who is the primary source of info about the construction jobsite
|
construction supervisor
|
|
what is used to record conversations, technical problems/solutions and safety reccommendations
|
daily job diary
|
|
when should the daily job diary be completed
|
once in the morning and once in the afternoon
|
|
all non-specific items are recorded and stored by
|
alphabetical order
|
|
what would a daily activity be stored by
|
date
|
|
what would a payment be stored by
|
date
|
|
what would a wage rate be stored by
|
date
|
|
what would a construction report be sorted by
|
date
|
|
what would a visitors log be stored by
|
date
|
|
what would a submittal log be stored by
|
date
|
|
how often should weather be recorded in the job diary
|
once in the morning and once in the afternoon
|
|
in the job diary, conversations should be logged in by
|
the time of the conversation
|
|
what should daily job diaries be kept in
|
a hard notebook like a surveryors book
|
|
if a page is to be voided in the job diary what should you do
|
put an X through it, dont tear it out
|
|
what should be done with daily reports on weekends and days that no work takes place
|
place the date on the page followed by the words "no work"
|
|
should telephone calls made and received be stored in the daily log
|
yes
|
|
where should you sign your name title, and date on the daily job diary
|
the very next line after the last entry
|
|
what is the report sent to the contractors home office describing the progress at the jobsite each day
|
daily construction report
|
|
what includes:
number of workers present, weather conditions, construction activited completed and in progress, quantitites placed, materials delivered, construction equipment, visitors, and meetings |
daily construction report`
|
|
all pages in the job diary must be numbered _____________
|
consecutively
|
|
all items in the job diary must be made in _______ by the person who is ______ to the event
|
writing
closest |
|
does the daily construction report include weather twice a day?
|
yes
|
|
materials and quantites present are included in the
|
daily construction report
|
|
equipment at the site is included in the
|
daily construction report
|
|
conversations are included in the
|
daily job diary
|
|
safety reccommendations are in the
|
daily job diary
|
|
meetings that took place are in the
|
daily construction report
|
|
work visa employees must complete the ___________ ___ ___ form
|
immigration act I-9
|
|
the immigration act I-9 must be completed within __ days of employment
|
3
|
|
what form must all employees complete
|
W-4
|
|
the employee exemption form is also known as
|
the W-4
|
|
the W-4 must be completed...
|
before starting work
|
|
what informs the accounting dept of the number of hours worked each day
|
daily time card
|
|
what distributes the workhours spent for each person to the construction activites they worked on
|
daily time card
|
|
on large projects, the daily time card is filled out daily by the
|
foreman
|
|
on large projects, who is the time card signed by
|
superintendent
|
|
who collects all of the time cards from the foreman, verifies the work being performed, rate classifications, approves the number of hours worked, and sends the card to the payroll dept
|
superintendent
|
|
who verifies the workhours worked from the time cards
|
payroll
|
|
EWO stands for
|
extra work order
|
|
how often should entries be made for the daily time card
|
twice
|
|
what includes:
equipment hours worked equipment hours idle cost codes |
equipment time card
|
|
are equipment hours idle important and included in the equipment time card
|
yes
|
|
construction reports, job diaries, time cards, equipment status reports, material delivery status reports, and field purchase orders should be filed under division...
section... |
01 -
040 |
|
should construction reports be filed alphabetically or by date
|
date
|
|
should job diaries be filed alphabetically or by date
|
date
|
|
should time cards be filed alphabetically or by date
|
date
|
|
should equip status reports be filed alphabetically or by date
|
date
|
|
should material delivery status reports be filed alphabetically or by date
|
date
|
|
should field PURCHASE orders be filed alphabetically or by date
|
alpha
|
|
permits, prevailing wages, minority hiring procedures and goals should be filed under division 01060 titled
|
regulatory requirements
|
|
change requests, change order proposals, and approved contract change orders should be filed under division 00 section 900 titled
|
modifications
|
|
documents should be filed in the field by
|
CSI numbering system
|
|
within a CSI division and section file, documents should be filed by (3)
|
alphabetical
numerical date |
|
within a file folder, place the ______ on top
|
latest
|
|
within a file folder, notes or working AGENDAS should be placed on the ____ side
|
left
|
|
should time cards be filed alphabetically or by date
|
date
|
|
should equip status reports be filed alphabetically or by date
|
date
|
|
should material delivery status reports be filed alphabetically or by date
|
date
|
|
change order requests, change orders, and extra work orders should be stored by
|
numerically
|
|
permits, prevailing wages, minority hiring procedures and goals should be filed under division 01060 titled
|
regulatory requirements
|
|
change requests, change order proposals, and approved contract change orders should be filed under division 00 section 900 titled
|
modifications
|
|
documents should be filed in the field by
|
CSI numbering system
|
|
within a CSI division and section file, documents should be filed by (3)
|
alphabetical
numerical date |
|
within a file folder, place the ______ on top
|
latest
|
|
within a file folder, notes or working AGENDAS should be placed on the ____ side
|
left
|
|
within a file folder, place the original documents or MINUTES on the _____ side
|
right
|
|
how should alternates be stored
|
numerically
|
|
how should shop drawings and product data sheets be stored stored numerically alphabetically or by date
|
alpha
|
|
in the pre-planning process you determine the labor production and expected production rate ___ _____ in advance
|
one week
|
|
in the pre-planning process, you should identify the pertinent, _____, _________, and ________ needed
|
tools, materials, and equipment
|
|
in the pre-planning process you should outline the safety _______ and a _____ of _______ for the crew
|
hazards and a plan of action
|
|
in the pre-planning process you should outline the ________ for each activity
|
sequence
|
|
in the pre-planning process, you should develop detailed ________ for specific activities
|
sketches
|
|
in the pre-planning process, you should develop a _______ _______ checklist
|
quality control
|
|
what has the greatest impact on the overall project cost
|
field planning (aka pre-planning, or look ahead)
|
|
the field planning look ahead labor section has all activities planned for the next
|
week
|
|
the field planning look ahead labor section has a projected _____ _____ and unit of measure for the next week
|
daily output
|
|
which section of the field planning look ahead includes the planned quantities, crew size distribution, and total workers needed for the next week? (sketches section, technical section, safety section, sequence section, quality section, labor section, materials section, or equipment section)
|
labor
|
|
what are the three sections of the field planning look ahead
|
labor
materials equipment |
|
the field planning look ahead MATERIALS section contains the quantity at the S___, the quantity N_____, and the quantity S________.
|
Site
Needed Shortages |
|
the field planning look ahead MATERIALS section contains the _______ of the materials at the site
|
location
|
|
the field planning look ahead for the technical section contains the overall project S_______, T________ specifications, R_______ standards, I___________ Manuals, the R_____ Handbook, S___ Drawings, and P______ D___ Sheets
|
schedule
technical specs reference standards installation manuals rigger handbook shop drawings product data sheets |
|
OSHA 1926 is the
|
construction safety standards
|
|
American Concrete Institute for Concrete, and Concrete Reinforcing Steel Institute are examples of
|
reference standards
|
|
the daily safety plan should address ________ hazards along with a ____ of action
|
safety hazards
plan of action |
|
the field planning look ahead plan section for SEQUENCE should address the ________ of activities and S_______ steps for each
|
sequence of activities
specific steps for each |
|
the field planning look ahead section for QUALITY should identify the P__________ Expected, A_________ Criteria, and the G____ Conditions
|
performance expected
acceptable criteria given conditions |
|
in the field planning look ahead section for SKETCHES you should _____ each view and state the _____ direction
|
label
polar |
|
in the field planning look ahead section for SKETCHES you should include the _______ dimensions along with the O_-_____ Spacing
|
overall dimensions
on-center spacing |
|
Labor Support activities that must be considered in addition to the work being performed:
U_______ Materials R_-_______ Materials |
Unloading materials
Re-loading Materials |
|
Labor Support activities that must be considered in addition to the work being performed:
P_________ Maintenance S________ Maintenance |
Protective
Scheduled |
|
Labor Support activities that must be considered in addition to the work being performed:
T___ and Inspect |
Test
|
|
Labor Support activities that must be considered in addition to the work being performed:
setup and S______ area |
staging
|
|
Labor Support activities that must be considered in addition to the work being performed:
sequence of E_______ |
erection
|
|
Labor Support activities that must be considered in addition to the work being performed:
T_______ Requirements |
Training
|
|
Labor Support activities that must be considered in addition to the work being performed:
S_____ Activities |
safety
|
|
Labor Support activities that must be considered in addition to the work being performed:
A_____ Tools |
Acquire
|
|
the job diary should be completed by the ____ and ______ of the event
|
hour and minute
|
|
conversations, technical problems/solutions, and safety are content of what
|
job diary
|
|
weather conditions, workers present, construction activities, materials used, construction equipment, visitors to the site, and meetings that took place are all content of the...
|
daily construction report
|
|
should the CONSTRUCTION REPORT be completed daily or twice per day
|
daily
|
|
what natural factor can affect structural steel erection and formwork
|
wind
|
|
what natural factor can affect drywall and painting
|
humidity
|
|
what poster describes the regulations for wage payment and hours of work for all industries and must be posted at the jobsite
|
fair labor standards
|
|
which association negotiates collective bargaining agreements on behalf of its members
|
Associated General Contractors
|