Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
10 Cards in this Set
- Front
- Back
Cost Variance (CV) |
CV = EV - AC EV: earned value AC: actual cost Positive (>0) is good Negative (<0) is bad Indicates if project is over/under budget |
|
Schedule Variance (SV) |
SV = EV - PV EV: earned value PV: planned value Positive (>0) is good Negative (<0) is bad Indicates if project is on track time wise |
|
Cost Performance Index (CPI)
|
CPI = EV/AC EV: earned value AC: actual cost CPI > 1 is good CPI < 1 is bad |
|
Schedule Performance Index (SPI) |
SPI = EV/PV EV: earned value PV: planned value SPI > 1 is good SPI < 1 is bad |
|
Estimate To Completion (ETC) |
ETC = BAC - EV BAC: budget at completion EV: earned value How much more money needs to be spent to complete project |
|
Estimate At Completion (EAC) [OPTIMISTIC] |
EAC = AC + (BAC - EV) AC: actual cost BAC: budget at completion EV: earned value |
|
Estimate At Completion (EAC) [SIMPLE FORECASTING] |
EAC = BAC/CPI BAC: budget at completion CPI: cost performance index |
|
Estimate At Completion (EAC) [CRITICAL RATIO FORECASTING / PESSIMISTIC] |
EAC = AC + (ETC/CR) AC: actual cost ETC: estimate to completion CR: critical ratio |
|
Critical Ratio (CR) |
CR = CPI x SPI CPI: cost performance index SPI: schedule performance index |
|
To-Complete Performance Index (TCPI) |
TCPI = (BAC - EV) / (BAC - AC) TCPI = work remaining / funds remaining |