Register to read the introduction… This would have been an acceptable problem had the issue been addressed at the time of sale. Instead Hodgkins took the option of hoping that customers would not modify their condominiums much and would settle for the original designs. This was a curious choice for Hodgkins to have made because the target market for the condominiums was that of relatively wealthy couples who would either be looking for a second home, or to move back to the city and live in relative comfort. This segment of the market is traditionally extremely particular about details and so would be expected to make changes to the condominium in order that it is exactly as desired. This was an oversight on Hodgkins’ behalf that put the general contractor in a difficult position with regards to schedules and budgets. Each time major changes were required the process of designing these changes would take several weeks[3] so that quotes could be gathered and the price of the changes could be agreed upon. If the issue had been addressed earlier then a proper framework could have been set up with adequate and fixed deadlines that would cause little or no problems to the general contractor and allow the changes to be made before critical areas of the condominiums were constructed. This difference would also have prevented the majority of complaints from customers regarding delays and slow …show more content…
As project manager success of the project should be the first and main priority however even though possible solutions to the problems have been given, Hodgkins did not appear to have used, or be likely to use any of them in order to resolve the current issues associated with the project.
The Miller’s Dilemma

Hodgkins states that there are effectively five different options available that could be taken. The table below summarises these options and their advantages and disadvantages.

|Decision |Advantages |Disadvantages |
|Inform the Millers that it was |No extra costs for the general contractor |The Millers would be extremely dissatisfied |
|too late to make the required |Schedule for construction of the units would not be|If the changes were carried out after closing, the |
|changes |delayed |entire floor would have to be shut down

Related Documents

  • Great Essays

    • Who raised the change? • What is the reason for the change? • What is the return required from the change? • What are the risks involved in the change? • What resources are required to deliver the change?…

    • 1234 Words
    • 5 Pages
    Great Essays
  • Great Essays

    I currently have a caseload of 30 learners, all of whom are working towards a level 2 and 3 in customer service or a level 2 in contact centre operations. The organisation has a mission that learners will complete a framework of learning (NVQ, technical certificate and key skills) and these objectives are laid down in a learning agreement at the start of the learning programme. Frameworks are Welsh Assembly Government (WAG) targets and these targets are monitored by DECELL’s and Estyn. As an IV within the customer service team I communicate the visions and objectives of the organisation through staff inductions, mentoring, team meetings and standardisation…

    • 2784 Words
    • 12 Pages
    Great Essays
  • Decent Essays

    Good Afternoon Dena, After discussing with Bruce the City’s concerns with the repayment of the Deferred Developer’s Fee and keeping with the previous repayment terms of the agreement Bruce is asking that the City consider and grant his request for the the following cash payment (4th paragraph) be included in the agreement amendment so that he can afford the administrative costs for the significant amount of staffing time and resources invested to complete the total renovation and reclamation of the subject property and create new affordable housing units within the City. He stated the current agreement defers his deferred cash payment for 55 years, while his request will allow for his deferred cash payment to be received as soon as there…

    • 336 Words
    • 2 Pages
    Decent Essays
  • Superior Essays

    Front Street Hospital: Uninsured Charges and Collections (pg. 237 of Cases in Healthcare Finance, 5th edition) It is quite clear from the text’s exposition on the policy, billing, and collection habits of certain not-for-profit hospitals that serious injustices were being committed against uninsured patients. These injustices were primarily financial in nature – although physical and psychological trauma almost always followed – and they reveal the systematic nature of the abuse. By setting “rack rates” – an extremely expensive set rate for medical procedures – as the ‘standard fare’ for all patients, while simultaneously granting clear and enormous discounts for those insured through third-party entities, the not-for-profit hospitals unconscionably…

    • 894 Words
    • 4 Pages
    Superior Essays
  • Improved Essays

    Ga Verification Process

    • 445 Words
    • 2 Pages

    During the inspection of documents related to the construction project in Atlanta, Ga., I was able to detect a lack of segregation of duties, all the responsibility for hiring employees and operation of the project, rests with one person, the foreman of the project, who is in charge not only of observe that the job is completed but also of the administrative area of the same. Some of the failures that have detected, as result of too much pressure on the foreman is that there is no way to locate information about the verification process for the hiring of 20 employees, rather than tax forms that were presented at the main office by the foreman of the project. This procedure gives the opportunity for the company to be subject to fraud, since there is no guarantee that…

    • 445 Words
    • 2 Pages
    Improved Essays
  • Decent Essays

    Many in the industry will agree when we say that the contracts in the construction industry have become more and more complex. Many owners will attempt to put extensive contracts in place that leave all responsibility on the contractor for the job. In response, contractors provide pages and pages of classifications, clarifications, exceptcions and alterations to terms laid out in the original contract. Over the last two decades, it has become difficult for owners and contractors. They must rely more than ever on legal maneuvering in order to minimize risks that come with the situation.…

    • 388 Words
    • 2 Pages
    Decent Essays
  • Improved Essays

    La Casita Centers mission is to enhance the health and well-being of Louisville’s Hispanic/Latino community through education, empowerment, advocacy, wellness, and mutual support. In order to create a thriving, healthy, and non-violent community that welcomes and celebrates its Hispanic/Latino members. Although the organization intended to focus on assisting the Hispanic community, single mothers, children, and they still uphold these as top priorities. However, they have opened up their mission to be inclusive of those from different ethnic or racial backgrounds, men, families, and adults and children with disabilities. Beliefs or Grounds of Meaning: La Casita Center does not instill religious principles into anyone who uses their services, but the foundation of the original organization – Casa Latina was modeled from the work of Dorothy Day.…

    • 412 Words
    • 2 Pages
    Improved Essays
  • Decent Essays

    Bosque Redondo Case Study

    • 134 Words
    • 1 Pages

    US Government wanted to move the Navajo to Bosque Redondo for several reasons. First, Navajos are seen as enemies. They occupied the annexed territory, so Navajo were treating like invaders even though they live first in those territories. Second, they wanted to expand to other territories, the Mexican-American war USA won the annexation of territory, so indigenous was hindrances. General Carleton believed that Navajo country was reach in Gold, so Navajo was obstacles to General Carleton.…

    • 134 Words
    • 1 Pages
    Decent Essays
  • Great Essays

    During 1938 baseball season, a great and prominent baseball player named Lou Gehrig noticed his performance on and off the field was not what it was supposed to be. He found himself stumbling over curbs and when running bases, he was more tired than usual, and he was fumbling the ball. On June 19, 1939, he was diagnosed with amyotrophic lateral sclerosis (ALS) on his thirty-sixth birthday. In the same year, Lou Gehrig retired from baseball, still considering himself to be the luckiest man alive and having a lot to live and be thankful for. Two years later he gave in to the disease and died on the second of June in 1941.…

    • 1511 Words
    • 7 Pages
    Great Essays
  • Great Essays

    American Shogun Case Study When a high-profile project is implemented, there needs to be a lot of planning, research, and flexibility. When a high-profile project also includes a very aggressive deadline, there is little room left for error.…

    • 1141 Words
    • 5 Pages
    Great Essays
  • Improved Essays

    1. INTRODUCTION In this report, it will be explain the authority and limitations of the Society of Construction Law Delay and Disruption Protocol, and an analysis of impact on programming techniques. 2. SOCIETY OF CONSTRUCTION LAW DELAY AND DISRUPTION PROTOCOL…

    • 775 Words
    • 4 Pages
    Improved Essays
  • Superior Essays

    The result was far different from the Scamozzian composition proposed two decades earlier. Instead of the classically upright villa-like form of the preliminary design with its dominant central portico and hipped roof that would have looked at home in the Veneto, the building has a distinctly cubic feel emphasised by the projecting terrace that forms the approach, the absence of a central pediment, the continuos balustrade disguising the roof and an altered relationship between the window and wall in which the windows now appear as isolated elements in a dominant wall…

    • 1643 Words
    • 7 Pages
    Superior Essays
  • Improved Essays

    Scope Creep When a project fails, it has a multitude of negative consequences. The loss of time, money, and other resources coupled with the effects on the morale of the project team are all high costs to pay if the project’s failure is the result of not following project management best practices. There is no definitive definition of what makes a project a failure; however, a good definition of a project is a failure when the projects needed resources erode the value of the project past a threshold of the projects projected value. Defining Scope Creep…

    • 732 Words
    • 3 Pages
    Improved Essays
  • Superior Essays

    Cancer has many forms of treatment, but the two that are known to most are chemotherapy and radiation therapy. Chemotherapy is the use of drugs like cytotoxic and others, where as radiation therapy is the use of x-rays or other similar forms of radiation to cure cancer. Arguments can and more than likely always arise that one form of the two treatments is more beneficial and effective than the other. Considering this, the type of treatment that may be used can differ for each type of cancer, just depending on which one is more useful for the particular illness. The two treatment may differ in a few ways but the biggest one can be the side effects of each one.…

    • 1260 Words
    • 5 Pages
    Superior Essays
  • Improved Essays

    Nayatel Case Study

    • 1443 Words
    • 6 Pages

    PMO DEPARTMENT IN NAYATEL COMPANY: After the analysis of PMO,the management has decided to establish the PMO department in Nayatel. The PMO plays a supportive role in the organization by providing training's to the project team members on various projects, tracking the progress of the project and communicating the success of the project to the board of directors and key stakeholder 1.ISSUES FACED BEFORE PMO: After the foundation of a Project Management Office, numerous issues and issues identified with projects have been resolve under the help of the PMO-Nayatel. The PMO has controlled the project consummation stages, making it a more light-footed, fruitful and viable process.…

    • 1443 Words
    • 6 Pages
    Improved Essays