Suggestive Method Statement

Superior Essays
Design Engineers are expected not just to design for the structural integrity of the building but also to consider the buildability of the structures with regard to health, safety and welfare of everybody in the influence of the structures. This consideration should be done prior to construction work, during construction, while the structure is undergoing maintenance and at normal operation time. Health, safety, and welfare also continue throughout the lifespan of the said structure, that is during the structure removal after its design life. Heath and safety works act 1974 put the onus on all duty holders to eliminate risks as much as is possible. In meeting his health and safety responsibility, an engineer is tasks with adopting the principle …show more content…
One of my alteration work projects required the need for steel works. I had designed a 9metre long steel to support existing partition wall above. In order to limit the lifting weight, I had to design a bolted splice connection; this was located close to the point of contraflexture. This provided ease handling of the material and made installation simpler. My main aim was to reduce the risk of injury due to lifting and reduce the consequence if things ever go wrong. I prepared a suggestive method statement for the lifting operation and advice on the weight of the 762x267x147kg/m to be 371 Kg (2.4m) and 1019 Kg (6.6m long), this is to ensure that competent personnel and equipment are employed in carrying out the lifting work. As the lifting was carried out under a limited space I instructed that the contractor may propose an alternative method of lifting before work could be carried out, if they have a different way of carrying out the work safely. The contractor was requested to supply the capacity of the lifting equipment’s that will be used. I also insisted that adequate lifting chain should be installed to ensure that the beams are stable during the lifting process. I was also concerned that there might be the possibility of working under the suspended beam. I, therefore, instructed the contractor to avoid working under the beam while it was being suspended. I requested that the lifting equipment should be subjected to a factor of safety of 2 -this is to build against all types of failure. I insisted that all equipment should be inspected before use to eliminate failure as a result of the equipment wear and tear, fracture and

Related Documents

  • Improved Essays

    Mr. Chavez stated that the claimant’s job required the claimant to use handheld tools along with small and large equipment such as wheel barrels, forklifts, and Bobcat Skip loaders. He stated that the physical demands of his job were 100 % that consisted of pushing, pulling, lifting, kneeling, and bending while using the handheld tools. Mr. Chavez said the claimant’s job required the claimant to lifting an average 90 pounds to include items such as bags of concrete, roofing materials, mortar, boxes of tiles, sinks, lavatories, doors, and street lights. Also, to these duties of carrying and lifting items, the Claimant’s physical functions requires the Claimant to perform the following physical motions: Kneeling, squatting, bending at the waist and bending at the neck.…

    • 592 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    Truss Bundles Essay

    • 401 Words
    • 2 Pages

    When truss bundles are delivered to the construction site they should never be placed flat on the ground. Instead, they need to be elevated in order to ensure that they do not come in contact with any water or excess moisture. The bundles can be elevated using blocking that is designed to elevate the truss bundles a few feet off the ground. When installed correctly pitch trusses are the features that really pull a home together. If neglected truss bundles can easily damage before the installation process begins.…

    • 401 Words
    • 2 Pages
    Improved Essays
  • Superior Essays

    Hazard Energy and Cintas Corporation Hudson E. Varner Embry-Riddle Aeronautical University Safety 590 Dr. Dawn Martin Abstract The purpose of this paper is to address the energy control program of Cintas Corporation. The company was cited for several safety violations as well as being responsible for an accident leading to the death of an employee. Hence, I was hired as a safety consultant by Cintas Corporation to audit their energy control programs, particularly their lockout/tag out program.…

    • 1793 Words
    • 8 Pages
    Superior Essays
  • Improved Essays

    After making calculations, LeMessurier found that strain on the building’s joints were increased by 40% and then 160% after a strain multiplier was accounted…

    • 722 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    Essay: A Modest Proposal

    • 445 Words
    • 2 Pages

    With so many moving parts to any design project, keeping everyone in- formed is always a top priority. When well executed, it speeds up the process and delivers far better outcomes. Once the design and development phase is complete, the construction documents get under way.…

    • 445 Words
    • 2 Pages
    Improved Essays
  • Improved Essays

    Mr. John H. Smith, President Smith’s Bubble Gum Company, LLC 123 Street Drive, Somewhere, ST 01234 Hearing Conservation Program Proposal Dear Mr. Smith, Thank you for your inquiry about a hearing conservation program for your company. I’ve provided an outline of a hearing conservation program with OSHA guidelines and costs for you to consider. To clarify some of your questions, the abbreviation of dB stands for decibels, which is how acoustic power is measured. Since the human ear can’t hear all the sounds that may be measured by a sound level meter or dosimeter, we will often add weighting, called A-weighting, to relate the results more accurately to the human ear.…

    • 1559 Words
    • 7 Pages
    Improved Essays
  • Improved Essays

    The main concern for the military was to make sure the structures will stand with minimal amount of material being…

    • 959 Words
    • 4 Pages
    Improved Essays
  • Great Essays

    The Chevrolet Corvair case… The task at hand is to outline or demonstrate the ignorance of a professional engineer with regards to the public health and safety and how this in overturn adversely affected or impacted the engineering outcome. Briefly a professional (a profession) by simpler definition is personnel who have a strong foundation in the principals of physics and exercise sound judgment when designing and analyzing such systems (Young, Michael; M&Y consultants and trainers (PTY) Ltd, 2016). There are attributes to which this definition extends (Fleddermann, 2008). Engineers, as other professions, are necessary to the functioning of society. They hold paramount the duties and responsibilities to society and have obligations in performing these duties by doing the right thing (they must act morally in their role as engineers), despite any cost (e.g. losing a job).…

    • 1399 Words
    • 6 Pages
    Great Essays
  • Improved Essays

    The structural elements of the Waddell a-truss bridge include two trusses, which each have compressive and tensile components. The beams in the middle did not carry any immediate load, other than the one attached to the actual bucket. The way the load is placed meant that bars were in tension,…

    • 616 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    The Shard, London Numerous challenges were encountered while constructing the tallest building in Western Europe’s skyline. Some of them being: Project Area: The land area on which this 95 storey tower was planned, was much smaller than the area on which any building of similar scale has been built. Location: The site was sandwiched between one of UK’s busiest stations, London Bridge Station and Guy’s Hospital. Also, the bus station on the doorstep of the site had to remain running.…

    • 1323 Words
    • 5 Pages
    Improved Essays
  • Great Essays

    1.3 Analyse health and safety priorities that are important in the respite care home. In the respite home, there are priorities to be set by Mr John on the health and safety in the workplace. This will reduce the conflicts which may developed in the implementation of the health and safety procedures. The priorities in the health and safety needed in the respite care home include; Falls from height: this is another aspect on health and safety which has to be given priority.…

    • 1300 Words
    • 6 Pages
    Great Essays
  • Great Essays

    Woody 2000 Case Study

    • 1292 Words
    • 6 Pages

    Each aspect during the designing, pre-construction, construction and post construction have made it flexible to modify and absorb any changes. The owners, vendors, regulatory authorities and third-parties are taken into consideration. The internal and external factors have been considered while developing the new project management plan. The design phase is adaptable and time flexible. Proper accountability and allocation has been done.…

    • 1292 Words
    • 6 Pages
    Great Essays
  • Improved Essays

    Mobile Crane Case Study

    • 816 Words
    • 4 Pages

    To meet the needs of Hong Kong people, the government has developed the infrastructure projects and building projects which are still growing vigorously. Almost every project included lifting operations, the lifting appliances and mobile crane becomes the main equipment in the construction project. Lifting appliances and mobile crane are used for raising or lowering a load when suspended. Mobile cranes have three main types such as Crawler-mounted Mobile Crane, Wheeled Telescopic Mobile Crane and Truck-mounted…

    • 816 Words
    • 4 Pages
    Improved Essays
  • Great Essays

    Chapter 1 INTRODUCTION 1.1 Introduction Penang Second Bridge is one of the largest civil engineering projects in Malaysia after the First Penang Bridge. Penang Second Bridge or also known as The Sultan Abdul Halim Muadzam Shah Bridge was a dual carriageway toll bridge in Penang, Malaysia. It was the second bridge which connects the mainland to the island after the first Penang Bridge. Once construction is completed, a maintenance management system plays an important role in maintaining the adequacy and the structure of the bridge so safe and comfortable in use by the general public.…

    • 1086 Words
    • 5 Pages
    Great Essays
  • Great Essays

    While the roof is in tension, the arches that the steel cables are connected to are in compression. Having these opposing components directly joining each other allows for simple stability. Equilibrium is consistent throughout the structure. The internal forces transfer to the arches’ intersections and then to the concrete abutments that are placed beneath the Earth’s surface (2). More cables are included underground and connected to each arch to provide added security for the structure’s stability.…

    • 1106 Words
    • 5 Pages
    Great Essays