Epc Case Study

Improved Essays
37.2 Should the Facility or any part thereof cease operating due solely to Defects or to corrective actions for Defects, the Defect Correction Period shall be extended by an amount of time equal to the amount of time during which the Facility was not in operation due to such Defects or for the correction of such Defects.
37.3 CONTRACTOR warrants that the written instructions regarding the use of equipment, including those instructions in operation and maintenance manuals, shall conform to this EPC Contract and GECP as of the time such instructions are prepared. If any non-conformance with CONTRACTOR's warranties set forth in this GC-37.3 occurs or is discovered at any time prior to or during the Defect Correction Period, CONTRACTOR shall,
…show more content…
All such warranties shall run to the benefit of CONTRACTOR but shall permit CONTRACTOR, prior to assignment to CMA, the right (upon mutual agreement of the Parties), to authorize CMA to deal with Subcontractor or Subsubcontractor on CONTRACTOR's behalf. Such warranties, with duly executed instruments assigning the warranties shall be delivered to CMA concurrent with the end of the Defect Correction Period. This shall not in any way be construed to limit CONTRACTOR's liability under this EPC Contract for the entire Work or its obligation to enforce Subcontractor and Subsubcontractor …show more content…
Upon CMA giving reasonable prior notice, CONTRACTOR shall furnish CMA with access to all locations where Work is in progress on the Work Site and at the offices of CONTRACTOR and its Subcontractors and Subsubcontractors. CMA shall be entitled to provide CONTRACTOR with written notice of any Work that CMA believes does not conform to the requirements of this EPC Contract. If any Work is Defective prior to Provisional Acceptance, then CONTRACTOR shall, at its own expense, correct such Defective Work. If such Defective Work is on the critical path for the Project or otherwise impacts the Facility or any portion of the Project, CONTRACTOR shall commence the correction of such Defective Work within a reasonable time but in no event later than the earlier of five (5) Business Days after receipt of notice from CMA or CONTRACTOR's becoming aware of such Defect, and shall diligently perform and complete the correction of such Defective Work using, as necessary, overtime or shifts and expediting the procurement of materials without cost to CMA. If CONTRACTOR fails to commence, perform or complete the correction of Defective Work as required by this GC-37.6, then CMA, upon providing written notice to CONTRACTOR, may perform such corrective Work and CONTRACTOR shall be liable to CMA for the reasonable costs incurred by CMA in

Related Documents

  • Improved Essays

    Teri Case Summary

    • 740 Words
    • 3 Pages

    FACTS Teri entered into a contract with Jack to sell her home for $300,000. After the parties sign the contract; Teri learns of a Boston municipal rule that all firefighters must live within the Boston city limits. Teri then calls Jack to back out of the contract to sell her house, because of the municipal rule. Jack is asking the judge for specific performance, to force Teri to sell the house in accordance with the original contract. Teri argues that, although specific performance is usually appropriate in land sale contract cases, the judge has the discretion to deny specific performance.…

    • 740 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    Hrm/531 Week 1

    • 881 Words
    • 4 Pages

    Provisions of paragraphs one, seven, and eight are for employees by stipulating the roles the employees are expected to perform. Additionally, it gives wider insights on the responsibilities that are expected from employees. The provisions also provide key terms that should be followed in the contract. Question 4 The provisions of paragraphs two and four are intended to protect the confidential information of the company and its inventions.…

    • 881 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Raytheon Core Values

    • 703 Words
    • 3 Pages

    This is a formal letter of warning, which will be placed in your HR file. This serves as documentation of your need to adhere to the guidance set by your supervisor, discontinue the disrespectful treatment toward your subordinates, publicly making comments that are inappropriate in the workplace, the lack of leadership and to document your need to exhibit behaviors that are more consistent with Raytheon core values. You are a leader in the Finance organization. In leading a team, it is Raytheon’s expectation that you treat all employees with respect and dignity, provide guidance to direct reports and cease making comments that are inappropriate in the work place.…

    • 703 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    Hello All, As you are aware Procurement is working with two separate companies, Total Construction and Titan Machinery, to rent a front wheel loader and 5 tandem dump trucks for spring land spreading. The equipment will be operated by MCES employees. Both companies have asked us to sign rental agreements that are not favorable to the Council. The largest concern relates to indemnification and insurance coverage. Phil Walljasper from Risk has weighed in and has concerns that the Council is not protected/covered from a risk perspective regarding either agreement.…

    • 252 Words
    • 2 Pages
    Improved Essays
  • Decent Essays

    Many in the industry will agree when we say that the contracts in the construction industry have become more and more complex. Many owners will attempt to put extensive contracts in place that leave all responsibility on the contractor for the job. In response, contractors provide pages and pages of classifications, clarifications, exceptcions and alterations to terms laid out in the original contract. Over the last two decades, it has become difficult for owners and contractors. They must rely more than ever on legal maneuvering in order to minimize risks that come with the situation.…

    • 388 Words
    • 2 Pages
    Decent Essays
  • Improved Essays

    That said, customers were not made aware of the extended warranty policies that entitles them to continuous coverage and protection from serious and costly damages after the factory warranty expires. Besides the large profit margin these types of warranties brings to the company, they help us earn our customers trust and satisfaction knowing they are taken care of should any unexpected costly repairs…

    • 840 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    participating in the May 8th mediation regarding the Davis lawsuit against many parties, including the Whispering Ridge HOA. Thank you for agreeing to mediate this case. I apologize in advance for any deficiencies in my responses. I am not an attorney and have no training in law. Due to the economic losses suffered by our members, we were forced to release our counsel.…

    • 360 Words
    • 2 Pages
    Improved Essays
  • Great Essays

    Burger King Case Study

    • 5506 Words
    • 23 Pages

    “A manufacturer is subject to liability for compensatory damages based on a product liability claim only if the claimant establishes, by a preponderance of the evidence, all of the following: “(1) Subject to division (B) of this section, the product was defective in manufacture or construction as described in section 2307.74 of the Revised Code, was defective in design or formulation as described in section 2307.75 of the Revised Code, was defective due to inadequate warning or instruction as described in section 2307.76 of the Revised Code, or was defective because it did not conform to a representation…

    • 5506 Words
    • 23 Pages
    Great Essays
  • Improved Essays

    With a constructive change, it is imperative for the Contractor to inform the Owner that one contemplates that a change has taken place. This gives the Proprietor the opportunity to mitigate or address the state of affairs. The changes clause that is considered for the Federal Government is one of the few stipulations that explicitly address the constructive change concept. Nonetheless, the constructive change is commonly accepted by the courts and industry as a part of a Changes Clause, whether specified or not. The concept is supplementary supported by the implied contract obligations of the Proprietor not to interfere, deter or delay, with the Contractors performance.…

    • 251 Words
    • 2 Pages
    Improved Essays
  • Decent Essays

    PLAINTIFF’S COMPLAINT AGAINST DANIELS Roosevelt Cannady alleges that on or about April 2, 2015, he was struck by construction scaffolding as he entered a store owned by Saving Incorporated d/b/a Dodge’s Store (Dodge’s Store) and/or Savings Oil Company. He claims that Defendant James Daniels d/b/a ABC Contracting Services (Daniels) was performing construction on the store’s roof at the time, and Daniels’s negligence during construction was the direct and proximate cause of his injuries. On February 26, 2016, Cannady filed a lawsuit against Dodge’s Store, Savings Oil Company, and Daniels. Cannady alleges that Daniels was negligent because he allowed an unsafe condition to exist at the store, knew or should have known of the unsafe condition, and he did not remedy the unsafe condition.…

    • 685 Words
    • 3 Pages
    Decent Essays
  • Superior Essays

    The employee/contractor is obligated to carry out all actions to certify compliance of the contract. 2. The employer is obligated to uphold their contract and ethical behavior of negligence. 4. Contracting versus Employment 1.…

    • 732 Words
    • 3 Pages
    Superior Essays
  • Improved Essays

    6 Force Majeure Essay

    • 3461 Words
    • 14 Pages

    In such circumstances, the party concerned is relieved from liability. The party claiming an event of force majeure is often required to use reasonable efforts to remove the causes of non-performance and to complete performance as promptly as possible. The term “force majeure” provisions usually include common features, such as: • a detailed definition of a force majeure event; • the obligations surrounding a force majeure event: these usually require the party claiming force majeure to serve notice to the other party and use all reasonable efforts to correct the situation as promptly as possible; • examples of events which constitute a force majeure event: this is usually a standard list and may be exhaustive or non-exhaustive; however, some jurisdictions have a broader list of examples than others;…

    • 3461 Words
    • 14 Pages
    Improved Essays
  • Improved Essays

    Design And Build Contract

    • 724 Words
    • 3 Pages

    In a design and build contract an initial contractor is employed by the client, then the contractor is responsible for overseeing both the design and construction phase of a project. The contractor would either have their own in house design team they would use or employ external consultants who would assist in the design phase. A novation agreement is sometimes used in a design and build contract, this is where the client employs consultants to produce their initial design then the same consultants are employed by contractor to complete the detailed design. In a design and build project the contractor has the majority of the responsibility so therefore also has a large share of the risk involved in the project as the “contractor 's liability…

    • 724 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    Modest Proposal

    • 1966 Words
    • 8 Pages

    EXECUTIVE SUMMARY The main purpose of the tender submission is to show our dedication and enthusiasm in understanding the design package of mousetrap car of Group 4B. The tender evaluation criteria list provides the criterion that have to be fulfilled by us in order to contract Group 4B design. Therefore, we as the contractors of Group 7A have to produce tender submission which provides explanation and evidences on how we fulfilled the criterion from the tendering company. There are few reasons that we chose the design package of Group 4B. One of the reasons is the design of mousetrap car of Group 4B is stable and efficient which can function welly since the prototype had been built.…

    • 1966 Words
    • 8 Pages
    Improved Essays
  • Improved Essays

    13. INSPECTION OF PREMISES. Lessor and Lessor's agents shall have the right at all reasonable times during the term of this Agreement and any renewal thereof to enter the Premises for the purpose of inspecting the Premises and all buildings and improvements thereon. And for the purposes of making any repairs, additions or alterations as may be deemed appropriate by Lessor for the preservation of the Premises or the building. Lessor and its agents shall further have the right to exhibit the Premises and to display the usual "for sale", "for rent" or "vacancy" signs on the Premises at any time within forty-five (45) days before the expiration of this Lease.…

    • 1327 Words
    • 6 Pages
    Improved Essays