• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/23

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

23 Cards in this Set

  • Front
  • Back

What is the date for completion?

The date fixed and stated in the contract particulars

How does this differ from the completion date?

This is the date for completion or any other date that is subsequently fixed (i.e. after an EOT)

What does it mean when ‘time is at large’?

There is no fixed completion date
The contractor must only complete the works in a reasonable time

What is practical completion?

When the employer takes back possession of the works

What is sectional completion?

The completion and handover of the works to the employer in agreed stages

Do the works have to be totally completed before practical / sectional completion is achieved?

Practical completion is a vague concept
It is not defined in JCT
It is reliant on the architect’s opinion that the works are complete
It should not be conditional
It is common practice for PC to be granted when the works are substantially complete – i.e. there may be minor defects or omissions BUT nothing that would prevent the employer taking occupation


Can the PC certificate be rescinded once issued?

No

What is the recourse if the contractor disagrees with the architect that the works are not completed?

Adjudication

What are the consequences of practical / sectional completion?

Half of the retention is released
The Rectification Period begins
The contractor’s responsibility for insuring the works (if applicable) ends
Contractor’s liability for liquidated damages ends
The employer is now responsible for any damages to the works

What is partial possession?


Where the employer requests and the contractor consents to the employer taking possession of the works / part of the works before the date for practical / sectional completion?


What is the difference between partial possession and sectional completion?


Sectional completion is a contractual obligation to hand over the section at the stated date, partial possession relies on the contractor’s consent

What does the architect have to do at partial possession?

Issue to a written statement to the contractor showing the relevant part and stating relevant date

What are the consequences of partial possession?

For the relevant part practical completion is deemed to have occurred on the relevant date
Therefore the same consequences follow
In addition, the liquidated damages for the works / that section are reduced by the proportion that the value of the relevant part relates to the contract / section sum


What is the rectification period?

The contractor has an obligation to make good any defects, shrinkages or other faults that arise during this period of time

How long is it?

The default position is 6 months
BUT it is common to amend this to 12 months – so the building is observed in all seasons

How can the architect get the contractor to fix the defects that arise during this period?

No later than 14 days after the end of the Rectification Period the architect must issue a written statement to the contractor detailed all of the defects that have arisen and need to be made good

How quickly does the contractor have to fix the defects?

Within a reasonable time

Can the architect get the contractor to fix defects faster or within the Rectification Period?

Yes, they can issue an AI to get them to fix ‘forthwith’ e.g. if serious defect – leaking pipe etc that cannot be left until the end of the Rectification Period

What is the certificate of making good?

Issued by the architect to certify that all of the defects that have been required to be made good by the contractor have been so

What are the consequences of the issue of the certificate of making good?

The remaining retention is released

What is a non-completion certificate?

Issued by the architect to certify that the works / section have not been completed by the relevant completion date

What are the consequences of a non-completion certificate?

The employer has the right to withhold liquidated damages, as long as a withholding notice has been given

What are the consequences of a non-completion certificate?

Interim certificate
Practical completion / sectional completion certificate
Non completion certificate
Certification of Making Good
Final Certificate