Wind general: types of coverage |
Serial Loss, Offshore Logistics, Lack of Wind
|
|
Wind serial loss: Cover
|
Retrofits, Supplier's warranty failure, Availability guarantee (onshore only), Multi-year
|
|
Wind serial loss: Retrofits: Due to which cause
|
Faulty workmanship, fautly material, faulty design (also if done by supplier)
|
|
Wind serial loss: Example for suppliers of components
|
Gearboxes, rotor blades, mast components
|
|
Wind serial loss: Start / End of cover
|
Start: Beginning of production year, End: End of guarantee period (max 5 years)
|
|
Wind serial loss: Possible insureds
|
Component manufacturers, WPP manufacturers, Developers large offshore parks
|
|
Wind serial loss: Multi-year cover "special"
|
Policy cannot be cancelled post-loss
|
|
Wind serial loss: Allocation of serial loss
|
All to one financial year, hence annual deductible eroded once
|
|
Wind serial loss: Availability guarantee: For who
|
Onshore only
|
|
Wind serial loss: Availability guarantee: What is it
|
Guarantee that WTGs work and deliver if weather conditions are that way. If not (stopped for repairs or broken), then substantial indemnification payments
|
|
Wind serial loss: Offshore cover special
|
Logistics costs: Special ship, crew
|
|
Wind serial loss: Offshore cover exclusion
|
Adverse weather delays
|
|
Wind offshore logistics: Parameters leading to delay
|
Wind speed, current, wave height
|
|
Wind offshore logistics: Costs per day of delay jack-up barge
|
Up to € 100,000
|
|
Wind offshore logistics: Cover of offshore logistics
|
Additional costs for overrunning of project period (incl weather buffers) per day
|
|
Wind offshore logistics: Reasons covered for overtime
|
Discontinuation due to bad weather, missed weather windows due to incorrect forecasts,discontinuation ordered by captain, accidents on board an machinery breakdown
|
|
Wind offshore logistics: Discussion points for cover
|
Weather related trigger (loss event), project planning and time buffers (deductible) rates for ship and crew (indemnification)
|
|
Wind lack of wind: Variables influencing modelled turnover
|
Historic wind speet at hub level, turbine's performance curve for entire windfarm, stipulated price per MWh
|
|
Wind offshore logistics: WOW - meaning
|
Wait on weather
|
|
Wind offshore logistics: CTP - meaning
|
Call to port
|
|
Wind offshore logistics: Significant wave height definition
|
Half wave = deviation from average sea level
|
|
Wind offshore logistics: Limit
|
Approx. 95% of probability of max. project length
|
|
Wind offshore logistics: Availability guarantee
|
Guarantee that WTGs work and deliver. If not (stopped for repairs or broken), then substantial indemnification payments
|
|
Wind operations and maintenance: Period
|
Multi-year (up to 10 years)
|
|
Wind operations and maintenance: Cover
|
Repair of major components
|
|
Wind operations and maintenance: Prerequisite production
|
Due dilligence of WTG production
|
|
Wind operations and maintenance: Prerequisite cover period
|
Third party inspection
|
|
Wind operations and maintenance: AAD function
|
AAD adds up year to year, only decreased by claim |