• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/80

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

80 Cards in this Set

  • Front
  • Back
flange
Horizontal elements of wide flange beam
Modulus of Elasticity
slope of stress/strain curve=E
z-arm
distance between two opposite forces in bending and shear
2/3 d (where D = depth)
web
vertical element of wide flange beam
wide-flange section (W)
cross section of efficient beam-reduces area (I) while maintaining strength
plate girder
Built up steel section; beacause it is so big
chord-top and bottom
flanges in a truss
T-beam
cross section used in concrete-material in compression
composite material
material or structure made up of more than one element

reinforced concrete
Glulam
method for wood construction
layers of glue and smaller members to create a stronger structural element
moment capacity envelope
diagram showing rectangular elevation with moment curve and extra material, used to create more efficient beams
bond stress
stress of rebar on concrete which prevents sliping
shear key
keys on rebar to keep it from slipping out of concrete
development length
length of rebar needed to develop total tension capacity in concrete (not in steel because no tension in steel)
hook
in short beams where capacity is reached before development length
compression reinforcing
reinforcing for negative moment (on compression side)
compression flange buckling
lateral buckling in unsupported compression flange
braced compression flange
mechanical connections-floors on top of beams, spot weld-connections that keep top flange from moving, buckling
unbraced compression flange
susceptible to compression flange buckling
lateral buckling
buckling due to lateral load
lateral moment of inertia
stiffness of cross section with lateral load (y-axis) in normal cross section Ix>Iy
lateral rigidity
resistance to lateral load
open section
T section or W section
closed section
box beam
spandrel beam
beams on ends of structure, load on one side only-
section has rotational force applied along its axis-
box beam better for spandrel
deflection
PL/EI
hinge, pin, shear connections
not fixed connections-don't develop moment
shear tab
steel plate that connects beam in shear, pin, hinge connections
cantilever
beam supported on one side only
acts as lever
beam acts shorter (less deflection)
balanced section
smallest cross section you can use in a beam
positive moment=negative moment
1/3 original span on either side
1/5 of total length
50% more span without decreasing cross section
Draw the elevation fo a simply-supported, uniformly-loaded rectangular beam whose section varies with respect to its bending stresses. What are the shear stress implications of such a profile

Why is a simply-supported constant cross section beam said to be "inefficient?" Show 2 possible methods to achieve a moe efficient member in each material: steel, wood, concrete
sheer increased-make sure you have capacity for shear
Draw the moment capacity diagram for the reinforced concrete beam shown on the board:
------
/ \
-- --
/ \
What two methods are used to anchor steel rebar in a concrete beam?
epoxy & shear key
List Six Factors that effect a beam' deflection:
PL/EI
1.)load
2.)length
3.)modulus of Elasticity
4.)moment of intertia
5.)types of connection
6.)post/pretenstion
Does the addition of an overhang decrease or increase the efficiency of a simply supported beam? why?
increase it's a cantilever it enables you to span more distance without changing the cross section
The roof of a building is 50' wide by 200' long. If the beams are 50' long and running parallel with the 50' (transverse) direction at a 25' spacing, what column spacing will require the smallest beam section if only two columns are used to suppor each beam?
30'
Show two methods of constructing a cantilever in steel and two ways in wood.
butt joint, continuous floor,triangular, clamped beam and clamped column (needs to be continuous
what architectural design advantage does cantilevering the floor at the exterior offer in a multistory highrise building? what is the corresponding interior planning ramification of this technique?
increase length-1/3 more floor area, decrease section
Can draped pre-stressing tendons be pre-tensioned? Why?
No. Cause they are draped.they would then have to be pre-tension before
What is the difference between bonded and un-bonded post-tensioning?
epoxy and no epoxy
Draw where the strands should be located for maximum efficiency in a simple-span beam that is pre-tensioned; post-tensioned:
in pretensioned_at the bottom of the beam pulled taut.

in post-tensioned draped along moment curve and then pulled taught to creat a camber.
why are the top surfaces of precast concrete floor elements typically finished with a rough surface?
to enable another pour of concrete for bonding
what purpose does a bearing pad under a precast concrete floor plank serve?
column doesn't crush by tension of beam.
In detailing the connection between an interior poured concrete bearing wall and the precast concrete hollow core floor planks bearing on it from both sides, what two items are critical to remember to specify
bearing pad, chamfer

protects column from being crushed from the deflection of the beam.
Briefly explain two reasons why the architectural design and structural/ construction concept of the Montreal 1976 Olympic Stadium (not the tower) were not complimentary:
No tension ring --► cantilever. slope different
Why are fixed connections very hard to achieve in a wood structure?
can't weld-no butt joints
What is necessary in the detailng of a fixed connection between:

a.) 2 steel WF sections
b.) a cold joint between two pours of a reinforced concrete member
a.)2 webstiffners...le box
b.)running rebar
Draw the bending stress diagrams for a steel rectangular section at the following loading stages: design limit, elastic limit, half plastic moment, full plastic moment.
safety
/

yield limit

+/

half-plastic moment
_/
elastic moment
_|
Where is it necessary to check for the need of lateral bracing along the length of the fixed end beam shown on the board? why?
compression flange buckling
What two additional costs are incurred when a building's structure is exposed to the exterior elements if it has a fixed connections?
thermal expansion, thermal transfer, thickened floors
prestressing
prestressing introducing stress before the beam is loaded
pretension
a type of prestressing. tensioning rebar before concrete is poured
post-tension
a type of prestressing. tensioning rebar after concrete has set
prestressing strand
post-tensioning strand
cable rod
precast concrete
concrete that is poured and then put into place
precast floor plank (solid, hollow)
concrete cast before put into place with tongue and groove joint to join in construction. and gives more of a connection
casting bed
mold
steam curing
strip formwork early
camber
curve concrete slab forms after post-tensioning
bearing pad
pad that is placed beam and coulmn to prevent crushing from deflection of beam
single tee
concrete section with rebar
double tee
concrete section with rebar
bonded (unbonded) tendons
bonded=epoxy unbonded=nothing
draped tendons
rebar & cable laid out for post-tensioning
creep
time concrete sets over 2 year period after pouring
segmental post-tensioning
tensioning bit by bit

(example olympic stadium)
clevis
holds suspension cable (never fixed) it's like a yoke
HSS (Hollow steel section)
tube of steel-spandrel beams no torsion
fixed end moment
moment incurred in a fixed connection
negative moment
moment below neutral axis...compression is on the bottom
negative moment reinforcing
compression flange reinforcment
elastic limit
before yield plateau
permanent set
steel not going back on the yield plateau
plastic
state at which steel becomes after elastic
plastic hinge
after loaded past capacity.. in a fixed connection forms a mechanism after 2 hinges
plastic moment
xxx
mechanism
xxx
ductile frame
xxx
induced moment
xxx