Calculating and Interpreting a Project Network Diagram Essay
In Table 1.0 you will find the results of our initial analysis which includes …show more content…
Table 1.0 - Note: Each task is estimated in weeks (ex. Task A optimistic estimate = 4 weeks)
Task
O M P E ES EF LS LF Slack
A 4 7 10 7 1 7 2 8 1
B 2 10 24 11 8 18 9 19 1
C 8 12 16 12 8 19 8 19 0
D 4 9 14 9 8 16 21 29 13
E 1 2 3 2 19 20 28 29 9
F 6 8 22 10 20 29 20 29 0
G 2 3 4 3 19 21 27 29 8
H 2 2 2 2 30 31 30 31 0
I 6 6 6 6 17 22 26 31 9
J 4 7 16 8 32 39 32 39 0
Our next exercise will consist of 4 different scenarios to show what could happen to the construction company’s project completion time-line if there is movement within any given task.
Scenario 1 – Task D and E are delayed by 9 weeks: Task D has an EF date of 16; thus, if 9 additional weeks were added to task D it would be completed at the end of week 25. Task E has an EF of 20 and by adding 9 additional weeks task E would be completed at the end of week 29. Therefore, the 9 additional weeks added to both task D and task E will not have any affect to its successor task H as the LS for task H is week 30. Moreover, the slack outlined for both tasks indicates as well that an additional 9 week delay does not impact the overall project completion timeline.
Scenario 2 – Task B delayed 3 weeks: Task B has a slack value of 1; therefore, any delay beyond 1