Carillion Construction Ltd V. Woods Bagot Europe Ltd & Ors

Improved Essays
Ferdoushi Akhtar Hashi Chowdhury 23/03/2018

Liability in Civil Engineering – A Case Study

Carillion Construction Ltd v Woods Bagot Europe Ltd & Ors [2016] EWHC 905 (TCC)
Introduction
This report presents a liability case study regarding the extension of deadlines in civil engineering projects, and the damages that might occur as a result of these delays. The liability aspect of the dispute presented in this report are reviewed and discussed, highlighting the importance understanding the implications of any delays in civil engineering projects.
The construction of the High Court Rolls Building in London experienced a delay due to a dispute between the main organisations involved in the project. The parties involved were Carillion Construction Ltd (Carillion),
…show more content…
A series of question were raised in a preliminary trial:
Assuming that EMCOR was entitled to an extension to the deadline, should that extension:
• run contiguously from the end of the prevailing date of completion, to provide a supplementary time for EMCOR to complete its sub-contract works (as EMCOR contended)? Or,
• as EMCOR contended, run on further periods during which the subcontractor could complete its sub-contract works, which were not necessarily contiguous but were equal to the delay period?
Assuming that, under the building contract, Carillion’s claim against the sub-contractors covered its liability to Rolls for liability damages:
• Had Carillion's liability to Rolls for the liability damages been annihilated by the additional supplemental agreement signed in November 2010?
• if that is the case, what is the effect on EMROC’s and AECOM’s liability to Carillion?
Final

Related Documents

  • Improved Essays

    ARGUMENT I. THE PETITIONER, IN THIS CASE, WAS AN EMPLOYEE OF PLUS BUILDING, INC., AND NOT AN INDEPENDENT CONTRACTOR. Respondent claims that Petitioner Mr. Kroplewski was not an employee of Plus Building, Inc., but an independent contractor. Although there is no rigid rule of law to determine whether an employer-employee relationship exists between parties, such determination depends on the particular facts of the case. The range of factors is considered in making that determination including the right to control the manner in which the work is done, the method of payment, the right to discharge, the skill required, and who provided the materials, tools, and equipment.…

    • 888 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Third, on September 27, 1982, PSI Cosmetics (defendant), leased a vehicle from Barco Auto (plaintiff). PSI stated that two months later the engine began to smoke and was towed to an authorized dealer. The dealer took over three months to repair a blown motor. The defendants continued making their payments, even though, they had no use of the vehicle. Mr. Golumbia was advised after 300 to 600 miles, he should have the vehicle serviced (retorqued).…

    • 1283 Words
    • 6 Pages
    Improved Essays
  • Improved Essays

    This involved two potential contracts: a unilateral, ‘process’ contract followed by a bilateral, binding agreement. An offer of a unilateral, process contract was sent to the three contractors by MML. To accept the offer, they are required to submit a tender and pay a $100 administration fee to be considered for the contract to paint Eastfield plaza. In this process contract, if accepted by the contractors, MML would have an obligation to accept the lowest-priced tender that complied with the terms of the tender process and be obliged to enter into a bilateral contract with them. These terms include the tenders being treated as confidential, the tender needing to be received by the 24th February at 5pm along with the aforementioned admin fee.…

    • 699 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    Ga Verification Process

    • 445 Words
    • 2 Pages

    During the inspection of documents related to the construction project in Atlanta, Ga., I was able to detect a lack of segregation of duties, all the responsibility for hiring employees and operation of the project, rests with one person, the foreman of the project, who is in charge not only of observe that the job is completed but also of the administrative area of the same. Some of the failures that have detected, as result of too much pressure on the foreman is that there is no way to locate information about the verification process for the hiring of 20 employees, rather than tax forms that were presented at the main office by the foreman of the project. This procedure gives the opportunity for the company to be subject to fraud, since there is no guarantee that…

    • 445 Words
    • 2 Pages
    Improved Essays
  • Decent Essays

    Many in the industry will agree when we say that the contracts in the construction industry have become more and more complex. Many owners will attempt to put extensive contracts in place that leave all responsibility on the contractor for the job. In response, contractors provide pages and pages of classifications, clarifications, exceptcions and alterations to terms laid out in the original contract. Over the last two decades, it has become difficult for owners and contractors. They must rely more than ever on legal maneuvering in order to minimize risks that come with the situation.…

    • 388 Words
    • 2 Pages
    Decent Essays
  • Improved Essays

    Article summaries: Article 1: Steers in ad row over macon burger: A Woman complained about the advertising of the macon burger, she claimed that it was misleading and violated religious beliefs as the meat used was beef. The word macon used for beef products violates religious beliefs because Muslims do not eat bacon and Hindus do not eat beef. Steers said they did not intend to violate any religious beliefs and simply use macon for their bacon burgers which are beef, in respect for halaal customers who do not eat bacon.…

    • 817 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    National Surety contends a fourteen-page settlement agreement that resolved an end-of-work payment dispute was a substitute contract, entirely replacing a multifaceted AIA Contract for the construction of an apartment complex. Assuming, arguendo, that the 2007 settlement agreement could influence the operation of the Waivers—it cannot—National Surety’s argument nevertheless fails because the plain and unambiguous terms of the settlement agreement evince an intent not to “extinguish [] the old contract, by the substitution for it of the new one.” Leisner v. Finnerty, 252 Md. 558, 564 (1969). Rather, the 2007 agreement merely modified the AIA Contract, and the Waivers of the AIA Contract prevail because they are not inconsistent with the 2007…

    • 629 Words
    • 3 Pages
    Improved Essays
  • Decent Essays

    On September 18, Custom Designs have order oak French doors that have been arrived on October 28. However, they were made too small. The measurements that were given was 3.55 meters and what we have received was 3.35 meters. The carpenter said that it was not possible for him to stretch the doors in order to fit the opening. Unfortunately, being a regular client of Capitol Lumber and Hardware this was not appreciated because on top of the five weeks’ delay, I had to be charged for $575 for to errors that have been issued.…

    • 144 Words
    • 1 Pages
    Decent Essays
  • Decent Essays

    Texas A & M Ethics

    • 206 Words
    • 1 Pages

    1. The purpose of this lecture is to enhance and broaden the students’ knowledge on ethics in the construction industry. 2. Professor Horlen, the Construction Science department head, specializes in legal issues involving construction, dispute resolutions, employment law, and product liability. Professor Horlen discussed different types of ethics, law, and morality that students endure daily.…

    • 206 Words
    • 1 Pages
    Decent Essays
  • Improved Essays

    EPC Contract

    • 690 Words
    • 3 Pages

    (2) Fails to make progress according to the agreed-upon EPC Contract Schedule so as to endanger performance of this EPC Contract; (3) Abandons or refuses to proceed with any of the Work, including modifications directed pursuant to General Condition 32, titled CHANGES; (4) Fails to fulfill or comply with any of the other material terms of this EPC Contract; (5) Fails to commence the Work in accordance with the provisions of this EPC Contract; (6) Abandons the Work; (7) Fails to maintain insurance required under this EPC Contract; (8) Materially disregards Applicable Law or applicable standards and codes; (9) Engages in behavior that is dishonest, fraudulent or constitutes a conflict with CONTRACTOR's obligations under this EPC Contract;…

    • 690 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    The Society of Construction Law has worked to promote for the public benefit education, study ad research in the field of construction law and related subjects in the UK and overseas. The SCL Delay and Disruption Protocol has been prepared for determining extensions of time and compensation for delay and disruption. Published on 2002, it exists to provide guidance to all parties to the construction process when dealing with delay. The Protocol examines the issues of delay and compensation…

    • 775 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    Case 13.3 Kohel v. Bergen Auto Enterprises, LLC Superior Court of New Jersey, Appellate Division, 2013. 2013 WL 439970. Issue: This case involved allegations of breach of contract involving which parties and for what actions?…

    • 508 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    The devastating failure of the Hyatt Regency Walkway was an important lesson in communication for engineers. Studying what mistakes the structural engineer made that led to the failure of the walkway created new standards for safety and communication to prevent negligence and misconduct in the practice of engineering. This begs the question how has the failure of the design changed the way engineering ethics sets the standard for safety and communication? Jack Gillum’s, the structural engineer, mistakes have impacted the way engineering is practiced today; regarding safety, communication, and responsibility, thus leading to encouraging proper practices of the Code of Ethics and effective communication to prevent future failures.…

    • 793 Words
    • 4 Pages
    Improved Essays
  • Superior Essays

    The cases have contrasting outcomes due mainly due to the language used by Manchester City Council which ended in Storer being able to buy the council house and Gibson being declined to buy the council house. In the Case of Gibson, Manchester City Council stated that they “may be prepared to sell the house”; whilst in the Storer case they stated that “if you will sign the Agreement and return to me, I will send you the Agreement sign on behalf of the Council in exchange”. The language and conduct of the Manchester City Council was objectively scrutinized in each case and found that there was intention to be bound in the Storer case however there was no intention to be bound in the Gibson case, Poole (2012). This can be applied in the scenario here, the language must be objectively scrutinized as this may affect whether Gary was issuing a counter-offer or a mere request for further information. This is critical as a counter offer voids the original offer in its entirety and therefore it would be determined that there is no valid contract between Gary and…

    • 1534 Words
    • 6 Pages
    Superior Essays
  • Improved Essays

    2. What information did the vice president fail to analyze? The vice president (VP) fails to analyze the overrun properly. The predictable overrun should be (81+55+73+70)/ (74+52+68+60)*2.66-2.66=$272,283, which is 10.24% of the overall budget, as well as the schedule.…

    • 1080 Words
    • 4 Pages
    Improved Essays