Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
16 Cards in this Set
- Front
- Back
Project Integration Plans |
1. Developing the project charter 2. Developing the project management plan 3. Directing and managing project work 4. Monitoring and controlling project work 5. Performing integrated change control 6.Closing the project or phase |
|
Project management knowledge areas |
1. Scope management 2. Time management 3. Cost management 4. Quality management 5. Human resource management 6. Communications management 7. Risk management 8. Procurement management 9. Stakeholder management 10. Project integration management |
|
Earned value management (EVM) components and formulas
|
integrates scope, time, and cost data.
Earned value (EV) EV + PV to date = RP Cost variance (CV) CV + EV = AC Schedule variance (SV) SV + EV = PV Cost performance index (CPI) CPI + EV /AC Schedule performance index (SPI) SPI + EV/PV Estimate at completion (EAC) EAC + BAC/CPI Estimated time to complete Original time estimate/SPI |
|
Types of Constraints |
scope, time, and cost |
|
Organizational Structures |
Functional - managers or
Project - program managers report to the CEO. earns its revenue primarily from performing
Matrix - middle ground between functional |
|
Project Management organizational structure |
Member identity Group emphasis People focus Unit integration Control Risk tolerance Reward criteria Conflict tolerance Means-ends orientation Open-systems focus |
|
PROJECT LIFE CYCLE phases |
the concept, development, implementation, and |
|
PROJECT MANAGEMENT PROCESS GROUPS and which ones intersect. |
Initiating, Planning, Executing,
Executing process, Monitoring and controlling processes overlap all group |
|
Pre-Initiation Tasks |
• Determine the scope, time, and cost constraints for the project |
|
Methods for Selecting Projects |
• Focusing on broad organizational needs |
|
WBS creation |
Scope baseline, project documents updates |
|
Finish-to-start (FS) |
Task (B) cannot start until task (A)
|
|
Start-to-start (SS) |
Task (B) cannot start until task (A) |
|
Finish-to-finish (FF) |
Task (B) cannot finish until task (A) |
|
Start-to-finish (SF) |
Task (B) cannot finish until task (A) |
|
PERT formula |
PERT weighted average = optimistic time + 4 X most likely time + pessimistic time / 6 |