• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/63

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

63 Cards in this Set

  • Front
  • Back
What is the management process that guides all DOD aquistion programs?
Defense Acquistion System
What is the systematic approach to choosing the best method of allocating scarce resources to achieve a given objective?
Economic Analysis
Under the Economy Act agreement, what must be done with funds that are unused when the ordering appropriation expires?
Returned to the sender
What document is the broad, time phased, operational goals, and a description of the required capabilities to address a specific gap?
Initial Capabilities Document
The analysis of the Initial Capabilities Document address what?
Material and non-material solutions.
The planning of O&S should begin prior to the program initiation and shall be documented where?
Life Cycle Support Plan
What acquisition is achieved through the Incremental Development process and requires collaboration among the warfighter?
Evolutionary
What is the formula for discounting?
PVF = 1/(1+d)^n
When is economic analysis required?
>$1M
Correlation Coefficient Measures what?
degree of relationship between two or more variables
The middle value in a list of number that divides arrayed sample of data in half?
median
What are some of the CAIV factors?
1) Manage risks
2)Set realistic but aggressive cost objectives
3) Motivate Government and industry managers to achieve program objectives
4) Not an open system
Program Acquistion Unit Cost (PACU) equals?
total cost for development, procurement, and military construction divided by # fully configured end items
Acquisition Procurement Cost Unit (APCU) equals?
total funds programmed to be available for obligation for procurement divided by # fully configured end items
What is a timed-phased schedule that serves as a tool for time phasing work and assessing techincal performance?
Integrated Master Schedule
What are the 3 linking factors critical to the sucess of any EVMS?
Cost
Schedule
Performance
What estimate is known as estimating the life cycle of his/her acquistion program?
Program Office Estimate
What estimate is done by the Component Analysis Agency?
Componenet cost Estimate
What are the key costs reflected in the Economic Analysis?
Present Value
What is the primary basis of an EA?
the comparision of estimated costs against anticpated benefits
All cost and benefits are adjusted to ______by using given discount factors to account for the time vlaue of money?
Present Value
What is a mean of translating resource requirements associated with programs, projects, and processes, into estimated dollars?
Cost Estimating
What approach is based on direct comparision with historical information of similar existing activities, systems, or components?
Analogy approach
What approach uses actual costs contracted for or actually incurred on the same system during an earlier period?
Actual approach
What is the result of actual reduction of an approved program if the benefits occurs during the POM period?
Cost Savings
What is the reduction or elimination of some future resources requirement. If a purchase of certain hardware has not been included in an approved program but the preferred alternative does not require its purchase?
Cost avoidance
At what level is sunk costs provided in?
Cost element level
Estimates prepare in constant dollars_____ show the changing spending power of the dollar over time
do not
NPV equals
total PV benefits minus total PV costs
The break even point or payback does not consider the time value of money?
True
What is the most commonly used decision making when projects are high risk and its is desirable to recover investment cost quickly?
Break Even analysis
Which type of contract does the Government bears significant risks?
Cost re-imbursement contract
Which contracts provides for a firm price or in appropriate cases, an adjustable contract?
Fixed Price Contract
What is the comparison of actual performance against an established baseline plan.
Contractor Performance measurement
What is the monthly report prepared by the contractor which assess his performance according to his planned cost and schedule?
Contract Performance Report
What is an integrated tool that relates technical performance to its associated cost and schedule, measures the work progress in objectible terms, and states the value of the work completed in dollars?
EVM
Which type of contract does the Government bears significant risks?
Cost re-imbursement contract
Which contracts provides for a firm price or in appropriate cases, an adjustable contract?
Fixed Price Contract
What is the comparison of actual performance against an established baseline plan.
Contractor Performance measurement
What is the monthly report prepared by the contractor which assess his performance according to his planned cost and schedule?
Contract Performance Report

Budgeted of work Performed (BCWP) minus the Actual Cost of Work Performed?
Cost Variance
BCWP minus BCWS
Schedule Variance
GANTT
Are better at displaying the schedule and resources used in a project.
1. lay out the project in order
2. Allows the manager to assess how long a period should take
3. Manage dependencies between tasks
4. Determine task and needed resources
PERT
1. Identify activities and milestones
2. Determine the proper sequence of the activities
3. Construct a network diagram
4. Estimate the time required for activities
What is the three part test of a necessary expense doctrine?
1. The expenditure must bear logical relationship to the appropriation
2. must not be prohibited by law
3. must not be otherwise provided for.
What are the three processes in the DoD that must work together to deliver the capabilities required by the warfighters
capabilities evaluation process; the acquisition process; and the PPBE
What system is based on a series of top-down analysis ultamately derived from formal strategic-level guidance, including the NSS, NMS, and the QDR?
JCIDS
What are the two important decisions made at milestone B in the EMD?
1. The quantity of the low rate initiation production
2. whether advance procurement will be requested when the system enters into production
During this phase, the program also achieves its Fully Operational Capability, which occurs when the total quanity of operational items is deployed to the warfighter user?
Operations and Support
These are intiatives proposed by USD AT&L to reduce acquisition costs and streamline the process in concert with the effort by SECDEF to reduce costs in the DOD?
Acquistion Policy Objectives
Where are decisions documented in Milestone C once the MDA makes a decision to commit DOD to production?
Acquisition Decision Memorandum
What sets forth mandatory procedures for all defense technology projects and acquisition programs?
Operation of the DoD Acquisition System. 5000.02
Title 10, U.S. Code, designated the highest level Defense acquisition program as what?
Major Defense Acquisition Program
Who defines the Major Automated Information Systems?
Assistant Secretary of Defense for Networks and Information Integration.
Who does the CIO delegates milestone decisions authority for ACAT IAC?
Component Acquisiton Executive (CAE) or Component CIO
What are the three life cycle cost estimate for ACAT 1 programs?
Program Office Estimate, Component Cost Estimate, and Independent Cost Estimate.
An economic analysis is intially prepare in constant base year dollars and presents a differential cost display by year over the project's expected economic life beginning with?
the budget first year for which investment funds are needed for any alternative, and ending when the alternative with the greatest economic life ceases to produce benefits.
What cost are past expenditures from prior fiscal year?
Sunk Cost
What dollars are expressed in the value of the year in which a cost is expected to occur?
Current dollars
What is the approach that includes all elements of the system from cradle to grave.
total system approach
What are the 3 ways to look at LCC
WBS, APN Category, and Cost category
What is the key document used by all analysis performing life cycle cost estimate?
Cost Analysis Requirment Document