Triangle Project Relation

Great Essays
For understanding oil and gas claims and disputes prevention strategies, it is essential to consider the triangle of project relations. This triangle includes substance, process and relationships. Substance refers to all contractual rights and obligations, which incorporated in the contract. The second part is process and procedures and third part refers to maintain good relationship between the parties. For the prevention of occurring disputes and claims, it is important to consider both the substance and procedure. We may have a balance win-win contract, but the improper procedures cause claims and disputes. For example the other party may claim only due to lack of being notified properly or on time. Thus preventing mechanisms are …show more content…
Procedural measures and strategies:

1- Communication of potential problems at the earliest opportunity:
The longer a potential problem or claim is allowed to go on the more likely it is to escalate and the less likely it is that the matter will be resolved without a dispute. The advance warning of a potential problem or claim has the advantage of avoiding surprise by the other side and it enables the parties at the earliest opportunity to consider solutions to avoid or minimize the impact of any potential claim.
This process requires the contractor to give the other an early warning as soon as they become aware of any matter that can give rise to an increase in price, delay completion or impair performance of the work.

2- Reporting:
Employers can take (out of contract) measures for reducing potent of claims. Submission of progress reports by contractor is one of such measures. If contractors inform employer for their current activities and volume of future works(for example in coming weeks), the employer can predict claims and prevent them.

3- Documentation system:
The main part of claim management is attributed to the good documentation. Claim mangers shall provide a comprehensive and reliable set of documents and evidences for the project. These documents are including tender docs, correspondences, notifications and

Related Documents

  • Improved Essays

    HL 531 Week 1 Assignment

    • 495 Words
    • 2 Pages

    We are writing to provide you with an update to our site cleanup and remediation efforts, specifically as it relates the holdback provision of our Agreement. As you are aware, the site due diligence and soils investigations we completed during our acquisition process confirmed the presence of contaminated and/or impacted soils at 50 Ann St. which require clean-up and removal prior to us being able to advance our residential re-development proposal. Our Agreement with you requires that prior to us advancing clean-up of the site, that we provide you with notice in advance of excavation to allow you the opportunity to retain a third party engineer to evaluate our findings and our proposed remediation program. Please accept this letter as the required formal notice. Our consultant, Trafalgar Environmental, has conducted extensive investigations on Site…

    • 495 Words
    • 2 Pages
    Improved Essays
  • Improved Essays

    Unit 21 D1

    • 698 Words
    • 3 Pages

    D1: Evaluate the effectiveness of term in a given contract. For D1, I will be evaluating the effectiveness of terms considered in a mobile contract. I will evaluate how implied terms of statue protect consumers from defective goods from sellers and how business protect themselves from liabilities through exclusion clause.…

    • 698 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    Ga Verification Process

    • 445 Words
    • 2 Pages

    During the inspection of documents related to the construction project in Atlanta, Ga., I was able to detect a lack of segregation of duties, all the responsibility for hiring employees and operation of the project, rests with one person, the foreman of the project, who is in charge not only of observe that the job is completed but also of the administrative area of the same. Some of the failures that have detected, as result of too much pressure on the foreman is that there is no way to locate information about the verification process for the hiring of 20 employees, rather than tax forms that were presented at the main office by the foreman of the project. This procedure gives the opportunity for the company to be subject to fraud, since there is no guarantee that…

    • 445 Words
    • 2 Pages
    Improved Essays
  • Decent Essays

    In addition to the more complex and lengthy construction contracts, there are drastically increased numbers of opportunities for contractual disputes to disrupt the process. Many construction contracts in the modern workforce already include Alternative Dispute Resolution (ADR). This is a…

    • 388 Words
    • 2 Pages
    Decent Essays
  • Improved Essays

    New Jersey Inc Case Study

    • 1510 Words
    • 7 Pages

    Determine who supplied the tools and equipment if in the construction field; 6. Check the method of transportation of the worker to the job site; 7. Investigate whether there are other sources of income or whether the putative employer is the only source of income; 8. Determine…

    • 1510 Words
    • 7 Pages
    Improved Essays
  • Improved Essays

    With a constructive change, it is imperative for the Contractor to inform the Owner that one contemplates that a change has taken place. This gives the Proprietor the opportunity to mitigate or address the state of affairs. The changes clause that is considered for the Federal Government is one of the few stipulations that explicitly address the constructive change concept. Nonetheless, the constructive change is commonly accepted by the courts and industry as a part of a Changes Clause, whether specified or not. The concept is supplementary supported by the implied contract obligations of the Proprietor not to interfere, deter or delay, with the Contractors performance.…

    • 251 Words
    • 2 Pages
    Improved Essays
  • Improved Essays

    Time impact analysis involves charting the effect of a delay at the point in time when it occurs, allowing the likely consequences of the event to be determined. Time impact analysis does not affect all of the delaying events into the approved programme, the method takes account of the actual progress before each event and the programme that the contractor intended to follow the event and, as the last delaying event is impacted, an as-built record of the project stretches out behind…

    • 775 Words
    • 4 Pages
    Improved Essays
  • Superior Essays

    Grocery, Inc. Case Study

    • 789 Words
    • 4 Pages

    Grocery, Inc. should win the breach of contract suit against Company A. The renovation contract covers the quality of workmanship that Grocery, Inc. agreed to when hiring Company A. The subcontractor B used by A did not meet the criteria of the contract. Additionally, Company A unilaterally decided that to finish the job was impossible.…

    • 789 Words
    • 4 Pages
    Superior Essays
  • Improved Essays

    Ferdoushi Akhtar Hashi Chowdhury 23/03/2018 Liability in Civil Engineering – A Case Study Carillion Construction Ltd v Woods Bagot Europe Ltd & Ors [2016] EWHC 905 (TCC) Introduction This report presents a liability case study regarding the extension of deadlines in civil engineering projects, and the damages that might occur as a result of these delays. The liability aspect of the dispute presented in this report are reviewed and discussed, highlighting the importance understanding the implications of any delays in civil engineering projects.…

    • 730 Words
    • 3 Pages
    Improved Essays
  • Decent Essays

    It is very important in the business field to be able to correctly prepare these documents. I need the ability to prepare written communication, proofread, editing, documentation formatting, and using different style guides in my career. Reflection: These…

    • 576 Words
    • 3 Pages
    Decent Essays
  • Improved Essays

    Promissory Estoppel Essay

    • 707 Words
    • 3 Pages

    This essay seeks to discuss the Doctrine of Promissory Estoppel and the Doctrine of Consideration, as well as a clear analysis, with the use of case law, how Promissory Estoppel has become an exception to the general principle that a promise may only be enforced if it is supported by good consideration; it will ultimately conclude whether or not a promise to accept a smaller sum in discharge of a larger sum, if acted upon, is binding notwithstanding the absence of consideration. A contract is a legally binding agreement in law between two or more parties, which is enforced by law or by binding arbitration if it covers the elements of a valid legal agreement. For there to be a valid contract, three elements must be present, offer, acceptance, and consideration. If there is no consideration, there is no contract; however, with promissory estoppel instead of consideration, if there is a promise which induces reliance, the court would find some sort of liability for the promise.…

    • 707 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    By reviewing the various aspects of the decision it will assist in making sure each team member understands what is expected. Another important strategy is to incorporate deadlines and to develop emergency plans. Through establishing deadlines, it keeps the team on track. Further, developing emergency plans will give reluctant team members a safety net to aid in their buy-in. A leader must not be afraid to make the wrong decision.…

    • 1450 Words
    • 6 Pages
    Improved Essays
  • Improved Essays

    Boeing is an Amercian multinational cooperation that offers aircraft and product support services (Boeing: The Boeing company, no date). Being in the aircraft business involves a lot of risk unless someone is not careful and decisions are not made through careful and accurate analysis. They need to be on top of their game at all times ensuring safety of passengers and to uphold a good reputation to be able to be successful in the industry, in the long run. Risk comes in a number of different ways and are often unexpected. Risk management is fundamental to all business activities.…

    • 862 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    2). In this case, A2Z Construction’s stakeholders consisting of organisation’s top management, employees, project team and leader, clients, suppliers need to commit to the project from the planning stage to the post-project monitoring stage. 2) The success principle The success principle entails understanding the project milestones and deliverables agreeing upon them before the project commences and activities designated (Wideman 2003, p. 2).…

    • 1014 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    James, Adjou, Sylvia, Bob and Tim (represented by Ian) require identifying and advice as to the applicability of relevant contract and tort/delict principles to the current scenario presented in the problem question. Before proceeding with advising the individual’s, we need to check the validity of the contract and to establish the note displayed on the car windscreen is “Invitation to Treat” (or) “Offer”. The difference between the two is significant and need to be specifically identify, as the ‘invitation to treat’ cannot be accepted legally and an offer is an expression of willingness to contract on the specified terms without further negotiation and which is legally accepted.…