CHAPTER EIGHT

Cost Estimation and Budgeting

To Accompany

PROJECT MANAGEMENT:
Achieving Competitive Advantage

By
Jeffrey K. Pinto

CHAPTER EIGHT

PROJECT PROFILE – Boston’s Central Artery/Tunnel Project: Updated and Complete
8.1 COST MANAGEMENT Direct vs. Indirect Costs Recurring Versus Nonrecurring Costs Fixed Versus Variable Costs Normal versus Expedited Costs
8.2 COST ESTIMATION Learning Curves in Cost Estimation Project Management Research in Brief: Software Cost Estimation Problems with Cost Estimation
PROJECT PROFILE – Heathrow Airport’s New Terminal Five Development
8.3 CREATING A BUDGET
…show more content…
|February |March |April |May |Total by |
| | | | | | |Activity |
|Survey |4,000 | | | | |4,000 |
|Design | |5,000 |3,000 | | |8,000 |
|Clear Site | |4,000 | | | |4,000 |
|Foundation | | |7,500 | | |7,500 |
|Framing | | | |8,000 |2,000 |10,000 |
|Plumb & | | | |1,000 |4,000 |5,000 |
|Wire