The Shard London Case Study

Improved Essays
The Shard, London
Numerous challenges were encountered while constructing the tallest building in Western Europe’s skyline. Some of them being:
Project Area: The land area on which this 95 storey tower was planned, was much smaller than the area on which any building of similar scale has been built.
Location: The site was sandwiched between one of UK’s busiest stations, London Bridge Station and Guy’s Hospital. Also, the bus station on the doorstep of the site had to remain running. Thus, the project had to operate around the thousands of commuters using these facilities. Moreover, the narrow roads and large amounts of pedestrians made moving materials to and from the site a major challenge.
Existing Facilities: Large Victorian water mains
…show more content…
The soil in the middle of excavation area is cut, leaving others to retain the deflection of diaphragm walls. This allows access to even farthest end without impeding the construction of struts and slabs. The dimension of the channel is determined by the space required by excavator and earth hauler. Also, the remaining soil should suffice the support required by diaphragm walls for deflection control. Thus, part A2 was completed using four vertical excavation stages of construction. Interference between material transportation and earth hauling was resolved by entrances in top slab of underpass and top slab of Part …show more content…
The scope of the project is to construct a six storey building using latest top down construction techniques, and develop all the levels under the basement. Later, a tunnel for the purpose of passage between new building and the store was also added to the scope. The tunnel was planned to be constructed 28m below the ground level into the london clay. The tunnel comprises of 5m connection tunnel along with 7.1m staging area. The construction work within the scope of the Harrods building had to be completed without interfering routine operations of the store. The construction material, plant and equipment had to use 1.5m wide and 2.0m high opening for entry or exit. As the construction was done during store hours noise and vibration was monitored and controlled strictly and most of the operations were done in confined spaces challenging the project in health and safety aspects. Congested roads of london added to the problems, resulting in only one access road (4.0m wide). Working hours for the project were limited. Harrods project faced many more challenges such as scope extended to save 15 weeks of construction time, using 28m long steel columns; accuracy in plan position to be achieved was within 10mm tolerance. All these challenges were overcome by Skanska Cementation 's proprietary CEMLOC™ system which was used to achieve such sensitive

Related Documents

  • Improved Essays

    Due to its high strength Steel is one of the most common materials within the construction industry. The most important properties of steel are density and robustness, good tensile and yield strength, good thermal conductivity and expansion. As well as these important properties, another very important of the stainless steel properties is its resistance to corrode. Steel is often used in the form of beams, columns and plates. Within the construction site steel played a huge part in the development of the project, having several different uses for this…

    • 526 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    The structural slab is specified to reach four-thousand pounds per square inch (psi) after twenty-eight days. The sampled concrete only reached two-thousand nine-hundred psi after twenty-eight days. I was able to understand the importance of the compression test due to the knowledge gained in Construction Materials and Methods II. The project team was discussing ways to remedy the issue of the failed concrete test.…

    • 1309 Words
    • 6 Pages
    Improved Essays
  • Improved Essays

    Bagdad Road Case Study

    • 638 Words
    • 3 Pages

    A substantial part of the rehabilitation focused on Bagdad Road. Bagdad Road is an extremely busy five-lane thoroughfare, which meant that extensive planning and effective traffic control was essential. Multiple other streets were…

    • 638 Words
    • 3 Pages
    Improved Essays
  • Superior Essays

    We interact and experience architecture every day. It is physically impossible not to and because of this, it is incredibly easy to take it for granted and to forget about all the thought and care that was taken to create such huge feats. Worcester’s Union Station is located directly off of highway 190 in Worcester, Massachusetts. Thousands of people pass by it on a daily basis without even realizing that it is something more than a “pretty train station”. Before we begin, let’s answer the question of just why are train stations so grand?…

    • 1449 Words
    • 6 Pages
    Superior Essays
  • Improved Essays

    Construction of the Concrete Roof of the Assembly Hall The University of Illinois- Urbana Champaign Assembly Hall has been the home of the Illini men’s basketball team for over half a century and has been one of the greatest engineering and architectural feats on campus ever since its creation over half a century ago. Beginning on May 25, 1959, construction of the Assembly Hall was carried out by structural engineers Othmar Ammann and Charles Whitney, general contractor Felmley-Dickerson Co., and architect Max Abramovitz, taking almost four years of construction before its completion on May 3, 1963. The Assembly Hall was an engineering wonder when it was first constructed, as it was the first ever concrete dome arena built and remained to be until the construction of the Astrodome in Houston, Texas two years later. Weighing over 4000 tons from only the roof, the concrete dome of the Assembly Hall spans at a 400 feet diameter, 128 feet tall, and built with a folded plate design in about 3.5 inches in thickness.…

    • 480 Words
    • 2 Pages
    Improved Essays
  • Decent Essays

    Severance, John, B. (2000). Skyscrapers: How America Grew Up. New York, NY, Holiday House. Skyscrapers are in the heart of Chicago and New York City.…

    • 204 Words
    • 1 Pages
    Decent Essays
  • Great Essays

    Among the most magnificent towers/skyscrapers around world. Chicago Tribune wanted to build “the most beautiful office building in the world”. In June 1922, Chicago tribune wanted to build an unusual and a style that was never repeated. The tribune tower had to be an iconic building in Chicago. Chicago Tribune were looking for an image over substance, personality over character, Salesman and acquisition over production.…

    • 1453 Words
    • 6 Pages
    Great Essays
  • Improved Essays

    The title is short and descriptive. It indicates the nature of project (high school expansion). It also points out the location of the project, which is Shakopee. However, the location could be expressed with more details such as city or township. A possible alternative could be “Shakopee High School Expansion in City of Shakopee.”…

    • 745 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    I will be writing about some 911 conspiracy theories that explained what really happened on that day, some theories will be convincing but others won’t. I want to start off with how the buildings were not destroyed by the fire. Multiple Chemists and physicists have said that it would be impossible for two planes to bring Down one of the best structurally engineered building in the world. There is lot of Things to back this up. First, there is the jet fuel witch the media and the US Government Sayed that fire which was ighted by jet fuel brought down tower 1 and 2.…

    • 648 Words
    • 3 Pages
    Improved Essays
  • Great Essays

    BTEC Subsidiary Diploma in Construction & the Built Environment Unit 4 – Construction Science and Materials Assignment 1 Human Comfort within Buildings Report Student: Peter McCaughey Teacher: Mrs Keyes Scenario A property developer is converting an old railway station into retail and office accommodation. The client is keen to make the working environment for the staff as comfortable as possible. As a consultant, explain how this can be done by addressing the relevant grading criteria.…

    • 1340 Words
    • 6 Pages
    Great Essays
  • Improved Essays

    Hundreds of ideas have been presented for an undersea tunnel that could possibly run underneath the Atlantic Ocean, where trains would reach speeds of over 5,000 miles per hour and the cities of New York and Paris would connect. The journey between Europe and the United States would take less than an hour. As compared to flight these trains, which would run on a magnetic field along the track inside a vacuum tight tunnel, are supposed to theoretically be faster and use electricity as a fuel source. Though due to issues like injury and cost, the project remains debated. The Trans-Atlantic Tunnel will, in theory, cost a minimum of 12 trillion dollars.…

    • 810 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Brunelleschi's Dome

    • 1007 Words
    • 5 Pages

    In architecture and civil engineering, sustainability plays a main role. All buildings and any construction could be potentially dangerous if they were built or designed in an inappropriate way. All structures and designs have to be safe and stable to prevent the fatal catastrophe of failing construction. The construction of any large objects, such as shopping centers, cathedrals, bridges, and other usually takes a lot of time.…

    • 1007 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    Building Codes Essay

    • 1194 Words
    • 5 Pages

    The process of erecting a structure has always been an immense responsibility as the lives of the public are at stake. Therefore when a building of any size loses…

    • 1194 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    The Earth is currently undergoing environmental problems. The existence of these environmental problems is represented by three factors: increase of population due to the rise of economic activities, decrease of the Earth’s resources, and the destruction of nature. Because of these, architects are searching for sustainable approaches and are promoting sustainable architecture. In the modern day, several infrastructures around the globe are based on. Architecture is more than building and designing.…

    • 748 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    The A2Z Construction will have to understand the timeline of the project and allocate both the estimated and supplementary budget. The project schedule needs to highlight the number of personnel working in the project and their specific jobs and deliverables. The risk factors associated with the building or purchase of new office space will require contingency/mitigations plans just in case the risk[s] occur. 3) The tetrad-off…

    • 1014 Words
    • 5 Pages
    Improved Essays