• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/10

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

10 Cards in this Set

  • Front
  • Back
Which of the following processes is not part of project integration management?
a. developing the project business case
b. developing the project charter
c. developing the project management plan
d. closing the project or phase
a: developing the project business case
What is the last step in the four-stage planning process for selecting IT projects?
a. IT strategy planning
b. business area analysis
c. mind mapping
d. resource allocation
d: resource allocation
Which of the following is not a best practice for new product development projects?
a. aligning projects and resources with business strategy
b. selecting projects that will take less than two years to provide payback
c. focusing on customer needs in identifying projects
d. assigning project managers to lead projects
b: selecting projects that will take less than two years to provide feedback
A new government law requires an organisation to report data in a new way. Which of the following categories would include a new information system project to provide this data?
a. problem
b. opportunity
c. directive
d. regulation
c: directive
If estimates for total discounted benefits for a project are $120,000 and total discounted costs are $100,000, what is the estimated return on investment (ROI)?
a. $20,000
b. $120,000
c. 20 percent
d. 120 percent
c 20 percent
A ________ is a document that formally recognises the existence of a project and provides direction on the project's objectives and management
Project Integration Management
a. project charter
b. contract
c. business case
d. project management plan
a: project charter
Which of the following items is not normally included in a project charter?
a. the name of the project manager
b. budget information
c. stakeholder signatures
d. a Gantt chart
d: Gantt chart
________ ensures that the descriptions of the project’s products are correct and complete.
a. Configuration management
b. Integrated change control
c. Integration management
d. A change control board
a: Configuration management
Which of the following is not a suggestion for performing integrated change control?
a. use good configuration management
b. minimize change
c. establish a formal change control system
d. view project management as a process of constant communication and negotiation
b: Minimize change
What tool and technique is used for all processes of project integration management?
a. project management software
b. templates
c. expert judgment
d. all of the above
c: expert judgement