Case Study: Avoiding Failure

Superior Essays
Avoiding Failure (Chuck Rambo)

As mentioned previously, the Coast Guard encountered many setbacks and failures during the Deepwater Horizon project. How can they avoid these identified miscalculations?

The Coast Guard did not follow their best practices and used unreliable life-cycle cost estimates. Using best practices, the foundation of any project, the Coast Guard would have managed the project within the agreed upon cost and guidelines. Additionally, the Coast Guard allowed the contractors to set the estimates and control the price, which got away from them and over ran the budget. They should have followed their own best practices and the four characteristics of reliable estimates: 1) well-documented, 2) comprehensive, 3) accurate,
…show more content…
By not doing so, labor, material, equipment, and funding requirements do not provide any benchmarks and the per-period cost of the project is not accurately reflected, leading to the project going over budget and wasting of scheduled resources not in use. Accurately reflecting this information will reduce the probability of the program slipping off schedule and budget. The critical path is the sequencing of the project to determine the minimum and maximum time needed for an operation. The Deepwater project did not develop and accurate program schedule, therefore, no critical path was determined. Failing to do determine the critical path put the management team at a significant disadvantage and unable to monitor activities that may have a detrimental effect on the project down the road. Developing an accurate project schedule and identifying the critical path will help identify issues downstream and provide timing and space for any …show more content…
The Coast Guard and Northrup Grumman stated that risk analysis was not part of the contract and therefore the responsibility to identify risk fell through the cracks. Also, failing to identify risk decreases the likelihood of meeting milestones and these failures add up and cause a breakdown in the project scheduling. The comprehensive schedule risk analysis is an essential tool for decision makers (page 76). This will allow the project manager to see across the breadth of the project and determine if scheduled activities will meet the completion date. A schedule risk analysis will calculate schedule reserves, which can be set aside for those activities identified as high risk. Without this reserve, the program faces additional delays to the scheduled completion date (page 76). Conducting schedule risk analysis, properly identifying the risk to the project timeline and milestones, and building in reserves, will reduce the overall risk to the project and keep it

Related Documents

  • Decent Essays

    Coast Guard Oil Spillsage

    • 252 Words
    • 2 Pages

    A benefit versus cost analysis of the United States Coast Guard Oil Prevention Spill program, concluded that efforts to reduce oil spills pays off. Resources allocated to safer working conditions and optimal maintenance suggest that reduced environmental damages could total 3.5 million dollars saved, 1.5 million saved in cleanup costs and approximately 1 million dollars of oil saved. Various ways to prevent oil spillage are the assessment of the technology used in transport and drilling, preparation of response training, improved surveillance of operations, and increased awareness of the dangers of all types of spillage. The primary technique is the mechanical containment and recovery of oil to collect, contain and recover spillage. The primary…

    • 252 Words
    • 2 Pages
    Decent Essays
  • Superior Essays

    INFO498 Final Case Studies Name:_Chris Harlan____ Instructions: Your essays will be graded on content to include grammar and spelling. Each case should take 1-2 pages including diagrams. The essay answers for both #2 and #3 should be 500 to 700 words each, in order to completely answer the questions. Please submit as one document.…

    • 1517 Words
    • 7 Pages
    Superior Essays
  • Improved Essays

    then the risks are documented, this ensures that the project team are aware of the risks and are able to anticipate and respond to them in an adequate manner (Project Management Institute, 2013). For this risk management plan we will identify 15 positive and negative risks. Positive risks are risks that are seen as opportunities as opposed to a threat to the project as we see with negative risks (Project Management Institute, 2013). we will use brain storming as well as checklist analysis to determine the possible risks that are associated with this…

    • 1584 Words
    • 7 Pages
    Improved Essays
  • Decent Essays

    Nortel Case

    • 440 Words
    • 2 Pages

    1. Financing risk – Probability that the taxpayers’ investment in the network (e.g. CRTC deferral account) will not provide the benefits expected. Analysis: In my view, the likelihood of this risk to occur was medium to high given that one of the Nortel’s top executive had failed ten years earlier implementing a similar initiative. In addition, risk # 5 increases the probability of this scenario to occur.…

    • 440 Words
    • 2 Pages
    Decent Essays
  • Great Essays

    Deepwater Program Failure

    • 1527 Words
    • 7 Pages

    The Deepwater Program provides an example of what can happen when performance requirements are not properly developed and managed. Departmental reviews in 2007 found there was lack of clarity in performance specifications. In the case of the NSC, for example, performance specifications caused significant disagreements within the Coast Guard. During phase 2 of the contract award, design standards were converted to guidance, and this decision permitted industry teams to select their own alternative standards.…

    • 1527 Words
    • 7 Pages
    Great Essays
  • Improved Essays

    Montreal Failure Essay

    • 973 Words
    • 4 Pages

    The biggest reason why Montreal had to suffer through this project was because Drapeau did not value risk management at all. Identifying feasible risks for a project during its planning phase is crucial because it gives all of the stakeholders an opportunity to address what predictable threats there are for the project. Thereafter, mitigation strategies can be generated respectively. And contingency plans are also there to reduce the potential consequence due to failed mitigation strategies.…

    • 973 Words
    • 4 Pages
    Improved Essays
  • Brilliant Essays

    The critical path of a project is the longest route that must be taken to reach the completion of the…

    • 1893 Words
    • 8 Pages
    Brilliant Essays
  • Improved Essays

    Risk management can work in both a positive and a negative focus based upon the risk. Some risk can be exploited thus enhancing the value of the project while another risk must be avoided if possible. (Mulcahy et al., 2013, p. 408) 3. When looking at risk; we must answer four major questions. The probability of the risk occurring, outcomes if the risk occurs, what impact will the risk have on the overall project and the frequency of which the risk may occur or has happened in past projects.…

    • 4985 Words
    • 20 Pages
    Improved Essays
  • Improved Essays

    There are three alternatives that serve as the best course of action to solve the problem at hand which is, the people making key decisions underestimated the complexity and risk involved which contributed to the DIA project being initiated too late. The key decision makers had a limited understanding of what was involved and lacked the necessary knowledge and expertise to advise appropriately and make good decisions. That lack of knowledge, combined with the fact that expert advice was routinely ignored, were part of the failure mode. Proper risk management planning would have allowed the PMT to decide how to approach and plan activities in the project plan better such as accurately estimating the complexity of the project in addition to the effort involved or that needed to be involved. Performing the necessary planning to address the risk of not having the necessary knowledge resources in place and involved in the appropriate project deliverables and decisions that were made is a key factor.…

    • 531 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    Identifying and managing risks is a critical responsibility of project managers. Risk is defined as the probability of a specified threat and the subsequent impact that the event produces (Vaidyanathan, 2013). Risks can also bring about either positive or negative outcomes for a project or organization. A project manager must identify potential risks and evaluate each one to determine the severity and likelihood of each event. Only by completing the risk management process, a project manager can determine what approach would work best to avoid, mitigate, and/or transfer the risk.…

    • 730 Words
    • 3 Pages
    Improved Essays
  • Improved Essays

    Given the complexity and scope of a utility company such as Velco, finding projects is not a problem. The abundance of choice can be seen as a positive or a negative. There is the freedom to choose what projects to work on, but there can also be choice overload. Project opportunities, at times, can seem unsurmountable. However, with a process set in place they become easier to actualize and complete.…

    • 1053 Words
    • 5 Pages
    Improved Essays
  • Improved Essays

    Case 11.1 Dangerous Stratagems According to the Webster dictionary, stratagems is a plan or scheme, especially one used to outwit an opponent or achieve an end.” In the US, federal budget cycle go through many stages before e it is approved. It is executively prepared and then the legislative go over it then approve it, the n the budget is executed and audited. The purposes of budgeting is to give a clear future expenditure.…

    • 966 Words
    • 4 Pages
    Improved Essays
  • Improved Essays

    The facilitator then discussed the risk management process so all participants understood the importance of risk identification as well as the end state of the process. Since having a large quantity of risks to analyze is important, participants were encouraged to bring up any relevant ideas, regardless of how unlikely or unconventional. Additionally, having a diverse group of participants allowed for the development of a very thorough list of risks due to the diversity of the participants’ experience. To aid in the generation of risks the schedule referenced in Appendix A was printed on a plotter and displayed during the session. As ideas were generated and discussed, risk events and impacts were annotated on the schedule at the period they were expected to occur in addition to being annotated on a spreadsheet.…

    • 1240 Words
    • 5 Pages
    Improved Essays
  • Superior Essays

    Between success and failure lies a very thin line, so thin that companies become vulnerable in thinking that a failed opportunity equates to the downfall of their brand. Some companies may even assume a misstep in their strategic initiatives could be the death of their company. That distance between success and failure, while not very far apart, encompasses a grey area that includes the painstaking but valuable takeaways derived from failing to meet a desired or perfected outcome. The case study titles Increase Your Return on Failure takes a deeper look into the ways in which a company can choose to learn from its past occurrences, and moreover, how a company builds upon their mistakes and instills key values from missed or failed opportunities to improve their future.…

    • 1398 Words
    • 6 Pages
    Superior Essays
  • Improved Essays

    Risk management is a critical element of all projects. Boeing can do so by identifying the risk then prioritising the risks based on its risk of occurrence and impact then make a plan to reduce and hopefully avoid such risks. The project will have a higher chance of being successful when the risks are anticipated prior to their occurrence. In May 2015 Boeing found that their engine would automatically shut down due to long use of the engine. This is extremely dangerous to many lives if they don’t have a backup…

    • 862 Words
    • 4 Pages
    Improved Essays