Social Security Number Expansion Case Study

Improved Essays
I believe that the two words that best describes Project Management are teamwork and communication. As I read the case study the one constant theme that from this Social Security Number Expansion project was the lack of teamwork and communication that was showed by the various departments involved. For this case it would be easy to put the blame on the Project Manager for not managing the various Functional Business Analysts the way he or she should have but I do not think that was the case. The boss who appointed the Project Manager should have communicated with these Functional Business Analysts that there is a designated Project Manager and that they need to listen and report to him or her. If that happened, then the issue of the Functional …show more content…
When it became obvious to the Project Manager that this SSN change affects more than just the HR area. The Files and data that were being changed were interfaced throughout the company’s systems. This should have been something that was thought about when the project first came to life, not three months into the project. This I blame the Project Manager and he should have taken this into account when planning the risks for the project. It would have prevented the Project Manager from trying to bring representatives from across the company together so that a common solution so late into the projects life. By putting this in the risk portion of the project it would have made the Project Manager notify these other representatives aware that this could have been an issue and the other representatives could have carved out time in their schedules a head of time if this risk came to life. By highlighting this risk at the start of the project, a representative from each department that could have been impacted should be invited to the bi-weekly status meetings. This would have allowed these other departments to see what exactly is going on with the project and how it would affect them. This issue is also something that the Systems Analyst should have worked on with the Project Manager. The Systems Analyst should have been seen this coming and notified the Project Manager that other departments within the company could …show more content…
I believe the flaw in this project was the boss did not communicate who the Project Manager was. If the boss did do that then the Project Manager would have been able to have the power and authority to get everything done in the way that he or she wanted to. The other departments did not see the urgency in this project because they thought that a random Systems Analyst was nagging them to do new work. If all of the solutions that I stated above were put into action this would have been a very successful project and would have been done way ahead of schedule. It all comes down to the fact that the key tools for a successful project are teamwork and communication. That is what failed is specific

Related Documents

  • Improved Essays

    Healthcare Gov Essay

    • 618 Words
    • 3 Pages

    These challenges include, inappropriate design, inadequate resources and time, lack of clearly outlined goals and plans and inadequate cooperation among team members. Individuals tasked with handing the above-mentioned challenges did not communicate and cooperate with each other in an appropriate manner. The situation would have been different if the project had a strong and competent management team. For instance, lack of White House support made the situation worse as those in charge had no one to look up to for guidance. Therefore, the complexity of this project required commitment from both the Whitehouse and those mandated implementing it.…

    • 618 Words
    • 3 Pages
    Improved Essays
  • Decent Essays

    Denver Airport Case Study

    • 1847 Words
    • 8 Pages

    The second way is to establish an early warning system. According to the article “Why bad projects are so hard to kill” (Royer I., 2003), in every project this kind of system should be established in order to see the first signs of possible failure and create control procedures and criteria for evaluating project viability at each stage of project’s development. These procedures should be clearly identified and top managers should not ignore them. In the Denver airport project, there should be a proper change management process to control changes. Also, at the beginning of the project Denver should have made a risk management exercise to identify potential risks that can occur and put together plans on how these risks would be managed. In this case many warning signs had been ignored, scope creep took a place. Denver should have created a project budget and had a system for monitoring and controlling costs of the…

    • 1847 Words
    • 8 Pages
    Decent Essays
  • Superior Essays

    Lean Management Case Study

    • 3945 Words
    • 16 Pages

    As previously stated, there are two other major organizational projects being worked on simultaneously using many of the same resources. Combined with summer vacation requests, scheduling large meetings proved to be very challenging and were ineffective in adding to production value. The project was broken down into three sub-groups; Checking Account Development, Visa Development, and Marketing, Training, and Employee Development. These groups were made by looking at the strengths that all of the team members possessed and delegating tasks within those boundaries. The project leaders understood that with the scheduling and staffing constraints that were present the team’s time was valuable and needed to be respected. Team members provided updates to the project managers via email. They were then updated as to the total project standings via email, and given the option to attend an in person meeting if they felt their presence was needed. This strategy proved to be very effective as it allowed team members to work at their own pace within the given limits and made them feel valued as their time was being respected by the team…

    • 3945 Words
    • 16 Pages
    Superior Essays
  • Improved Essays

    The project charter was incredibly detailed however it was not detailed enough for the IT team and every detail was not documented.…

    • 731 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    In September 2013 Jessica Bennett, Rusty Shingleton & Matt Johnson had me come into Jessica office to explain that SOT (Select Oilfield Trucking) would roll up into SFS (Select Field Services) and at the time SOT had Christa Wigal and Mary Williams. Christa Wigal was the processor and Mary ran the scales. Christa Wigal had moved up to the now Select yard prior to the roll over to SFS due to getting rid of the office trailer at the stone yard, to save money monthly. I was told during my meeting that I would be the supervisor over Christa and Mary but was not to say anything yet but to start streamlining processes for SOT to roll into SFS.…

    • 1315 Words
    • 6 Pages
    Improved Essays
  • Improved Essays

    Dvf Project Failure

    • 1029 Words
    • 5 Pages

    The successful completion of the Federal Bureau of Investigation’s Virtual Case File project was unlikely from the outset. Most projects are destined for either success or failure based on the ability of management to put all the necessary pieces together ensuring the completion of the project in its entirety and on time. The VCF project experience major issues that continued to plagued the project throughout its duration. Some of the issues which caused the failure of the VCF project can be attributed to the fact that the project did not have a set of well-defined requirements from the beginning, inability of the contractors to deliver the completed project, repeated turnover of management and CIO’s, and miscalculating the need for a phase-in period for the new system..…

    • 1029 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    The FBI underestimated the complexity of interfacing with the legacy system and did not retain a project integrator to manage contractor interfaces and take responsibility for the overall integrity of the program.…

    • 975 Words
    • 4 Pages
    Improved Essays
  • Great Essays

    There were many obstacles involved in this project. First of all, there were no seasoned project managers available and a novice was brought in to handle this project. In order to set the project manager, Melanie Lehr, up for success, she was given a mentor. Through this mentorship, she was able to seek counsel with a veteran project manager and avoid making…

    • 1141 Words
    • 5 Pages
    Great Essays
  • Improved Essays

    The vice president (VP) fails to analyze the overrun properly. The predictable overrun should be (81+55+73+70)/ (74+52+68+60)*2.66-2.66=$272,283, which is 10.24% of the overall budget, as well as the schedule. Essentially the project is now 15.05% behind the schedule, which means roughly 2.7 month delay in total if the problem lasts. And he failed to take the project phases effect into consideration because these are very important for project managers. By thinking in each term of stages, we can make sure that the deliverables made at the finish of each phase meet their purpose, and that project team members or sub-teams are properly organized for the next stage or phase. We can recognize…

    • 1080 Words
    • 4 Pages
    Improved Essays
  • Decent Essays

    If I would have been the project manager, I would have focused more on the implementation process. With this project being the first of its kind for Higher Ed, it needed a lot of research. While the project manger did a great job and knew a lot about the process, the service team did not. The service team would be the primary supporters of the systems once it was implemented. Support would come in the form of training documents, knowledge base articles, or general hands on training. The service desk team is responsible for taking calls and emails from users experiencing issues with the system. In order to troubleshoot these issues efficiently the service desk team should be familiar with the inputs, outputs, and the components of the system.…

    • 178 Words
    • 1 Pages
    Decent Essays
  • Improved Essays

    When a project fails, it has a multitude of negative consequences. The loss of time, money, and other resources coupled with the effects on the morale of the project team are all high costs to pay if the project’s failure is the result of not following project management best practices. There is no definitive definition of what makes a project a failure; however, a good definition of a project is a failure when the projects needed resources erode the value of the project past a threshold of the projects projected value.…

    • 732 Words
    • 3 Pages
    Improved Essays
  • Great Essays

    This case was developed for class discussions, rather than to illustrate either effective or ineffective handling of an administrative situation. The case has been prepared using primary and secondary information. The author would also like to thank company for their help.…

    • 1478 Words
    • 6 Pages
    Great Essays
  • Improved Essays

    Why Do Projects Fail

    • 700 Words
    • 3 Pages

    Perhaps the most important reason of project failure is that some developers are not using a proper structured methodology when they are working on a project. People that are new to this industry tend to rush to the programming itself. However, according to the article, Top 10 Reasons Why Systems Projects Fail, using a proper system development methodology is critical for the project to succeed. Coming up with the right kind of methodology that suites the project requires experience and skills. None of these methodologies is necessarily to be used in every project. Each of them have their own weaknesses and strengths. The project manager should be able to determine the methodology by looking at the…

    • 700 Words
    • 3 Pages
    Improved Essays
  • Decent Essays

    If any project has given a deadline where we can 't alter at any of it, make sure plans are so made that testing has to be done immensely, which is not happening in this project which may be the biggest error that management couldn 't afford to. Tests that are run poorly designed filed to withstand expected loads. These faults made system would never allow users have a nice time in responding to their requests and failing to complete their transactions. Quality control was highly not sufficient with common cases not tested as it has to…

    • 852 Words
    • 4 Pages
    Decent Essays
  • Improved Essays

    Nayatel Case Study

    • 1443 Words
    • 6 Pages

    A project frequently confronted postpones that would be an after effect of HR falling sick or leaving the projects or a lack of assets . After the implementation of the Project Management Office, project achievement turned out to be more up and coming due to the deliberate, and more controlled asset arranging and streamlining introduced by the Project management office. Tools like resource calendars and histograms have helped not just determination issues identified with deficiency of assets, yet in addition execute backups and substitutes.…

    • 1443 Words
    • 6 Pages
    Improved Essays