• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/11

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

11 Cards in this Set

  • Front
  • Back

Where are the fire water / cooling water cross tie fittings located?

P2 TA's office

What is the 100 / 200 supervisory air pressure range?

25 - 28 Oz.

What is the 100 / 200 sprinkler system water supply range?

85 - 120 psi

What means is there to manually trip the 300 foam system?

P-2 C/R switch



Local trip switch

What must be done prior to resetting the 100 / 200 snuffing steam valve?

It must be reset in the P2 C/R.

Explain the importance of the steam trap on the snuffing steam systems?

To remove water from the line which would damage instruments and the Heb.

What should be done prior to isolating a block fire system?

Notify Es&s. Does not apply to snuffing steam.

What is co2 used for? Should you continue to run if it is used?

Co2 is used when snuffing steam doesn't put out the fire. If co2 is used the turbine should be shut down.

What are the probable causes of a fire in the hot end bearing tunnel?

Low vacuum allowing oil to leak out of seals.



Oil leak from tubing or instruments.



300 - Plugging of the hot end bearing vent line.

What other than a fire could cause the snuffing steam valve to trip?

Loss of a lube oil evactor



Low LO Reservoir vacuum

What should be done if the tattle tale is leaking?

Contact Es&s, the repair would be done by us through a work request however they need to be involved.