• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/14

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

14 Cards in this Set

  • Front
  • Back

Sampling by this method is required when tests are to be made to determine _______ with specification requirements

compliance

This method covers sampling from four types of mixers which are

Open top, revolving drum, paving mixer, stationary mixer

The maximum allowable time between obtaining the first and final portions of a composite sample is _____ minutes

15 minutes

Portions of a composite sample shall be thoroughly remixed before beginning tests on the sample. T or F?

True

The maximum elapsed time allowed between obtaining the final portion of the composite sample and beginning the tests for slump, temperature and air content is ______ minutes

5 minutes

The molding of strength test specimens shall begin within ______ minutes after fabricating the composite same

15 minutes

The concrete sample must be protected from contamination and

evaporation, sun and wind

the minimum size sample for making strength test specimens is

28L or 1ft^3

When sampling from a stationary mixer, the batch must be sampled at _____ or more regularly spaced intervals during discharge of the middle portion of the batch

2

The composite sample for a paving mixer must represent a minimum of _____ different portions of the batch of concrete taken from the pile after discharge

5

When sampling from a revolving drum truck mixer, concrete must be sampled at a minimum of ______ regularly spaced intervals during discharge of the middle portion of the batch

2

Concrete samples from a truck mixer must be obtained before any water or admixtures are added to the mixer at the job site. T or F

False

The composite sample from a truck mixer must be obtained from the _____ portion of the batch.

Middle

When the concrete contains aggregates larger than that permitted for a particular test method, the sample of concrete must be ____ ______ before making the test

Wet sieved