who is S-3
|
operations officer
|
|
who is responsible to make sure that necessary sources are available on the project site on the day the wor is to be performed?
|
the crew leader
|
|
who is the S3A
|
the assistant operations officer
|
|
Who is S3C
|
the operations chief
|
|
when does planning for construction tasking begins?
|
approximatley 10 months before deployment when the battalion recieves the tentative tasking message.
|
|
how is the entire history of each NCF project documented, from the initial planning phase through the execution phase to the closeout phase?
|
in a nine-folder project package called the standard NCF project package outline
|
|
what is contained in file 1 of standard NCF project package outline
|
general information file
|
|
what is contained in file 2
|
correspondence file
|
|
what is contained in file 3
|
activity file
|
|
what is contained in file 4
|
network file
|
|
what is contained in file 5
|
material file
|
|
what is contained in file 6
|
quality control file
|
|
what is contained in file 7
|
safety/environmental file
|
|
what is contained in file 8
|
plans file
|
|
what is contained in file 9
|
specification file
|
|
what is the first project planning milestone
|
designating crew leaders and planning team.
|
|
what is the last project planning milestone?
|
preparing the project briefing.
|
|
what is of paramount importance in identifying long lead-time items for realistic schedules
|
yo must take in account anticipated material delivery dates
|
|
where are all required resources listed
|
on the CAS sheets.
|
|
what is the purpose of the master ativity listing
|
to make clear to all personnel involved in the planning process exactly what work is included in each master activity
|
|
what is a good guide for developing the construction activites?
|
the work element checklist in appendix A to the NAVFAC P-405, Seabee planner's and estimator's handbook.
|
|
what is listed in the P-405 to aid in seabee man-day estimates?
|
how many man-hours it takes to do one unit of work and the size of the unit required.
|
|
hwo are man-day estimates and durations calculated
|
quantity of work divided by the unit size and multiplied by the man-hours required to do one unit. you then divide by 8 man hour per man-day and multiply by a delay factor(DF)
|
|
what is the intent of a production efficiency factor?
|
to adjust for factors that will make you more or less productive than the average seabee
|
|
what production factor is assigned for each element?
|
between 25(low production) and 100(high production).
|
|
What is concidered the average production factor
|
67
|
|
what is the formula for determing the mand-day capability(MC) for the main body and each detail
|
MC=DL X WD X ME X AF use DL to represent the number of direct labor assigned; WD for the number of available workdays; ME for the length of the workday divided by 8 (9/8=1.125); and AF is the availabilty factor.
|
|
how is each construction activity represented in a logic diagram
|
by an activity block
|
|
what is the first step in determinging the basic schedule
|
doing a forward pass which gives yo the total duration of your project
|
|
what are lag times
|
manditory wait times between activities
|
|
where do you take information to make a level II barchart?
|
From the information gained from the level III
|
|
what is indicated by the vertical lines on the level III barchart?
|
th separate the weeks
|
|
what is indicated by horizontal lines on the level III barchart?
|
To separate the master activities
|
|
where are the master activities listed on a level II barchart?
|
in a column on the left
|
|
what should be highlighted in red on level III barchart?
|
the critical path
|
|
what should be highlighted in yellow on a level III barchart?
|
the daily status
|
|
what is productive labor?
|
man-day expended that directlycontrubute to the accomplishment of the battalion mission
|
|
what is direct labor
|
all man-days expended directly on assigned construction activity, either in the field or in the shop and includes any labor that contrubutes directly to the completion of the project
|
|
what is indirect labor
|
man-days expended to support construction operations, but that doesn't produce an end product in itself.
|
|
what is overhead labor?
|
man-days expended that must be performed regardless of the assigned mission.
|
|
how many man-days remaining if a cnostruction activity with an original estimate of 20 man-days is 25% complete
|
15 man-days remaining (there are 15 man-days remaining because 75 percent of the work is left to be done and 75x20/100)
|
|
who enters any field chanfges in red on the red-line drawings by entering all changes and comparing them with the drawings held in the operations department?
|
the crew leader
|
|
what is the purpose of the hard card checklist for concrete or asphalt?
|
to ensure the site of the placement has been adequately prepared
|
|
when are the hard-card checklist for concrete or asphalt prepared?
|
must be completed 24 hours before placement of materials.
|
|
what materials must be reflected in the BMs?
|
EVERYTHING needed to complete the project
|
|
what form is used to requisition all material from MLO
|
1250-1
|
|
what lead time is required for normal material requisitioned from CONUS?
|
at least 60 days
|
|
what lead time is required for long lead material requisitioned from CONUS?
|
at least 120 days
|
|
how is excess material disposed when a job is completed
|
offered to the customer
|
|
what happens to excess material a customer don't wants?
|
stored in MLO for six months.
|
|
how often are tool kit inventories required by the Seabee Supply Manual, except for some large kits?
|
twice a month
|
|
how often must all electrical tools be safety checked and verified to have the right color tape on the cord?
|
monthly
|
|
what is the first thing anyone notices about your jobsite?
|
the general appearance
|
|
what is an aid in explaining the project schedule to a visitor to the jobsite?
|
the level III barchart
|
|
what eight items must mandatory be posted on the jobsite information board?
|
level III bar chart; safety plan/EM385 1-1; quality control plan; construction activity summary sheet; weekly goal; daily safety topics; emergency telephone numbers; and the crew organization/chain of command.
|