm at 10% exceedance

What are the requirements for Env Tobacco Smoke Control prereq (non residential)? (3)

No smoking inside, no smoking within 25' of entries/OAI, signs of smoking policy 10' of all bldg entryways

What is the smoking inside exception for residential?

Smoking allowed inside in compartamentalized spaces: weather stopping and separate ventilation/exhaust systems

What 7 material categories are included in Low Emitting Materials?

Interior paints/coatings


Interior adhesives


Flooring


Composite Wood


Ceilings/walls/accoustic insulation


Furniture


Exterior Applied Products (schools/healthcare)

What are the reqs for Construction IAQ Mgmt plan? (5)

MERV 8 during construction, protect absorbative materials to prevent mold, no smoking inside bldg, sealed ductwork, high VOC materials stored outside

What is the flushout requirement if done before occupancy?

14000 ft3 OA/SF at 60-80F and <60% humidity

What is the flushout requirement if partially done after occupancy?

3500 CF/SF before occup., 0.30 OA/SF until 14000 CF met

What are the two requirements for Thermal Comfort credit?

Meet ASHRAE 55 -2010


Thermal control for 50% of individuals and 100% of shared spaces

What are the 6 factors for thermal comfort?

Temperature, RH, fpm, clothing factor, thermal radiation, and occupant activity

For lighting control option under Interior Lighting Credit, what are the two requirements?

90% of occupants must have task lighting and 100% of shared spaces


Lighting controls must have off, mid, and on levels

SDA?

Spatial Daylight Autonomy - % of floor space where lighting can be met for 50% of hours

ASE

Annual Sunlight Exposure - % of work hours that lighting exceeds a certain threshold

DAM

Daylight Autonomy Max - % of work hours that daylighting exceeds design

What is the percentage of areas that must have direct line of site to views?

75%

What qualifies as line of site view? (2/4)

Multiple lines of sight in difference direction (90d)


Views that include 2/3: flora/fauna, movement, or objects 25'+ from exterior


Unobstructed views located within 3x head height


View Factor of 3+

What is the max background noise for schools from HVAC?

40 dBa