Construction Contract Case Study

Superior Essays
Introduction
In construction sector, construction contract will be used. Inside the construction contract, there mainly including length of project, complexity, size of project, and the price that has been agreed. In the case Modern Engineering (Bristol) Ltd v. Gilbert-Ash Northern (1974) AC 689, it mentioned that construction contract is for selling goods, services, and labour, which is lump sum price payable by installment according to the work done. This shows that the contractor have obligation to the employer to finish the work on time as the length of project have been mentioned in the contract. However, the delay of the working process may not is contractor’s fault only. Employer’s fault or other external factors can also affect the
…show more content…
Therefore, employer has to take action when this happened in order to claim the loss. The case Shawton Engineering Ltd v DGP International Ltd (2006) BLR 1 shows what should employer do and the contractor liability. Since it is breach of contract when the contractor delays the completion, the employer can issue notice for the contractor. The notice will not go into effect until the contractor delay the construction work. If the contractor is in breach of contract, the employer can terminate the contract or claim from contractor. It is very common practice to mention in the contract that what the damages in different period of time if the contractor fail to meet the completion date. This kind of damage is called liquidated damages. So, when the contractor fails to meet the completion date, he has this liability to compensate the employer since the employer already issue notice for …show more content…
The reason is that the employer maybe fails to fulfill some of the terms in the contract. This may delay the contractor working process. Variation is one of the reasons to cause delay. In common law, it mention that contractor have the liability to provide evidence to claim money. First of all, it has to prove that the work is extra and have not been included in the contract. Also, there should have terms promised by employer to pay for the work done. Moreover, the contractor can find any thing or agent that have authority to issue instruction for the completed work. Just like in the case Malloy v. Liebe (1910) 102 LT 616, employer asked contractor to do some work and then employer think that is included in the contract, but contractor do not think so. However, the judge mention that the work in this case is the variation, if employer continue want contractor carry out that work, employer need to pay contractor.

Except variation may make the contractor delay the working process, there is some other reason that may make contractor can meet the completion date. In clause 2.4 of JCT SBC, the employer must give contractor permission to go into the site on the date that have been stated in the contract. Otherwise, employer fails to let contractor to follow the obligation to work ‘regularly and diligently’. This will make contractor fail

Related Documents

  • Improved Essays

    Law: Contract Law Reasons: Failure of consideration so, terms are not binding Ratio: Consideration needed in order to achieve constructive dismissal in regards to changes on contract terms. Works Cited Hilton v. Norampac Inc., V-193113CM (Ontario Superior Court of Justice May 22, 2002). Honda Canada Inc. V. Keays, 31739 (Supreme Court of Canada June 27, 2008). Richard A. Yates, T. B.-K. (2011). Buisness Law in Canada (9th ed.).…

    • 1173 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    This case is a very good example of a good project management with high risk management. This case talks about the importance of project management process and risk management. Their approach to project management is bottom up, executive teams don’t tell project teams what to do, it project managers and project teams who provide project plans and analyse the risk and decide whether to do the project or not. Project teams take at least 6 months to bid for a RFP, and when they win the bid they know what they are going to do next. They are having a unique approach towards risk management and compliance process.…

    • 701 Words
    • 3 Pages
    Improved Essays
  • Decent Essays

    To: Richard Ramirez and Juan Carlos Gutierrez For the last 6 months, we have been complaining to you to complete the job. We also met with you to go over the details of the work that has not been completed with any success, but we always ended up arguing. I don't want to go through it again because it is such a mental distress to me when I only see you avoiding your responsibility, not admitting your faults, and not recognizing how much money I'm losing daily.…

    • 173 Words
    • 1 Pages
    Decent Essays
  • Improved Essays

    Ga Verification Process

    • 445 Words
    • 2 Pages

    During the inspection of documents related to the construction project in Atlanta, Ga., I was able to detect a lack of segregation of duties, all the responsibility for hiring employees and operation of the project, rests with one person, the foreman of the project, who is in charge not only of observe that the job is completed but also of the administrative area of the same. Some of the failures that have detected, as result of too much pressure on the foreman is that there is no way to locate information about the verification process for the hiring of 20 employees, rather than tax forms that were presented at the main office by the foreman of the project. This procedure gives the opportunity for the company to be subject to fraud, since there is no guarantee that…

    • 445 Words
    • 2 Pages
    Improved Essays
  • Improved Essays

    However, as time goes on, the contractor not only does not produce the sealed document, but also pulls back his promise which is the extension of the owner’s payment date to the owner. Thus, the Court of Appeals implements the rule of equity. Similarly, the case one implements the same principle. Therefore, the information technology firm is not entitled to terminate the contract and it will be equitably estopped. The airline will be successful in suing the information technology firm and deserve a compensation which include the extra cost of the price of hiring another firm to finish the project and any further damages directly due to the breach of…

    • 1169 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    Peng, Chen MGMT 3720 Assignment #1 Walt Henderson is a draftsman in Wilson Construction Company. One day he was working on his personal project during company time and caught by his supervisor, Ken Hardy. Walt believes he has right to work on his personal project as long as he has completed all his work. However, Ken doesn’t agree with that because he believes workers are not allowed to do their personal project during company time based on the company rules. Then they had an argument about working at home and while on the company time.…

    • 729 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    With a constructive change, it is imperative for the Contractor to inform the Owner that one contemplates that a change has taken place. This gives the Proprietor the opportunity to mitigate or address the state of affairs. The changes clause that is considered for the Federal Government is one of the few stipulations that explicitly address the constructive change concept. Nonetheless, the constructive change is commonly accepted by the courts and industry as a part of a Changes Clause, whether specified or not. The concept is supplementary supported by the implied contract obligations of the Proprietor not to interfere, deter or delay, with the Contractors performance.…

    • 251 Words
    • 2 Pages
    Improved Essays
  • Improved Essays

    PM 598 Final Exam Keller Purchase here http://devrycourse.com/pm598finalexamkeller Product Description TCO A) All the below are tools and techniques of conduct procurement, except (Points : 5) (TCO A) All the below are tools and techniques of control procurement, except (Points : 5) (TCO B) Proper selection criteria are critical for a successful project.…

    • 985 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Federal OSHA is an agency responsible for the safety and health of 130 million workers and 8 million worksites throughout the nation. According to information obtained from the U.S. Bureau of Labor and Statistics, more than 4,500 workers were killed in 2013. When compared to 2012, fatal work injuries related to the private construction sector increased by 3 percent. This increase represents the largest number of fatal work injuries in this sector since 2009. In 2013, the fatal work injuries involving contractors accounted for nearly 20 percent of all fatal work injuries.…

    • 939 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    The Society of Construction Law has worked to promote for the public benefit education, study ad research in the field of construction law and related subjects in the UK and overseas. The SCL Delay and Disruption Protocol has been prepared for determining extensions of time and compensation for delay and disruption. Published on 2002, it exists to provide guidance to all parties to the construction process when dealing with delay. The Protocol examines the issues of delay and compensation…

    • 775 Words
    • 4 Pages
    Improved Essays
  • Decent Essays

    Case Study 8 The Ccmma

    • 783 Words
    • 3 Pages

    CASE STUDY-8 THE CCPM DILEMMA Executive Summary: Pinyarat worked in IT department of diversified firm. Firm increment budget by 10 percent to all activity because all project were coming to late while people was working too hard and wants to relief. Result this approach failed, after this firm decide to give extra time and 10 percent for complete project on given time schedule but overall result failed. Nothing improved and project continued late from actual date.…

    • 783 Words
    • 3 Pages
    Decent Essays
  • Improved Essays

    Importance of Standard Default Clause All government contracts contain provisions that protect the interest of the government and the contractor. The provisions in a contract indicate the requirements, conditions, and the obligations for all who are involved in the contract. Provisions suggest the contractor is to conduct business during the period of a contract. Interfacing with the government is also included in the provisions. Contractors who are new to government contracting and do not understand or are aware of the provisions in contract are those contractors that have some sort of dispute (Hearn, 2011).…

    • 780 Words
    • 4 Pages
    Improved Essays
  • Great Essays

    Introduction Williams v Roffey Bros. is a leading case in English contract law. The appellant is Williams and the respondent is Roffey Bros. & Nicholls (contractors)Ltd. Facts In September 1985, the building contractor, Roffey Bros. & Nicholls Ltd., entered into a contract with Shepherds Bush Housing Association Ltd. to refurbish a block of flat, Twynholm Mansions, Lillie Road, London SW 6, and became is the main contractors for the works. Williams, the carpenter, was engaged to carry out the carpentry work of the 27 refurbished flats. Williams was originally engaged on three separate subcontracts, however, there are all superseded by a writing subcontract made on 21 January 1986.…

    • 1444 Words
    • 6 Pages
    Great Essays
  • Superior Essays

    Final Outline Brandy Noell BUS 311: Business Law I Instructor Brian Lahargoue September 19, 2016 I. Introduction 1. Acme Fireworks sells kinds of fireworks that include but are not limited to single-use and aerial display ground show. If an individual can think of it, Acme Fireworks can supply it. Acme Fireworks is a sole proprietorship that started out in a smal garageand is now looking to change its entity status. They are looking change because of the recent influx of larger business contract requests that will create a larger employee base, causing more liability risk, and higher demand for what some may deam either dangerous or even a hazzardous product which in turn will prompt evaluation of insurance coverage and…

    • 732 Words
    • 3 Pages
    Superior Essays
  • Improved Essays

    2. What information did the vice president fail to analyze? The vice president (VP) fails to analyze the overrun properly. The predictable overrun should be (81+55+73+70)/ (74+52+68+60)*2.66-2.66=$272,283, which is 10.24% of the overall budget, as well as the schedule.…

    • 1080 Words
    • 4 Pages
    Improved Essays