Phase 1 and 2 of the Muslet Bros project was first undertake by KBSS Construction, a construction company from Sebring Florida. Unable to successfully complete phase 1 of the project and in disagreement with the project owner, KBSS Construction was released of their construction duties and Atlantis Engineering Services was hired on March 18, 2013 to complete the outstanding for phase 1 and to start and finished phase 2.
One of the major problem was rectify the civil engineering design (water, sewer and drainage) and installation. The redesign was need so as to make meet Palm Beach County Water Utilities standards (PBCWUD).
On March 13, 2013, Mr. Carl Cool , the project engineer submitted to Mr. Adam Galicki