when the Owner hires an
Architect or a firm to coordi- nate the WHOLE RANGE of CAS, this Constitutes Project Management. Involves Management Acti- vities over & above the normal Architectural & Engineering (A&E) Services operates as a member of an Owner-Architect-Engineer- Contractor Team TIME, COST & QUALITY |
Project Management (PM)
2 - 5 % Estimated Project Cost |
|
*The presence of a PM does not relieve the
Designers & Contractors of their respective normal duties & responsibilities in the design & construct- ion of a Project. He COMPLEMENTS the functions of the Architects, Engineers and Contractors in meeting the broad and complex requirements of Projects. |
null
|
|
regular consultations with
the Owner & with the Archi- tects & Engineers on all aspects of planning for the Project. |
Pre-Construction Phase
|
|
If the PM also serves as the
CM to oversee time, cost, & quality control during the Construction of the Project, he shall provide the services detailed under SPP 204a and/or 204b |
Construction Phase
|
|
If a PM is hired by Owner:
a. hire the CM to be paid by him or directly by the Owner on Salary or on % of PCC, or b. to serve as the CM himself c. The FTS can either be a staff member of the PM or hired by the Owner. |
A Team of Professionals:
1. Architects 2. Engineers 3. Market Analysts 4. Accountants 5.General Contractors 6. Real Estate Consul- tants 7. Sociologists 8. Planners 9. Bankers 10. Lawyes |
|
Plan / Design of the Project
|
Architect & Specialist
Consultants (SCs) |
|
repective Engineering Plans
|
Engineers
|
|
His men & equipment & the
delivery of the Project |
Contractor
|
|
Decisions on the Project &
Funds are available |
Owner
|
|
Overall Cost Control
Plan, Program & monitor t various activities, act as an adviser on Material Costs Construction methods. |
Project Manager (PM)
|