PMS was developed to provide the "organizational level" with the tools to ____, ________, ___ _______ planned maintenance effectively.
|
plan, schedule, and control
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-1 PURPOSE |
|
What entities are responsible for the for the accountability and distribution of PMS documentation?
|
The Fleet Technical Support Centers, Atlantic/Pacific (FTSCLANT/FTSCPAC).
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-2 SCOPE |
|
How does a Ship's 3-M PMS keep equipment or systems from becoming inoperable?
|
1. Maintain equipment within specifications through preventive maintenance.
2. Identify and correct potential problems. |
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-3 OBJECTIVE |
|
The Commanding Officer is responsible to ______ that the 3-M System functions effectively within the command and the ship's maintenance is accomplished following 3-M System and quality maintenance procedures.
|
ensure
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.1 Commanding Officer |
|
The Executive Officer is the Ships' 3-M System manager and is responsible to the Commanding Officer for the _______ __________ of the Ships' 3-M System program.
|
overall management
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.2 Executive Officer |
|
The 3-M System Coordinator is the functional manager of the 3-M System and is responsible to the Executive Officer for the System and is responsible to the Executive Officer for the ____________ ___ ______ ___________ of all administrative facets of the Ships' 3-M System program.
|
coordination and direct supervision
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.3 3-M System Coordinator |
|
Each Department Head is responsible to the ___ _______ for the effective operation of the 3-M System within the department.
|
3-M Manager
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.4 Department Head |
|
From what officer and or enlisted ranks can a Department Head assign to the position of Departmental 3-M Assistant?
|
1. Officers
2. Chief Petty Officers 3. First Class Petty Officers |
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.5 Departmental 3-M Assistant |
|
The Division Officer assists in ________ ___ ___________ required for the equipment within division responsibility.
|
managing the maintenance
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.6 Division Officer |
|
"Group Supervisors" are Chief Petty Officers who are responsible to the Division Officer for the proper performance of the 3-M System functions within ________ ____ _______.
|
multiple Work Centers
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.7 Group Supervisor |
|
A Work Center Supervisor is responsible to the Division Officer via the Group Supervisor, if applicable, for the _________ _________ of the 3-M System within his/her respective Work Center.
|
effective operation
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.8 Work Center Supervisor |
|
A Work Center Supervisor is responsible for maintaining a detailed working knowledge of all _________ ____________ within the Work Center.
|
equipment deficiencies
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.8 Work Center Supervisor Work Center Supervisor responsibilities are: |
|
Maintenance personnel are responsible to the ____ ______ __________.
|
Work Center Supervisor
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel |
|
One of a maintenance personnel's 3-M System duties is to perform assigned scheduled maintenance requirements using ____, ____, and ____ as indicated by the weekly schedule.
|
MRCs, TGLs, and EGLs
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
What does the acronym MRC stand for?
|
Maintenance Requirement Card
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B LIST OF ACRONYMS APPENDIX E M MRC |
|
What does the acronym TGL stand for?
|
Tag Guide List
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B LIST OF ACRONYMS APPENDIX E T TGL |
|
What does the acronym EGL stand for?
|
Equipment Guide List
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B LIST OF ACRONYMS APPENDIX E E EGL |
|
During a PMS, if a 3-M Maintenance personnel discovers that tools, materials, or other items prescribed by the MRC are not available, then he or she should promptly notify the ____ ______ __________.
|
Work Center Supervisor
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
When performing PMS, promptly notify the Work Center Supervisor when anything on an MRC is not fully __________.
|
understood
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
When performing PMS, promptly notify the Work Center Supervisor when anything on an MRC appears to be _________.
|
incorrect
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
When performing PMS, promptly notify the Work Center Supervisor when anything on an MRC cannot be accomplished as _______.
|
written
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
When performing PMS, promptly notify the Work Center Supervisor when any doubt exists about __________, ________, or __________ to properly perform the maintenance requirement as prescribed.
|
capability, training, or experience
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
When performing PMS, promptly notify the Work Center Supervisor when factors exist which would make performance of the maintenance requirement ______ or _________.
|
unwise or dangerous
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
When performing PMS, promptly notify the Work Center Supervisor when equipment ____________ or __________ are discovered.
|
deficiencies or casualties
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
Inform the Work Center Supervisor when planned maintenance requirements are completed and sign the ______________ ___.
|
accountability log
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
The Work Center Supervisor must be informed of any ________ encountered under current schedules and/or MRCs.
|
problems
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel Their 3-M System duties include |
|
When performing corrective maintenance repair notify the Work Center Supervisor of the _______ of the corrective action.
|
details
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel When performing corrective maintenance (repair): |
|
When performing corrective maintenance repair particular attention must be given to the _____ ____ and remarks/description entries.
|
cause code
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-4 SHIPBOARD 3-M ORGANIZATION AND RESPONSIBILITIES 1-4.9 Maintenance Personnel When performing corrective maintenance (repair): |
|
The PMS Master File contains information relative to PMS requirements for specific _________ for which the command is responsible.
|
equipment
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-5 PMS FUNCTIONAL OPERATIONS 1-5.1 PMS Master File The master contains, but is not limited to: |
|
The PMS Master file contains, but is not limited to: additional instructions, information, and data provided to assist in ______________ and ______________ of PMS.
|
implementation and accomplishment
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-5 PMS FUNCTIONAL OPERATIONS 1-5.1 PMS Master File The LOEP is a part of the PMS Master file and contains: |
|
The LOEP provides a listing of the ____ assigned to each Work Center.
|
MIPs
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-5 PMS FUNCTIONAL OPERATIONS 1-5.1 PMS Master File The LOEP is a part of the PMS Master file and contains: |
|
The LOEP provides a listing of the system equipment that does ___ require PMS.
|
NOT
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-5 PMS FUNCTIONAL OPERATIONS 1-5.1 PMS Master File The LOEP is a part of the PMS Master file and contains: |
|
The LOEP's Report Date is the date the LOEP was ________.
|
produced
|
NAVAL SEA SYSTEMS COMMAND INSTRUCTION
November 13, 2003 SHIPS’ MAINTENANCE AND MATERIAL MANAGEMENT (3-M) MANUAL NAVSEAINST 4790.8B Planned Maintenance System (PMS) SECTION I CHAPTER 1 1-5 PMS FUNCTIONAL OPERATIONS 1-5.1 PMS Master File The LOEP is a part of the PMS Master file and contains: |