Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
49 Cards in this Set
- Front
- Back
what are 3 reasons to take less money on a project
|
-get your foot in the door
-market yourself -keep workers working |
|
3 goals for successful completion
|
-meets owner's needs and requirements
-on time -within budget |
|
the __________ ________ ________ helps to communicate the construction plan, establish production goals, monitor and measure progress, and manage change
|
construction project schedule
|
|
what is the best way to communicate
|
the construction project schedule
|
|
what are the 4 project management objectives
|
-time mgmt
-resource mgmt -quality mgmt -risk (safety) mgmt |
|
what are the 4 project management functions
|
-planning
-scheduling -monitoring -controlling |
|
what are the only activities that don't consume time
|
milestones (start, finish etc.)
|
|
what are the 5 activity categories
|
-administration
-mobilization/demobilization -procurement -construction -start-up and testing |
|
what is a change prior to the bid
|
addenda
|
|
F/R/P concrete stands for...
|
form, reinforce, place
|
|
nature of the work, quality of work, mgmt and skill, work restrictions, and seasonal conditions are all...
|
factors affecting productivity
|
|
what are the 6 uniformat 2 categories
|
-substructure
-superstructure -services -interiors -special const and demo -equip and furnishings |
|
the minimum overall duration of the project is also known as the
|
critical path
|
|
earliest time each activity can start and finish
|
forward pass
|
|
all time on the schedule is at the end of the day in what type of construction
|
end-of-day construction
|
|
latest time that an activity can start and finish while maintaining minimum overall duration of the project
|
backward pass
|
|
forward pass
|
earliest time each activity can start and finish
|
|
backward pass
|
latest time that an activity can start and finish while maintaining minimum overall duration of the project
|
|
total float is also known as
|
project float
|
|
the time span in which the completion of an activity may occur and not delay the completion of the project
|
total float
|
|
total float
|
the time span in which the completion of an activity may occur and not delay the completion of the project
|
|
can total float be negative
|
yes
|
|
free float is also known as
|
managerial float
|
|
the time span in which the completion of an activity may delay and not delay the start of any successive activity
|
free float
|
|
free float
|
the time span in which the completion of an activity may delay and not delay the start of any successive activity
|
|
can free float be negative
|
no
|
|
definition of critical path
|
path through the network that establishes minimum overall project duration
|
|
if any activity on the critical path is delayed, then...
|
the completion of the project will be delayed
|
|
PDM stands for
|
precedence diagram method
|
|
an example of a generic assignment would be...
|
"workers"
|
|
an example of a trade specific assignment would be...
|
"carpenters, laborers, finishers" etc
|
|
a daily resource usage histogram using _____ start has more activities at the end
|
late start
|
|
a daily resource usage histogram using _____ start has more activities at the beginning
|
early start
|
|
a larger quantity of resources is required in the beginning of the project and the curve of the cumulative resource usage graph's slope is greater at the beginning in a ____ start schedule
|
early start
|
|
a larger quantity of resources is required at the end of the project and the curve of the cumulative resource usage graph's slope is greater at the end in a ____ start schedule
|
late start
|
|
the ______ schedule falls in between the early start and late start curves on the graph
|
target schedule
|
|
the ideal graph of the target schedule is...
|
a straight diagonal line going between the early and late start curves
|
|
when the assigned resources exceed the available resources, solutions are to...
|
-extend planned completion date
-obtain more resources for excess periods -shift non-critical activities within the schedule |
|
what is the tool used to CONCEPTUALIZE and BUILD the schedule
|
schedule board
|
|
what is the tool to PROCESS the logic, duration and resources of the tasks
|
computerized master schedule
|
|
what should be developed as the outcome of the scheduling meeting be
|
the preliminary construction schedule
|
|
most projects are ____ constrained schedules
|
time
|
|
the type of scheduling where there is a fixed end date for project completion that must be met
|
time constrained scheduling
|
|
_______ constrained schedules are not common in construction schedules except perhaps in labor shortage areas or equipment shortage areas
|
resource
|
|
the type of scheduling where there is a shortage of available resources and the project has to be adjusted accordingly
|
resource constrained scheduling
|
|
when you attempt to keep the requirements for a construction resource as constant as possible over the duration of the project
|
resource leveling
|
|
do most firms resource load?
|
no
|
|
the leveling of one or more resource is not practical without the use of a
|
program
|
|
in automated resource leveling, the algorithms used are ____-based
|
rule
|