• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/53

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

53 Cards in this Set

  • Front
  • Back
In CPM, two activity times and two __________ are specified.
costs
If deterministic time estimates are used and if project __________ are firm, there is a high likelihood that it will be necessary to crash the last few activities of most projects.
deadlines
This schedule compression technique expedites a project by overlapping the design and build phases.
fast-tracking
The __________ approach to constrained resource scheduling problems is the only feasible method of attacking the large, nonlinear, complex problems that tend to occur in the real world of project management.
heuristic
The __________ heuristic provides a general solution for critical path and time. It is usually the default rule for a schedule.
as soon as possible
Using the shortest task first heuristic method, the project team can complete the __________ number of tasks during given period of time.
maximum
The student syndrome, observed by __________, proposes that if an activity has slack time, often times the start of the task is delayed until the slack is removed.
Goldratt
The primary reason project managers are surprised by resource constraints on a project is their failure to include __________ in risk identification activities.
resource availability
The standard practice with PERT/CPM is to estimate activity times under the assumption of resource loadings that are __________.
normal
When using heuristic solutions to schedule, __________ will always take precedence.
technological necessities
The usual purpose of the __________ scheduling heuristic is to delay cash outflows as long as possible.
as late as possible
A project task is said to be system constrained if it requires a fixed amount of __________ and known quantities of resources.
time
Resource leveling aims to minimize the period-by-period variations in resource loading by shifting tasks within their ________.
slack allowances
The formula for computing the cost/time slope for each activity that can be crashed is (Crash cost - normal cost) / (crash time - normal time).
True
Most heuristic solution methods start with the master schedule and analyze resource usage period by period, resource by resource.
False
One of the most common priority rules is the longest task first.
True
Resource leveling describes the amounts of individual resources an existing schedule requires during specific time periods.
False
While standard practice and rules of thumb are sufficient for estimating the resourceneeds for normal progress, careful planning is critical when attempting to expeditea project.
True
When crashing a project, a change in technology with which something is done will change. In economics terms, this is a change in the “execution function.”
False
Resource loading aims to minimize the period-by-period variations in resource loading shifting tasks within their slack allowances.
False
In CPM, ________ are specified.
Two activity times and two costs
The standard practice with PERT/CPM is to estimate activity times under the assumption of ________.
Resource loadings that are normal
If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will ________.
Be necessary to crash the last few activities of most projects
The formula for computing the cost/time slope for each activity that can be crashed is ________.
(Crash cost - normal cost) / (crash time - normal time)
Economically speaking, crashing a project creates a technology change in the ________ for an activity.
Production function
The ________ schedule compression technique overlaps the design and build phases of a project to expedite a project.
Fast-tracking
The points between the extreme points of the relationship between time use and resource use represent ________.
Alternatives for trade-offs between time and resources
The two fundamental approaches to constrained allocation problems are ________.
Heuristic approaches and optimization models
The ________ approach to constrained resource scheduling problems is the only feasible method of attacking large, nonlinear, complex problems that tend to occur in the real world of project management.
Heuristic
Most heuristic solution methods start with the ________ and analyze resource usage period by period, resource by resource.
PERT/CPM schedule
When using heuristic solutions to build a schedule, ________ will always take precedence.
Technological necessities
The ________ heuristic provides a general solution for critical path and time. It is usually the default rule for a schedule.
ASAP
The usual purpose of the ________ scheduling heuristic is to delay cash outflows as long as possible.
ALAP
If a date-constrained project is scheduled from the ending date constraint using the ALAP heuristic, the following effect will be observed in the network..
Each activity will have zero slack and be located on the critical path
The methods to find an optimal solution to the constrained resource scheduling problem fall into two categories. They are ________.
Mathematical programming and enumeration
A project is said to be ________ if all three variables --- time, cost, and specifications --- are fixed by the project sponsor.
overdetermined
A project task is said to be ________ if it requires a fixed amount of time and known quantities of resources.
system constrained
________ describes the amounts of individual resources an existing schedule requires during specific time periods.
resource loading
________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.
resource leveling
________ refers to the amount of time beyond the project’s due date or beyond the expected delivery date required to complete the project.
schedule slippage
Three important parameters used to assess the effectiveness of a scheduling system include schedule slippage, in-process inventory, and ________.
resource utilization
With respect to project scheduling, ________ is the amount of work waiting to be processed because there is a shortage of some resource.
in-process inventory
Work = duration * units. Given that task A will use three carpenters and have duration of six days, task A requires ________ days of work.
18

18 days = three resources * six days.

The number of work periods required to complete the work effort for an activity is its ________.
duration
Given a scheduling equation W = D * U, if the equation for task A is initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are ________.
D = 8d

In an effort-driven task, W is held constant when resources are changed. Therefore, 40 days of work spread among 5 resources should require 8 days instead of 10 days to complete the job.

Given a scheduling equation W = D * U, if the equation for task J is initialized so that W = 20d, D= 5d, and U = 4 resources, and task J is a non-effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are ________.
W = 25d

In a non-effort-driven task, D is held constant when resources are changed. Therefore, 5 days of duration spread among 5 resources should require 25 days instead of 20 days of effort to complete the job. Adding resources to a non-effort driven task will not decrease duration.

Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. If Bob was 100 percent available to work on task R during the entire five days, his efficiency rate is ________%.
80

Work / duration = efficiency if the resource is 100 percent available over the entire duration.

Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. Bob was expected to be 100% available to work on task R during the entire five days. However, Bob left the company and will be replaced by Sam. Sam’s efficiency rate is 90%. If Sam is only 70% available, Sam will require ________ hours to complete task R.
50.8

(32 hours of work) / (70 percent availability * 90 percent efficiency) = 50.8 hours for duration.

Describe the extreme points of the relationship between time use and resource use.
If the project is time-limited, it will seek to use as few resources as possible but will be constrained by time. If the project is resource limited, it will seek to finish as soon as possible but will be resource constrained. The points between these two extremes represent time/resource use trade-offs available to the project manager.
Discuss the advantages obtained from resource leveling.
First, less hands-on management is required if the use of a given resource is nearly constant over its period of use. Second, if resource usage is level, the project manager may be able to use a just-in-time inventory policy without much worry that the quantity delivered will be wrong. For human resources, leveling can improve morale and lead to fewer problems in the personnel and payroll offices due to increasing and decreasing labor levels. Moreover, the leveling of resources tends to level costs. And since hiring and layoff costs can be significant, leveling can minimize such costs.
Describe the basic procedure for resource leveling.
Identify the type and quantity of resources that are required to complete activities in the network. Once the logical relationships between tasks and their duration have been established, resource assignments will establish the initial load required to accomplish the work. Working within project constraints for time and resources, fluctuations in load for each resource will be minimized.
Suggest some options for leveling the load placed on resources.
Leveling demand arrival patterns would be one possible option. If this were not possible, personnel could be asked to alter working hours to accommodate the demand arrival patterns. The third possibility would be to hire temporary workers to handle peak demand patterns exceeding the internal capacity of the organization. It is also important to allow for unexpected delays associated with resource availability problems. For example, is generally unwise to load scarce resources with demand exceeding 85 to 90 percent of the resources’ available capacity. Thus, if future load will consistently exceed the existing capacity of the organization, it may be appropriate to hire additional resources in the affected resource category.
Discuss some other causes of the strong optimistic bias in a project schedule.
An overly optimistic project manager simply ignore the need to perform risk management. When problems arise, this category of project manager treats the problem as an act of chance that cannot be forecasted. When senior managers refuse to recognize that the capacity to undertake projects will need to exceed the demand for projects, then resources will become overloaded. Goldratt described the student syndrome as a scenario where students always want more time to complete a project. Then, the project will be delayed until the last possible moment. Multitasking to reduce idle time actually increases the amount of time it takes to accomplish work. The perception that people need a reason to work hard will often result in arbitrary reductions to the allotted time to complete activities. To mitigate the impact of arbitrary cuts in the schedule, game playing may take place during planning.