• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/94

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

94 Cards in this Set

  • Front
  • Back
Project Manager or Project Sponsor?

Major decision making role and participation in the sales effort and contract negotiation
Project Sponsor
Project Manager or Project Sponsor?

Prepare detailed project reports
Project Manager
Project Manager or Project Sponsor?

Provides assistance in getting the project underway by communicating processes and procedures and securing appropriate staffing
Both
Project Manager or Project Sponsor?

Liaison to executive committees and steering committees
Project Sponsor
Project Manager or Project Sponsor?

Prepare detailed project budget estimate
Project Manager
Project Manager or Project Sponsor?

Prepares performance appraisals for project team members
Project Manager
Project Manager or Project Sponsor?

Interprets company policies and communicates information about organizational process assets
Project Sponsor
Project Manager or Project Sponsor?

Becomes involved in solving major project related problems
Project Sponsor
Project Manager or Functional Manager?

Set project goals and objectives
Project Manager
Project Manager or Functional Manager?

Develop detailed task descriptions
Functional Manager
Project Manager or Functional Manager?

Communicate/Establish major milestones
Project Manager
Project Manager or Functional Manager?

Set high-level requirements
Project Manager
Project Manager or Functional Manager?

Provide detailed schedules
Functional Manager
Project Manager or Functional Manager?

Identify areas of risk, uncertainty, and conflict
Functional Manager
Project Manager or Functional Manager?

Establish ground rules and provide assumptions
Project Manager
Project Manager or Functional Manager?
Define project constraints
Project Manager
Project Manager or Functional Manager?
Provide summary status reports for the sponsor
Project Manager
Planning or forecasting?

Give a complete definition of the work
Planning
Planning or forecasting?

Lay out a proposed schedule
Planning
Planning or forecasting?

Establish project milestones
Planning
Planning or forecasting?

Determine the need for different resources
Forecasting
Planning or forecasting?

Determine the skills required for each WBS task or element
Planning
Planning or forecasting?

Change the scope of the effort and obtain new estimates
Planning
Planning or forecasting?

Estimate the total time to complete the required work
Planning
Planning or forecasting?

Consider changing resources
Forecasting
Planning or forecasting?

Assign appropriate personnel to each WBS element
Planning
Planning or forecasting?

Reschedule project resources
Planning
Which chart displays logic and dependencies?

(Gantt, GERT, Network Diagram, Pareto Diagram, Flow Chart)
Network diagram - shows dependencies
Which chart displays process steps and sequences?

(Gantt, GERT, Network Diagram, Pareto Diagram, Flow Chart)
Flow chart - complete process flow, allows for identification of gaps; effective in communicating process information
Which chart indicates project progress?

(Gantt, GERT, Network Diagram, Pareto Diagram, Flow Chart)
Gantt
Which chart displays feedback loops, conditional branches and alternative paths?

(Gantt, GERT, Network Diagram, Pareto Diagram, Flow Chart)
GERT - addresses different possible outcomes
Which chart has displays causes in order of frequency of occurrence?

(Gantt, GERT, Network Diagram, Pareto Diagram, Flow Chart)
Pareto diagram - identifies and prioritizes items that warrant immediate attention
What are is the type, WBS relationship and accuracy of a parametric estimate?

*Type - ROM, Budget, Definitive
*WBS - Top down or bottom up
*Accuracy -
(25%) - 75%
(10%) -25%
(5%) - 10%
*ROM - rough order of magnitude - no engineering estimates; may use past experience
*Top-down estimate
*Accuracy - (25%) - 75%

>Takes days
What are is the type, WBS relationship and accuracy of a analogy estimate?
*Budget
*Top-down estimate
*Accuracy - (10%) - 25%

>Takes weeks
What are is the type, WBS relationship and accuracy of a engineering estimate?
*Definitive
*Bottom up estimate
*Accuracy - (5%) -10%

>Takes months
Direct or indirect cost?
PM travel expenses
Direct
Direct or indirect cost?
Project team labor rates
Direct
Direct or indirect cost?
Equipment costs
Direct
Direct or indirect cost?
Taxes
Indirect
Direct or indirect cost?
Maintenance/janitorial
Indirect
Direct or indirect cost?
Reward and recognition of project team
Direct
Direct or indirect cost?
Company benefits
Indirect
Direct or indirect cost?
Materials
Direct
Direct or indirect cost?
Accounting services
Indirect
Direct or indirect cost?
Utilities
Indirect
Product life cycle, project life cycle or both cost?

R&D
Product
Product life cycle, project life cycle or both cost?

Production
Both
Product life cycle, project life cycle or both cost?

Construction
Both
Product life cycle, project life cycle or both cost?

Operation and Maintenance
Product
Product life cycle, project life cycle or both cost?

Product Retirement
Product
What is the revised estimate for the final cost at the completion of the project?

PV, EV, AC, BAC, SV, CV, EAC, ETC
EAC
How much money was expended thus far
AC
How much physical work was actually accomplished thus far
EV
How much money was originally budgeted
BAC
From where we are today, how much money is needed to complete the work
ETC
By how much have we deviated from the schedule baseline, favorably or unfavorably
SV
By how much have we deviated from the cost baseline, favorable or unfavorably
CV
What is the planned cost or value of the work accomplished thus far
PV
What factors are associated with a management reserve?

Labor rate escalations
Estimating Errors
Overhead Escalations
Material Price Escalations
Workmanship errors
Flood, natural disaster
Scope changes
Previously documented schedule delays
Management reserves are intended for unknown unknowns that cannot be planned or anticipated for.
What factors are associated with a management reserve?

Labor rate escalations
Estimating Errors
Overhead Escalations
Material Price Escalations
Workmanship errors
Flood, natural disaster
Contingency reserves deal with known unknowns; issues and risks that can be planned for.

Scope changes
Previously documented schedule delays
What metrics answer the question, "Where are we at today"?

PV, EV, AC, EAC, ETC, VAC, SPI, CPI
PV, EV, AC
What metrics answer the question, "Where will we end up?

PV, EV, AC, EAC, ETC, VAC, SPI, CPI
EAC, ETC, VAC, SPI, CPI
Which terms belong in a progress report?

PV, EV, AC, EAC, ETC, SPI, CPI, SV, CV
PV, EV, AC
Which terms belong in a status report?
SV, CV
Which terms belong in a forecast report?

PV, EV, AC, EAC, ETC, SPI, CPI, SV, CV
EAC, ETC, VAC, SPI, CPI
Is this risk response Assumption/Acceptance, Transfer, Mitigation, Avoidance?

"I know we have three different designs we can select from in order to satisfy the customers’ requirements. However, I am very reluctant to consider the second option, because if we are wrong, there exists the chance of imminent damage to the project”
Avoidance
“This design has a very high possibility of creating a severe financial problem for us. I have asked the design team to develop an alternate that will minimize our risk exposure”
Assumption/acceptance
“I know we can manufacture the product ourselves, but there are a number of potential risks to consider. I would rather award a fixed-price contract to Alpha company and have them do the manufacturing instead. They have a strong record of success in this area”
Transfer
“I have set up a management reserve just in case there are escalations in the costs of the raw materials we must purchase”
Mitigation
“There is a strong possibility that one of my team members may leave the project for better paying job assignment so I have added an end of project bonus to retain the employee”
Mitigation
“I have arranged for an insurance company to handle any direct property damage and any worker injuries during the project”
Transfer
“We have assessed the risk and are aware that it may occur within the next phase of the project. We have developed a contingency to manage the risk of it occurs”
Assumption/acceptance
Who has more risk - buyer or seller?

Cost + percentage of cost
Buyer
Who has more risk - buyer or seller?

Fixed price with economic price adjustments?
Seller
Who has more risk - buyer or seller?

Fixed price incentive fee
Seller
Who has more risk - buyer or seller?

Cost plus incentive fee
Buyer
Who has more risk - buyer or seller?

Time and materials not to exceed certain amount
Seller
Who has more risk - buyer or seller?

Cost plus fixed fee - in dollars
Buyer
Who has more risk - buyer or seller?

Cost plus award fee - %
Buyer
Who has more risk - buyer or seller?

Firm fixed price
Seller
Who has more risk - buyer or seller?

Cost sharing
Buyer
Who has the greatest risk in a firm fixed price or lump sum contract?
Seller
Who has the greatest risk in a cost plus contract?
Buyer
Who has the potential to benefit from a cost plus incentive fee contract?
Seller & Buyer
In a cost plus fixed fee contract, who pays for all project costs?
Buyer
In the cost reimbursable type contracts, who generally has the greatest risks?
Buyer
The cost plus percentage of cost contract reduces the motivation of the _____ to complete the contract and may result in enormous cost to the _____
Seller, buyer
An almost bottomless pit of funds whereby the seller is reimbursed all costs as well as a profit for all the money spent

Firm fixed price, cost plus incentive fee, fixed price incentive fee, cost sharing, cost plus percentage of cost, cost plus fixed fee, cost plus award fee
Cost plus percentage of cost (CPPC)
A sharing formula for the costs above and below a target as well as a ceiling and floor on profits
Cost plus incentive fee (CPIF)
A profit fixed in dollars rather than percent
Cost plus fixed fee (CPFF)
A profit based upon how well the buyer likes the end result
Cost plus award fee (CPAF)
A contract which does not allow for profits and where the seller pays part of the cost
Cost sharing (CS)
A contract with a point of total assumption
Fixed price incentive fee (FPIF)
A contact where the maximum risk resides with the seller
Firm Fixed Price (FFP)