Due to the requirement in unique specialisations of resources in the project along with the project core team being a consulting company, the project team will consist with both internal and external workers. This means the project team will be a cross-functional where core team being co-located and Subject Matter …show more content…
For each phase, there is at least one human resource primarily responsible for completing the activities within the phase others may be involved in the other capacities such as accountable, consult and informed. However, only one person has primate accountability, as it would eliminate the risk of blaming each other if something goes wrong. The responsibilities are shown in the RACI table, a common type of responsibility assignment matrix that is a grid that shows the project resources assigned to each work package. Each letter in RACI represents the action of the resource has in each activity. R stands for responsible, A stands for accountable whereas C and I stand for consult and inform