• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/43

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

43 Cards in this Set

  • Front
  • Back

Which of the following should be put on CAS sheet?



1. Tools and crew members


2. Charts and diagrams


3. Parts, MSDS sheets, and project package


4. Materials, tools, and equipment

Materials, tools, and equipment

Which of the following is a major use of a level II Gantt II chart?



1. Provide an overall picture of the entire deployment


2. Coordinate the planning effort between companies


3. Provide periods where special tools are required


4. Provide material delivery dates

Provide an overall picture of the entire deployment

What does a logic network illustrate?



1. Material shortage from start to finish


2. Construction activity duration and crew size


3. Overall project duration and critical activity


4. Construction activity sequence from start to finish

Construction activity sequence from start to finish

Which of the following is a major use of logic network during the planning stage?



1. Provides indication of all activities that must be accomplished


2. Records the number of drawings for each project


3. Shows structural change


4. Lists the quantities and types of work

Provides indication of all activities that must be accomplished

Why is it important to prepare the logic network when breaking the project down into construction activities?



1. Guarantees network is completed on time


2. Ensures all items of work are included


3. Verified that quality control is implemented


4. Maintains safety on the project

Ensures all items of work are included

In the logic network, what shape is used to represent activities?



1. Octagonal box


2. Start and finish node


3. Rectangular box


4. Round node

Rectangular box

What does the forward pass equation determine?



1. Early finish and early start dates


2. Early project workday


3. Lag times


4. Duration of the activity

Early finish and early start dates

What are lag times?



1. Mandatory break times


2. Mandatory wait times between activities


3. Optional break times


4. Optional wait times between activities

Mandatory wait times between activities

What factor is determined by the backward pass computations?



1. Earliest possible start and finish dates


2. Critical path


3. Duration of the project


4. Computed float only

Earliest possible start and finish dates

Which of the following phrases best describes the critical path in a precedence diagram?



1. Construction activities that must be started on time and completed


2. Path with the most free float and the most total float


3. Longest path throughout the network


4. Path with the most total float

Construction activities that must be started on time and completed within the duration

What term is used to identify the number of days an activity can be delayed without delaying the project completion date?



1. Float


2. Allowance of time


3. Dead time


4. Total float

Total float

Which of the following statements best describes free float?



1. The number of days free during the deployment


2. The number of days an activity can be delayed without taking float away from the next activity


3. The number of days free during the project


4. The number of days off during the project

The number of days an activity can be delayed without taking float away from the next activity

When network calculations are being performed, the total float of an activity should be determined by the use of what formula?



1. Total float = late start plus early start


2. Total float = early start minus early finish


3. Total float = late start plus late finish


4. Total float = late start minus early start

Total float = late start minus early start

When calculating the start and finish dates of a project network, what logic type will give you the longest project duration?



1. Finish-to-start


2. Start-to-start


3. Finish-to-start


4. Late finish to early finish

Finish-to-start

Resource leveling involves shifting construction activity schedules to spread requirements across the time frame of the project, while __________.



1. avoiding overall project duration delay


2. rescheduling activities


3. matching construction activities


4. planning the next project

avoiding overall project duration delay

Man-day estimates are taken from what source?



1. Histogram


2. Network


3. CAS sheets


4. Level I Gantt chart

CAS sheets

On a level II Gantt chart, the scheduled progress curve is drawn by plotting the percent complete scheduled at the end of what period of time?



1. One week


2. Two weeks


3. Thirty days


4. Quarterly

Two weeks

On a level II Gantt chart, the scheduled progress curve is drawn by plotting the percent complete scheduled at the end of what period of time?



1. One week


2. Two weeks


3. Thirty days


4. Quarterly

Two weeks

Which of the following is considered an important use of the CAS sheets?



1. Control the work load


2. Control the job conditions


3. Estimate resource requirements


4. Track labor skills

Estimate resource requirements

What individual initiates local purchase actions?



1. Expediter


2. Project chief


3. MLO


4. Crewleader

MLO

Of the following Gantt charts, which is used to reflect the daily status of your project?



1. Level I


2. Level II


3. Level III


4. Level IV

Level III

The critical path on the bar chart that is posted on the job site should be hi-lighted in what color?



1. Yellow


2. Red


3. Green


4. Blue

Red

Which of the following factors, if not tracked continuously, could cause a work delay?



1. Long lead items


2. Personnel assigned


3. Tools required


4. Man-days allocated

Long lead items

If the project is behind schedule, what form is used to reflect how the team is going to get back on schedule?



1. Level I Gantt chart


2. Level II Gantt chart


3. CAS Sheet


4. Two-week schedule

Two-week schedule

A construction activity with an original estimate of 40 man-days is 25 percent complete. How many man-days are remaining?



1. 30


2. 25


3. 20


4. 15

30



25% x 40 = 10


40 - 10 = 30

Who is responsible for safety on the job site?



1. Safety officer


2. Safety chief


3. Crewleader


4. FEAD

Crewleader

What is the most common cause of project mishaps?



1. Safety chief not on job site


2. Unsafe construction practices


3. Material delay


4. Insufficient tools

Unsafe construction practices

What is the purpose of the daily stand-up safety lecture?



1. Discuss daily events


2. Ensure personnel awareness


3. Distribute routine tasking


4. Discuss project status

Ensure personnel awareness

Ground Fault Circuit Interrupters (GFCIs) should be used with what type of tools?



1. Manual


2. Pneumatic


3. Hydraulic


4. Power

Power

Guidance on the removal of asbestos can be found in which of the following instructions?



1. NAVFAC P-908


2. NAVFAC P-307


3. COM2NDNCB/COM3RDINST 11200 series


4. NCF Occupational Safety and Health Program Manual

NCF Occupational Safety and Health Program Manual

Upon completion of a project, excess project material is turned in to __________.



1. DRMO


2. MLO


3. FEAD


4. CTR

MLO

At the close of a project, the battalion is required to turn in how many sets of red-line drawings to the FEAD?



1. Two


2. Four


3. Six


4. Eight

Two

After the preliminary acceptance inspection with the FEAD, who provides the written punchlist?



1. Operations officer


2. Customer


3. FEAD


4. Project supervisor

FEAD

After the project has been accepted, the project files are closed and retained for what amount of time?



1. 6 months


2. 12 months


3. 24 months


4. 36 months

24 months

Which of the following is used primarily by the crew leader to ensure that all materials are on the job site?



1. Inventory log


2. Expediter log


3. Two-week schedules


4. MLO Log

Two-week schedules

What is the minimum number days of lead time a crew leader should provide to MLO when requesting material?



1. One


2. Two


3. Three


4. Four

Three

What is the formula for calculating the actual availability factor for your project?



1. AF = MD expended / Crew assigned x WD x MDE



2. AF = Crew assigned / WD x MDE



3. AF = Crew assigned x WD x MDE / MD expended



4. AF = MDE / MD expended x WD

AF = MD expended / Crew assigned x WD x MDE

Projects are initially laid out on a logic diagram using what type of logic relationship?



1. Start-to-finish


2. Start-to-start


3. Finish-to-finish


4. Finish-to-start

Finish-to-start

At what point during the construction project is a firm schedule set?



1. After the BEEP


2. At or about the 30-day mark


3. After the 90-day review


4. After the project start date

At or about the 30-day mark

What is the most accurate way of recording actual man-hours expended on a project?



1. Labor reports


2. Time cards


3. SITREPs


4. Bar charts

Time cards

Man-days expended directly on construction activities--in the field or the shop--are considered what type of labor?



1. Direct


2. Indirect


3. Productive


4. Overhead

Direct

When filing out a SITREP feeder, what is the formula for figuring the weighted percent for each master activity?



1. Man-day estimate divided by total project man-day estimate


2. Total project estimated man-days divided by master activity estimated man-days


3. Original estimated man-days divided by project estimated man-days


4. Project estimated man-days divided by original estimated man-days

Man-day estimate divided by total project man-day estimate



WP of MA = MD estimate / Total project man-day estimate

What is the allowable percent deviation between actual WIP and scheduled WIP for a project of 800 man-days?



1. 20%


2. 15%


3. 10%


4. 5%

10%