Commands for pitching 135 ladder |
Standby to slip 135 ladder Release Slip - well Ready, brace, lift 3 and 4 site the heel Under run Ground props Prepare to extend Extend - well Pawls engaged (no 2+4) Head in Ladder pitched, get to work |
|
Making up 135 |
Head out Extend to lower Lower Ladder to vertical Walk in Clear behind Under run Ready, brace, lift Well - ready, brace, lower (6m from rear of appliance) Ready, brace, lift Standby to launch Launch House Ladder secure |
|
Ladder security checks |
No 1 visually checks yellow strap is secured in position Open hands push red ladder securing handles forward to ensure they are fully engaged Visually check primary and secondary latches Pulls back on gantry handlebar |
|
Pitch checks |
3-5 rounds above sill Within 150mm from the frame Bottom round in sill parralel to sill |
|
Safety checks |
No 1 ensures all pawls are engaged on the round Ensure clearance between ground and yellow carrying handles Ensure Jack pads are flat on the ground |
|
Safety considerations |
Ladder must be slipped and launched in-line with gantry Slip and launch at walking pace with crew members monitoring ladders direction of travel If ladder becomes difficult to launch or comes to a complete halt on the beam stop and correct the angle of the ladder before continuing |