Multi Span Bridges Essay

17044 Words Mar 15th, 2016 69 Pages
A DISSERTATION ON

SCHEDULING OF MULTI SPAN BRIDGES:
AN APPLICATION OF REPETITIVE SCHEDULING METHOD

Submitted to
Rajiv Gandhi Prodhyogiki Vishwavidhyalaya, Bhopal (MP)

For Partial fulfilment of requirements of
Master of Engineering (Civil) with specialization in
Construction Technology and Management

* 2009

Submitted by
KAVI PRAKASH

Department of Civil Engineering MADHAV INSTITUTE OF TECHNOLOGY AND SCIENCE (An autonomous Institute under R.G.P.V., Bhopal) Gwalior (MP) MADHAV INSTITUTE OF TECHNOLOGY AND SCIENCE (An autonomous Institute under R.G.P.V., Bhopal) Gwalior (MP) * * * * * 2009 * Recommendation
This dissertation work entitled
…show more content…
S K Jain
Professor and Head
Department of Civil Engineering
M.I.T.S. Gwalior-5
Dr. M M Pande
Professor
Department of Civil Engineering and Dean (Academic)
M.I.T.S. Gwalior-5
This is to certify that the above statement of the candidate is true to best of our knowledge

* ABSTRACT
The scheduling problem posed by multi span bridge has the characteristics of problem posed by linear repetitive construction however the repetitive units in this case of bridge may vary greatly in work from one unit to the other. The network methods are not effective to address such problems. When two activities are independent of each other, network techniques are incapable of scheduling the activities logically. Additional artificial constraints are required to schedule the activities which have constant production rate. These methods are not efficient in addressing problems of continuous utilization of resources.
Line of Balance (LOB) is well suited for repetitive activities where different crews performs the activities one after the other; however this is not effective in scheduling multi span bridges where large numbers of activity are dependent on each other. Further, LOB is primarily a technique with emphasis on continuous utilization of resources and therefore is not ideally suited for scheduling bridges where activities and quantum of work varies from one unit to another.

Linear scheduling Method developed primarily for scheduling linear