• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/1210

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

1210 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)
"should cost" estimates
aka independent estimates
1FB
Invitation for Bid
9 Knowledge areas...
Integration, scope, time, cost, quality, human resources, communications, risk, procurement.
A balanced matrix structure has many of the same attributes as a weak matrix
but the project manager has more time and power regarding the project.
A feasibility study is conducted
to prove a problem actually exists, document the opportunities at hand, and then determine if a project can be created to resolve the problem or take advantage of the opportunity cited. A feasibility study may also look at the cost of the solution in relation to the possible rewards gained by its implementation.
A key part of communication
is active listening
A project is a
temporary endeavor to create a unique product or service. Operations are ongoing activities
A project life cycle is
the duration of a project
A project manager in a matrix environment
can have low, balanced, or high authority over the project. A project manager in a projectized organization will have a high level of authority on the project
A project manager must
monitor, maintain, and control the work of the project to ensure timeliness, accountability, quality, and success
A project phase
allows a project manager to see the project as a whole and yet still focus on completing the project one phase at a time.
A small change, delay, decision (or lack thereof)
can amplify into serious problems further down the project timeline.
A stage gate allows a project to
continue after performance and deliverable review against a set of predefined metrics
A work authorization system is a method that
allows work to begin according to schedule and circumstance
Accept
The act of formally receiving or acknowledging something and regarding it as being true, sound, suitable, or complete.
acceptable planning solution for long projects whose late activities in the project schedule are unknown or will be determined based on the results of early project phases
describes the work, and only the required work, necessary to meet the project objectives. The scope statement establishes a common vision among the project stakeholders to establish the point and purpose of the project work. It is used as a baseline against which all future project decisions are made to determine if proposed changes or work results are aligned with expectations.
Acceptance Criteria
Those criteria, including performance requirements and essential conditions, which must be met before project deliverables are accepted.
achievement theory
3 motivators:
Achievement
Power
Affiliation
Acquire final team
1. Executing
Acquire Project Team [Process]
The process of obtaining the human resources needed to complete the project.
active listening
occurs when the receiver confirms the message is being received by feedback
Activity
A component of work performed during the course of a project. See also schedule activity.
Activity Attributes [Output/Input]
Multiple attributes associated with each schedule activity that can be included within the activity list. Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, unposed dates, constraints, and assumptions.
Activity Code
One or more numerical or text values that identify characteristics of the work or in some way categorize the schedule activity that allows filtering and ordering of activities within reports.
Activity definition
To define the required activities, and only the required activities, to complete the project scope
Activity Definition [Process]
The process of identifying the specific schedule activities that need to be performed to produce the various project deliverables.
Activity Description (AD)
A short phrase or label for each schedule activity used in conjunction with an activity identifier to differentiate that project schedule activity from other schedule activities. The activity description normally describes the scope of work of the schedule activity.
Activity Duration
The time in calendar units between the start and Finish of a schedule activity. See also actual durcrtiatt original duration, and remaining duration.
Activity duration estimating
To determine the estimated required work units to successfully complete the defined activities.
Activity Duration Estimating [Process]
The process of estimating the number of work periods that will be needed to complete individual schedule activities.
Activity Identifier
A short unique numeric or text identification assigned to each schedule activity to differentiate that project activity* from other activities. Typically unique within any one project schedule network diagram.
activity list
network diagramming method rarely used. activity lengths on arrows
activity on nodes
network diagramming method commonly used
Activity Resource Estimating [Process]
The process of estimating the types and quantities of resources required to perform each schedule activity.
Activity sequencing
To determine the best sequence of planned activities within the project work.
activity sequencing
a process of setting order of activities.

Inputs:
Activity List
product description
mandatory (hard logic) dependencies
discretionary (soft) dependencies
external dependencies
milestones
Activity Sequencing [Process]
The process of identifying and documenting dependencies among schedule activities.
Activity, List [Output/Input]
A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
Activity-on-Arrovv (AOA)
See arrow diagramming method. Activity-on-Node (AON). See precedence diagramming method.
Actual Cost (AC)
Total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity or work breakdown structure component. Actual cost can sometimes be direct labor hours alone, direct costs alone, or all costs including indirect costs. Also referred to as the actual cost of work performed (ACWP). See also earned value management and earned value technique.
Actual Cost (Actual cost of work performed)
Sum of all costs at a given time.
Actual Cost of Work Performed (ACWP)
See actual cost (AC).
Actual Duration
The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete.
Actual Finish Date (AF)
The point in time that work actually ended on a schedule activity. (Note: In some application areas, the schedule activity is considered "finished" when work is "substantially complete.")
Actual Start Date (AS)
The point in time that work actually started on a schedule activity.
ACWP
Actual Cost of Work Performed
AD
Activity Description
ADM
Arrow Diagramming Method
Administer contracts
16. Monitoring & Controlling
Administering Contracts
Procurement involves administering the contracts between the buyer and the seller. The contract must be fair and legal. The contract typically is a document that represents the offer and acceptance of both parties. Some organizations may utilize centralized contracting or a contracting office to manage all project contracts
administrative closure
documenting of the project results and the acceptance of the product by the customer or sponsor. Also needed when project is terminated.
Administrative closure
To gather, evaluate, and disseminate the required information on the project or phase, its performance, quality, and completeness. Administrative closure also includes completing the lessons learned document and filing for future reference
AE
Apportioned Effort
AF
Actual Finish date
All of the different elements in project management are integrated
The cost, time, scope, cultural achievability, technical achievability, and more are all related and interdependent
All projects, large or small, have a triple constraint
time, cost, and quality
analogous estimating
top-down estimating, relies on historical estimating.
Analogous Estimating [Technique]
An estimating technique that uses the values of parameters, such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar activity as the basis for estimating the same parameter or measure for a future activity. It is frequently used to estimate a parameter when there is a limited amount of detailed information about the project (e.g., in the early phases). Analogous estimating is a form of expert judgment. Analogous estimating is most reliable when the previous activities are similar in fact and not just in appearance, and the project team members preparing the estimates have the needed expertise.
AOA
Activity-on-Arrow
AON
Activity-on-Node
Application Area
A category of projects that have common components significant in such projects, but are not needed or present in all projects. Application areas are usually defined in terms of either the product (i.e., by similar technologies or production methods) or the type of customer (i.e., internal versus external, government versus commercial) or industry sector (i.e., utilities, automotive, aerospace, information technologies). Application areas can overlap.
Apportioned Effort (AE)
Effort applied to project work that is not readily divisible into discrete efforts for that work, but which is related in direct proportion to measurable discrete work efforts. Contrast with discrete effort.
Approve
The act of formally confirming, sanctioning, ratifying, or agreeing to something.
Approve changes, defect repair, preventive and corrective actions
8. Monitoring & Controlling
Approved Change Request [Output/Input]
A change request that has been processed through the integrated change control process and approved. Contrast with requested change.
Arbitration is a form of negotiation
Technically, it is a form of assisted negotiation
archives should serve as a wealth of historical information
for later reference, future project managers, and reference for versioning, updates, or potential changes to the current project deliverables
are needed to alert management as to when monies must be available for the project to continue.
Cash flow projections
Armed with the appropriate information for each project phase, the project manager can plan for
, schedules, resource availability, risk management, and other project management activities to ensure that the project progresses successfully
Arrow
The graphic presentation of a schedule activity in the arrow diagramming method or a logical relationship between schedule activities in the precedence diagramming method.
Arrow Diagramming Method (ADM [Technique]
A schedule network diagramming technique in which schedule activities are represented by arrows. The tail of the arrow represents the start, and the head represents the finish of the schedule activity. (The length of the amlow does not represent the expected duration of the schedule activity.) Schedule activities are connected at points called nodes (usually drawn as small circles) to illustrate the sequence in which the schedule activities are expected to be performed. See also precedence diagramming method.
AS
Actual Start date
As a project manager, you should identify the requirements
as close to the project launch as possible
As the project moves closer to completion, the likelihood of
risk diminishes
assumptions
beliefs considered to be true, real for the purposes of planning
Assumptions [Output/Input]
Assumptions are factors that, for planning purposes, are considered to be true, real, or certain without proof or demonstration. Assumptions affect all aspects of project planning, and are part of the progressive elaboration of the project. Project teams frequently identify, document, and validate assumptions as part of their planning process. Assumptions generally involve a degree of risk.
Assumptions Analysis [Technique]
A technique that explores the accuracy of assumptions and identifies risks to the project from inaccuracy, inconsistency, or incompleteness of assumptions.
At the end of each of the listed phases
there’d likely be an inspection and confirmation that the project is moving towards its completion. The completion of a phase allows a project to move into the next phase
At the launch of a project, the project manager must
have inherited the vision of the project
Attributes of a project manager in a balanced matrix are
Reasonable authority

Management of a part-time project team

Full-time role as a project manager

May have part-time administrative staff to help expedite the project
Attributes of a project manager in a strong matrix include
A reasonable to high level of power

Management of a part-time to nearly full-time project team

Full-time role as a project manager

Has a full-time administrative staff to help expedite the project
Auditing Procurement Documents
The project manager has spent the money, but on what? The procurement audit process requires accountability for the monies that have been invested in the project. In some instances, the financial audit is more formal, and an accountant or a finance professional reviews the project’s accounting. In other instances, the process is considered a debriefing and is completed with the project manager and management. In practically all instances, the intensity of the procurement audit is relevant to the autonomy of the project manager: the more power and responsibility the project manager has in an organization, the more accountable he is for the project budget.
Authority
The right to apply project resources*, expend fluids, make decisions, or give approvals.
autocratic
making decisions regardless of team input
avoidance
response to risk event. planning a different technique to remove risk from project
BAC
budget at completion -- predicted budget for project
Backward Pass
The calculation of late finish dates and late start dates for the uncompleted portions of all schedule activities. Determined by working backwards through the schedule network logic from the project's end date. The end date may be calculated in a forward pass or set by the customer or sponsor. See also schedule network analysis.
Balanced matrix
The project manager has balanced project authority with management. This model allows efficient use of functional resources.
Bar Chart [Tool]
A graphic display of schedule-related information. In the typical bar chart, schedule activities or work breakdown structure components are listed down the left side of the chart, dales are shown across the top, and activity durations are shown as date-placed horizontal bars. Also called a Gantt chart.
Baseline
The approved time phased plan (for a project, a work breakdown structure component, a work package, or a schedule activity), plus or minus approved project scope, cost, schedule, and technical changes. Generally refers to the current baseline, but may refer to the original or some other baseline. Usually used with a modifier (e.g., cost baseline, schedule baseline, performance measurement baseline, technical baseline). See also performance measurement baseline.
Baseline Finish Date
The finish date of a schedule activity in the approved schedule baseline. Sec also scheduled finish elate.
Baseline Start Date
The start date of a schedule activity in the approved schedule baseline. See also scheduled strut date.
BCWP
Budgeted Cost of Work Performed
BCWS
Budgeted Cost of Work Scheduled
Before projects can move into the implementation
Before projects can move into the implementation
Beginning Vendor Solicitation
In most projects, vendors are involved at some point. Part of the executing process is to solicit vendors should they need to be involved with the project. Adequate timing is required for the procurement process to allow the vendors to provide adequate, appropriate information for the project—and to allow the project manager to make an educated decision on which should be selected. Vendor solicitation includes obtaining quotations, bids, and proposals for the services or the goods to be purchased for the project completion.
benchmarking
using prior projects to set quality standards for processes and results
benefit measurement methods
used in comparing the value of one project to another
Beware of exam questions that tell you the scope is completed but that the customer is not satisfied.
Know first that if the scope is complete, the project is complete
bid
document from seller to buyer. Used when price is determining factor
bidder conference
hoster by buyer, ensures all bidders have equal opportunity to gain information
Bill of Materials (BOM)
A documented formal hierarchical tabulation of the physical assemblies, subassemblies, and components needed to fabricate a product.
BOM
Bill Of Materials
bottom-up estimating
budgeting technique where each component in the WBS is estimated then totaled. Longest but most accurate.
Bottom-up Estimating [Technique]
A method of estimating a component of work. The work is decomposed into more detail. An estimate is prepared of what is needed to meet the requirements of each of the lower, more detailed pieces of work, and these estimates are then aggregated into a total quantity for the component of work. The accuracy of bottom-up estimating is driven by the size and complexity of the work identified at the lower levels. Generally smaller work scopes increase the accuracy of the estimates.
Brainstorming [Technique]
A general data gathering and creativity technique that can be used to identify risks, ideas, or solutions to issues by using a group of team members or subject-matter experts. Typically, a brainstorming session is structured so that each participant's ideas are recorded for later analysis.
Budget
The approved estimate for the project or any work breakdown structure component or any schedule activity. See also estimate.
Budget at Completion (BAC)
The sum of all the budgets established for the work to be performed on a project or a work breakdown structure component or a schedule activity. The total planned value for the project.
budget estimate
used in early Planning process and in top-down estimates. Variance -10 to +25
Budgeted At Completion
See earned value (Elf). Budgeted Cost of Work Scheduled (BCWS). See planned value (P V). Buffer. See reserve.
Build
Within this phase, there’d be logical activities and mini-phases necessary to reach the project completion, such as the foundation, the framing, the roofing, and so on
bull's eye
creates limits to acceptable earned value metrics. Outside 'eye' is automatic escalation to management
By involving the stakeholders at different aspects of the project, their requirements are more likely to be met
By involving the stakeholders at different aspects of the project, their requirements are more likely to be met
CA
Control Account
Calendar Unit
The smallest unit of time used in scheduling the project, Calendar units are generally in hours, days, or weeks, but can also be in quarter years, months, shifts, or even in minutes.
CAP
Control Account Plan
Cardinal scales
numerical value
e.g., .01 to 1.0
cause-and-effect diagrams
fisbone, Ishikawa

Goal: treat root cause
CCB
Change Control Board
centralized contracting
all contracts need to be approved by central unit in organization
Change Control
Identifying, documenting, approving or rejecting, and controlling changes to the project baselines *.
Change Control Board
A board that determines the validity of and approves project change requests.
Change Control Board (CCB)
A formally constituted group of stakeholders responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, with all decisions and recommendations being recorded.
Change Control System
A system to determine the validity of and act upon project change requests.
Change Control System [Tool]
A collection of formal documented procedures that define how project deliverables and documentation will be controlled, changed, and approved. In most application areas the change control system is a subset of the configuration management system.
Change Request
Requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets, or revise schedules. Requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually mandated or optional. Only formally documented requested changes are processed and only approved change requests are implemented.
Chart of Accounts [Tool]
Any numbering system used to monitor project costs* by category (e.g., labor, supplies, materials, and equipment). The project chart of accounts is usually based upon the corporate chart of accounts of the primary performing organization. Contrast with code of accounts.
Checklist [Outputllnput]
Items listed together for convenience of comparison, or to ensure the actions associated with them are managed appropriately and not forgotten. An example is a list of items to be inspected that is created during quality planning and applied during quality control.
checklists
lists of activities to check off to make sure work is done. QC
Claim
A request, demand, or assertion of rights by a seller against a buyer, or vice versa, for consideration, compensation, or payment under the terms of a legally binding contract, such as for a disputed change.
Close Project [Process]
The process of finalizing all activities across all of the project process groups to formally close the project or phase.
Closing
Ah, the best process of them all. The closing process, sometimes called the project postmortem, involves closing out the project accounts, completing final acceptance of the project deliverables, filing the necessary paperwork, and assigning the project team to new projects. Oh yeah, and celebrating!

Most projects have similar characteristics, such as the following:
Closing Administrative Duties
When the project is completed, the project manager must finalize all reports, document the project experience, and provide evidence of customer acceptance. The project manager will create a final report reflecting the project success, or failure. The project manager will also provide information reflective of the project product and how it met the project requirements, and then will complete the lessons learned documentation
Closing Processes [Process Group]
Those processes performed to formally terminate all activities of a project or phase, and transfer the completed product to others or close a cancelled project.
Closing Vendor Contracts
At the completion of a project or project phase the vendor contracts must be closed out. Confirmation that vendor invoices and purchase orders have been fulfilled, met, and paid is needed to complete the vendor closeout process. Closing out vendor contracts may also require proof or delivery of the goods or services purchased. The vendor contracts may be audited to confirm the vendor responsibilities have been met
Co-location [Technique]
An organizational placement strategy where the project team members are physically located close to one another in order to improve communication, working relationships, and productivity.
Code of Accounts [Tool]
Any numbering system used to uniquely identify each component of the work breakdown structure. Contrast with chart of accounts.
coercive power
a.k.a., penalty power. Team is afraid of PM
Collect processes, procedures and historical information
3. Initiating
collection of projects with a common cause
Programs are
collective bargaining agreements
contractual agreements that may be constraints
Common Cause
A source of variation that is inherent in the system and predictable. On a control chart, it appears as part of the random process variation (i.e., variation from a process that would be considered normal or not unusual), and is indicated by a random pattern of points within the control limits. Also referred to as random cause. Contrast with special cause.
Common constraints you’ll encounter
time constraints in the form of deadlines and the availability of resources
Communication
A process through which information is exchanged among persons using a common system of symbols, signs, or behaviors.
Communication Management Plan [Output/Input]
The document that describes: the communications needs and expectations for the project; how and in what format information will be communicated; when and where each communication will be made; and who is responsible for providing each type of communication. A communication management plan can be formal or informal, highly detailed or broadly framed, based on the requirements of the project stakeholders. The communication management plan is contained in, or is a subsidiary plan of, the project management plan.
Communication skills are
included as part of the Professional Responsibility portion of the PMP exam. We’ll cover the Professional Responsibility information in Chapter 13
Communications is an activity that will consume
much of the project manager’s time, but it is not one of the five process groups.
communications management plan
documents & organizes stakeholders communications needs
Closing Processes [Process Group]
Those processes performed to formally terminate all activities of a project or phase, and transfer the completed product to others or close a cancelled project.
Closing Vendor Contracts
At the completion of a project or project phase the vendor contracts must be closed out. Confirmation that vendor invoices and purchase orders have been fulfilled, met, and paid is needed to complete the vendor closeout process. Closing out vendor contracts may also require proof or delivery of the goods or services purchased. The vendor contracts may be audited to confirm the vendor responsibilities have been met
Co-location [Technique]
An organizational placement strategy where the project team members are physically located close to one another in order to improve communication, working relationships, and productivity.
Code of Accounts [Tool]
Any numbering system used to uniquely identify each component of the work breakdown structure. Contrast with chart of accounts.
coercive power
a.k.a., penalty power. Team is afraid of PM
Collect processes, procedures and historical information
3. Initiating
collection of projects with a common cause
Programs are
collective bargaining agreements
contractual agreements that may be constraints
Common Cause
A source of variation that is inherent in the system and predictable. On a control chart, it appears as part of the random process variation (i.e., variation from a process that would be considered normal or not unusual), and is indicated by a random pattern of points within the control limits. Also referred to as random cause. Contrast with special cause.
Common constraints you’ll encounter
time constraints in the form of deadlines and the availability of resources
Communication
A process through which information is exchanged among persons using a common system of symbols, signs, or behaviors.
Communication Management Plan [Output/Input]
The document that describes: the communications needs and expectations for the project; how and in what format information will be communicated; when and where each communication will be made; and who is responsible for providing each type of communication. A communication management plan can be formal or informal, highly detailed or broadly framed, based on the requirements of the project stakeholders. The communication management plan is contained in, or is a subsidiary plan of, the project management plan.
Communication skills are
included as part of the Professional Responsibility portion of the PMP exam. We’ll cover the Professional Responsibility information in Chapter 13
Communications is an activity that will consume
much of the project manager’s time, but it is not one of the five process groups.
communications management plan
documents & organizes stakeholders communications needs
Communications planning
To determine who needs what, when they need it, and in what modality (paper, electronic, and so on) it may be needed
Communications Planning [Process]
The process of determining the information and communications needs of the project stakeholders: who they are, what is their level of interest and influence on the project, who needs what information, when will they need it, and how it will be given to them.
Compensation
Something given or received, a payment or recompense, usually something monetary or in kind for products, services, or results provided or received.
Complete contract closure`
2. Closure
Complete product scope
3. Excectuing
Completing projects as needed
These non-project-centric entities can complete projects successfully, but may not have the project systems in place to efficiently support projects. The lack of a project support system can cause the project to succumb to additional risks, lack of organization, and reporting difficulties. Some organizations may have special internal business units to support the projects in motion that are separate from the accounting, time, and management systems used by the rest of the organization.
Completing projects for others
These entities swoop into other organizations and complete the project work based on specifications, details, and specification documents. Classical examples of these types of organizations include consultants, architectural firms, technology integration companies, and advertising agencies
Completing projects internally through a system
These entities have adopted management by projects (discussed in Chapter 1). Recall that organizations using management by projects have accounting, time, and management systems in place to account for the time, cost, and worth of each project.
Completing Scope Verification
Scope verification is a control process. However, at the end of the project the scope must be verified for final acceptance. This process is completed with the project manager and the key stakeholders. Scope verification is the process of inspecting, touring, and “taking a walk-through” of the project deliverables to confirm that the requirements of the project have been met. Scope verification may happen at different intervals throughout the project, such as at key milestones or phase completions. Scope verification at the end of a project may require a formal sign-off from the customer that the project is complete and to their satisfaction
complex organization of decision-making, planning, implementation, control, and documentation of the experience from start to finish. In addition to traditional project management, there are related areas of project management that you may encounter, have encountered, or are actively participating in.
Project management is a
Component
A constituent part, element, or piece of a complex whole.
compromising
requires both parties to give up something. Lose-lose situation
configuration management
activities focusing on controlling the characteristics of a product or service. AKA a rigorous change control system.
Configuration management
5. Monitoring & Controlling
Configuration Management System [Tool]
A subsystem of the overall project management system. It is a collection of formal documented procedures used to apply technical and administrative direction and surveillance to: identify and document the functional and physical characteristics of a product, result, service, or component; control any changes to such characteristics; record and report each change and its implementation status; and support the audit of the products, results, or components to verify conformance to requirements. It includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes. In most application areas, the configuration management system includes the change control system.
Confirm work is done to requirements
3. Closure
Conflict Resolution Techniques (5)
From best to worst:
1. Confrontation
2. Compromise
3. Withdrawl
4. Smoothing
5. Forcing
Consider the Expected Quality
What good is a project if it is finished on time and on budget, but the quality of the deliverable is so poor it is unusable? Some projects have a set level of quality that allows the project team to aim for. Other projects follow the organization’s Quality Assurance Program such as ISO 9000. And, unfortunately, some projects have a general, vague idea of what an acceptable level of quality is. Without a specific target for quality, trouble can ensue. The project manager and project team may spend more time and monies to hit an extremely high level of quality when a lower, expected level of quality would suffice for the project. Quality is needed, but an exact target of expected quality is demanded.
Consider the Project Risk
Do you play golf? In golf, as in project management, there is a theory called The Risk-Reward Principle. You’re teeing off for the seventh hole. If you shoot straight, you can lay up in the fairway, shoot again, and then two-putt for par. Pretty safe and predictable. However, if you have confidence in your driver, you may choose to cut the waterway and get on the green in one. If you accept and beat that risk, you’ll have a nice reward. Choke and land in the water and you’re behind the game. In project management, the idea is the same. Some risks are worth taking, while others are worth the extra cost to avoid. You’ll learn all about risks in Chapter 11.
constrained optimizaion methods
complex mathematical formulas and algorithms used to predict the future success of projects. E.g., linear programming
Constraint [Input]
The state, quality, or sense of being restricted to a given course of action or inaction. An applicable restriction or limitation, either internal or external to the project, that will affect the performance of the project or a process. For example. a schedule constraint is any limitation or restraint placed on the project schedule that affects when a schedule activity can be scheduled and is usually in the form of fixed imposed dates. A cost constraint is any limitation or restraint placed on the project budget such as fiends available over time. A project resource constraint is any limitation or restraint placed on resource usage, such as what resource skills or disciplines are available and the amount of a given resource available during a specified time frame.
constraints
any influence on a project that may limit the options of the team
Constraints Are Imposed
Within every project there is a driving force for the project. You’ve probably experienced some force first-hand. For example, ever had a project that had to be done by an exact date or you’d face fines and fees? This is a schedule constraint. Or a project that could not go over it’s set budget? This is a financial constraint. Or what about a project that had to hit an exact level of quality regardless of how long the project took? This is scope constraint. All are forces that tend to be in competition with each other.

Specifically, there are three constraints that a project manager will encounter
Contingency
See reserve. Contingency Allowance. See reserve.
contingency reserve
a time or dollar amount allotted to risk response
Contingency Reserve [Output/Input]
The amount of,junds, budget, or time needed above the estimate to reduce the risk of overruns of project objectives to a level acceptable to the organization.
Continuous improvement
7. Executing
contract
legal, binding agreement, preferably written, between buyer and seller detailing requirements and obligations of both parties. Must have:
1. Offer
2. Acceptance
3. Legal capacity
4. Consideration
5. Legal purpose
Contract [Output/Input]
A contract is a mutually binding agreement that obligates the seller to provide the specified product or service or result and obligates the bui'er to pay for it.
contract administation
process of ensuring the buyer and seller perform to specs in contract
Contract Administration [Process]
The process of managing the contract and the relationship between the buyer and seller, reviewing and documenting how a seller is performing or has performed to establish required corrective actions and provide a basis for future relationships with the seller, managing contract related changes and, when appropriate, managing the contractual relationship with the outside buyer of the project.
contract change control system
defines how contracts may be changed
contract closeout
process for confirming the obligations of the contract went as expected. PM, customer, key stakeholders perform product verification
Contract closeout
To complete and finalize any procurement issues such as payment, inspection of procured services and goods, and any open project items.
Contract Closure [Process]
The process of completing and settling the contract, including resolution of any open items and closing each contract.
contract file
a complete indexed set of procurement records incorporated into admin closure. includes financial as well as scope verification
Contract Management Plan [Output/Input]
The document that describes how a specific contract will be administered and can include items such as required documentation delivery and performance requirements. A contract management plan can be formal or informal, highly detailed or broadly framed, based on the requirements in the contract, Each contract management plan is a subsidiary plan of the project management plan.
Contract Statement of Work (SOW) [Output/Input]
A narrative description of products, services, or results to be supplied under contract.
Contract Work Breakdown Structure (CWBS) [Output/Input]
A portion of the work breakdown structure for the project developed and maintained by a seller contracting to provide a subproject or project component.
Control [Technique]
Comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed.
Control Account (CA) [Tool]
A management control point where scope, budget (resource plans), actual cost, and schedule are integrated and compared to earned value for perfomiance measurement. Control accounts are placed at selected management points (specific components at selected levels) of the work breakdown structure. Each control account may include one or more work packages, but each work package may be associated with only one control account. Each control account is associated with a specific single organizational component in the organizational breakdown structure (Ol3S). Previously called a cost account. See also work package.
Control Account Plan (CAP) [Tool]
A plan for all the work and effort to be performed in a control account. Each CAP has a definitive statement of work, schedule, and time-phased budget. Previously called a Cost Account Plan.
Control Chart [Tool]
A graphic display of process data over time and against established control limits, and that has a centerline that assists in detecting a trend of plotted values toward either control limit.
control charts
illustrate performance of project over time. Upper and lower limits indicate whether project is out of control
Control Limits
The area composed of three standard deviations on either side of the centerline, or mean, of a normal distribution of data plotted on a control chart that reflects the expected variation in the data. See also specification limits.
Controlling
The project manager must control the work the project team and the vendors are completing. The project manager checks that the deliverables of the phases are in alignment with the project scope, defends the scope from changes, and confirms the expected level of quality of the work being performed. This process also requires the project manager to confirm that the cost and schedule are in sync with what was planned. Finally, the project team will inform the project manager of their progress, who will, in turn, report on the project’s progress to the project sponsor, to management, and perhaps even to key stakeholders in the organization
Controlling
Project performance is monitored and measured to ensure the project plan is being implemented to design specifications and requirements
Controlling Processes
Controlling processes are the activities that ensure the project goes according to plan and the actions to implement when evidence proves the project is not going according to plan. Specifically, the controlling processes verify project work and the response to that work. In addition, the project manager must work to control the predicted cost and schedule of the project. Variances to the cost and schedule will affect the project’s success
COQ
Cost of Quality
core processes
Common to all projects:
scope planning
scope definition
activity definition
activity duration estimating
activity sequencing
cost budgeting
cost estimating
resource planning
risk management planning
schedule development
project plan development
Corrective Action
Documented direction for executing the project work to bring expected future performance of the project work in line with the project management plan.
Cost
The monetary value or price of a project activity* or component that includes the monetary worth of the resources required to perform and complete the activity or component, or to produce the component. A specific cost can be composed of a combination of cost components including direct labor hours, other direct costs, indirect labor hours, other indirect costs, and purchased price. (However, in the earned value management methodology, in some instances, the term cost can represent only labor hours without conversion to monetary worth.) See also actual cost and estimate.
cost baseline
what is expected to be spent in a project. Usually shown in an S-curve
Cost budgeting
To determine the estimated cost of the activities to complete the project work

the process of assigned a cost to an individual work package. Results in an S-curve that becomes the baseline
Cost Budgeting [Process]
The process of aggregating the estimated costs of individual activities or work packages to establish a cost baseline.
Cost Budgets,
Budgets, monies, greenbacks, dead presidents, whatever you want to call it—the cost of completing the project is always high on everyone’s list of questions. The project manager must find a method to accurately predict the cost of completing the project within a given timeline, and then control the project to stay within the given budget. We will learn more about this in Chapter 7. Sounds easy, right? The following diagram illustrates the Iron Triangle of scope, schedule, and cost constraints.
cost change control
documents the procedures to request, approve and incorporate changes to project costs. Part of Integrated Change Control
Cost control
To prevent unnecessary changes to the project budget.
an active process to control causes of cost change, document and monitor
Cost Control [Process]
The process of influencing the factors that create variances, and controlling changes to the project budget.
Cost estimates can be calculated a number of different ways
such as through top-down estimates, bottom-up estimates, or the dreaded informal “hallway estimates.” All estimates should identify a range of variance reflective of the degree of confidence of the estimate, the assumption the estimate is based on, and how long the estimate is valid
cost estimating
the process of calculating the costs by category of the resources to complete project work
Cost estimating
To determine an estimated amount of monies to complete the project work using the defined facilities, services, and goods
Cost Estimating [Process]
The process of developing an approximation of the cost of the resources needed to complete project activities*.
cost management plan
details how variances from the project costs will be managed. Output of cost estimating.
Cost Management Plan [Output/Input]
The document that sets out the format and establishes the activities and criteria for planning, structuring, and controlling the project costs. A cost management plan can be formal or informal, highly detailed or broadly framed, based on the requirements of the project stakeholders. The cost management plan is contained in, or is a subsidiary plan, of the project management plan.
cost of nonconformance
cost of completing project work without meeting quality standards. Biggest issue is money for rework.
cost of quality
expense of all activities within a project to meet quality objectives
Cost of Quality (COQ) [Technique]
Determining the costs incurred to ensure qualitt. Prevention and appraisal costs (cost of conformance) include costs for quality planning, quality control (QC), and quality assurance to ensure compliance to requirements (i.e., training, QC systems, etc.). Failure costs (cost of non-conformance) include costs to rework products, components, or processes that are non-compliant, costs of warranty work and waste, and loss of reputation.
Cost Performance Index
EV / AC

(Rate at which we are meeting cost expectations)
Cost Performance Index (CPI)
A measure of cost efficiency on a project. It is the ratio of earned value (EV) to actual costs (AC). CPI = EV divided by AC. A value equal to or greater than one indicates a favorable condition and a value less than one indicates an unfavorable condition.
cost plus fixed fee
profit margin for seller
cost plus incentive fee
seller determines price for product or service but includes reward for completing ahead of time
cost plus percentage of cost
cost overruns assigned to buyer. illegal in USA
Cost Variance
EV - AC

(Difference between what was expected to spend and actually spent)
Cost Variance (CV)
A measure of cost performance on a project. It is the algebraic difference between earned value (EV) and actual cost (AC). CV = EV minus AC. A positive value indicates a favorable condition and a negative value indicates an unfavorable condition.
Cost-Plus-Fee (CPF)
A type of cost reimbursable contract where the buyer reimburses the seller for seller's allowable costs for performing the contract work and seller also receives a fee calculated as an agreed upon percentage of the costs. The fee varies with the actual cost.
Cost-Plus-Fixed-Fee (CPFF) Contract
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller's allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).
Cost-Plus-Incentive-Fee (CPIF) Contract
A type of cost-reimbursable contract where the barer reimburses the seller for the seller's allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.
Cost-Plus-Percentage of Cost (CPPC)
See cost-plus-fee.
Cost-Reimbursable Contract
A type of contract involving payment (reimbursement) by the buyer to the seller for the seller's actual costs, plus a fee typically representing seller's profit. Costs are usually classified as direct costs or indirect costs. Direct costs are costs incurred for the exclusive benefit of the project, such as salaries of firll-time project staff. Indirect costs, also called overhead and general and administrative cost, are costs allocated to the project by the performing organization as a cost of doing business, such as salaries of management indirectly involved in the project, and cost of electric utilities for the office. Indirect costs are usually calculated as a percentage of direct costs. Cost-reimbursable contracts often include incentive clauses where, if the seller meets or exceeds selected project objectives, such as schedule targets or total cost, then the seller receives from the buyer an incentive or bonus payment.
cost-reimbursable contracts
contract that pays seller for product
CPF
Cost-Plus-Fee
CPFF
Cost-Plus-Fixed-Fee
CPI
Cost Performance Index

How the project is doing financially

CPI = EV/AC
CPIF
Cost-Plus-Incentive-Fee
CPM
critical path method. used to determine float
CPPC
Cost-Plus-Percentage of Cost
crashing
practice of adding additional resources to critical path to end project early. results in increased costs.
Crashing [Technique]
A specific type of project schedule compression technique performed by taking action to decrease the total project schedule duration* after analyzing a number of alternatives to determine how to get the maximum schedule duration compression for the least additional cost. Typical approaches for crashing a schedule include reducing schedule activity durations and increasing the assignment of resources on schedule activities. See schedule compression and see also fast tracking.
Create activity list
5. Planning
Create forecasts
15. Monitoring & Controlling
Create network diagram
6. Planning
Create process improvement plan
20. Planning
Create project scope statement
2. Planning
Create WBS (Work Breakdown Structure) [Process]
The process of subdividing the major project deliverables and project work into smaller, more manageable components
Create WBS and WBS dictionary
4. Planning
Criteria
Standards, rules, or tests on which a judgment or decision can be based, or by which a product, service, result, or process can be evaluated.
Critical Activity
Any schedule activity on a critical path in a project schedule. Most commonly determined by using the critical path method. Although some activities are "critical," in the dictionary sense, without being on the critical path, this meaning is seldom used in the project context.
Critical Chain Method [Technique]
A schedule network analysis technique* that modifies the project schedule to account for limited resources. The critical chain method mixes deterministic and probabilistic approaches to schedule network analysis.
Critical Path [Output/Input]
Generally, but not always, the sequence of schedule activities that determines the duration of the project. Generally, it is the longest path through the project. I-lowever, a critical path can end, as an example, on a schedule milestone that is in the middle of the project schedule and that has a finish-no-later-than imposed date schedule constraint. See also critical path method.
Critical Path Method (CPM) [Technique]
A schedule network analysis technique* used to determine the amount of scheduling flexibility (the amount of float) on various logical network paths in the project schedule network, and to determine the minimum total project duration. Early start and finish dates* are calculated by means of a forward pass, using a specified start date. Late start and finish dates* are calculated by means of a backward pass, starting from a specified completion date, which sometimes is the project earl) finish date determined during the forward pass calculation.
Current Finish Date
The current estimate of the point in time when a schedule activity will be completed, where the estimate reflects any reported work progress. See also scheduled finish date and baseline finish elate.
Current Start Date
The current estimate of the point in time when a schedule activity will begin, where the estimate reflects any reported work progress. See also scheduled start date and baseline start date.
Customer
The person or organization that will use the project's product or service or result. (See also user).
Customers, internal or external
are the most important stakeholders in a project
CV
Cost Variance
CWBS
Contract Work Breakdown Structure
Data Date (-DD)
The date up to or through which the project's reporting system has provided actual status and accomplishments. In some reporting systems, the status information for the data date is included in the past and in some systems the status information is in the future. Also called as-of date and time-non' date.
Date
A term representing the day, month, and year of a calendar, and, in some instances, the time of day.
DD
Data Date
Decision Tree Analysis [Technique]
The decision tree is a diagram that describes a decision under consideration and the implications of choosing one or another of the available alternatives. It is used when some future scenarios or outcomes of actions are uncertain. It incorporates probabilities and the costs or rewards of each logical path of events and future decisions, and uses expected monetary value analysis to help the organization identify the relative values of alternate actions. See also expected monetary value anal ys i.s.
decoder, encoder
part of communications model
Decomposition [Technique]
A planning technique that subdivides the project scope and project deliverables into smaller, more manageable components, until the project work associated with accomplishing the project scope and providing the deliverables is defined in sufficient detail to support executing, monitoring, and controlling the work.
Defect
An imperfection or deficiency in a project component where that component does not meet its requirements or specifications and needs to be either repaired or replaced.
Defect Repair
Formally documented identification of a defect in a project component with a recommendation to either repair the defect or completely replace the component.
Defining Project Management
Is the supervision and control of the work required to complete the project vision
Defining the Project Life Cycle
One common attribute of all projects is that they eventually end. Think back to one of your favorite projects. The project started with a desire to change something within an organization. The idea to change this “something” was mulled around, kicked around, and researched until someone with power deemed it a good idea to move forward and implement the project. As the project progressed towards completion there were some very visible phases within the project life. Each phase within the life of the project created a deliverable.

For example, consider a project to build a new warehouse. The construction company has some pretty clear phases within this project: research, blueprints, approvals and permits, breaking ground, laying the foundation, and so on. Each phase, big or small, results in some accomplishment that everyone can look to and say, “Hey! We’re making progress!” Eventually the project is completed and the warehouse is put into production.

At the beginning of the project, through planning, research, experience, and expert judgment, the project manager and the project team will plot out when each phase should begin, when it should end, and the related deliverable that will come from each phase. Often, the deliverable of each phase is called a milestone. The milestone is a significant point in the schedule that allows the stakeholders to see how far the project has progressed—and how far the project has to go to reach completion.
Defining the Project Management Process
Will all projects have the same phases? Of course not! A project to create and manufacture a new pharmaceutical will not have the same phases as a project to build a skyscraper. Both projects, however, can map to the five project management processes. These processes are typical of projects, and are iterative in nature—that is, you don’t finish a process never to return. Let’s take a look at each process and its attributes.
definitive estimate
used in late Planning process and in bottom-up estimates. Variance -5 to +10
deliverable
The outcome of a project or phase.
Deliverable [Outputllnput]
Any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project. Often used more narrowly in reference to an external deliverable, which is a deliverable that is subject to approval by the project sponsor or customer. See also product, service, and result.
Delphi Technique [Technique]
An information gathering technique used as a way to reach a consensus of experts on a subject. Experts on the subject participate in this technique anonymously. A facilitator uses a questionnaire to solicit ideas about the important project points related to the subject. The responses are summarized and are then re-circulated to the experts for further comment. Consensus may be reached in a few rounds of this process. The Delphi technique helps reduce bias in the data and keeps any one person from having undue influence on the outcome.
Dependency
See logical relationship.
Design
The architects and the designers would work with the requirements to create the specifications for the house in alignment with the requirements of the customer
design of experiments
relies on statistical 'what-if' scenarios to determin what variables in a project will give the best outcome. Most often used on the product.
Design Review [Technique]
A management technique used for evaluating a proposed design to ensure that the design of the system or product meets the customer requirements, or to assure that the design will perform successfully, can be produced, and can be maintained.
Determine communications requirements
14. Planning
Determine company culture and existing systems
2. Initiating
Determine critical path
9. Planning
Determine how you will do plannning -- part of management plans
1. Planning
determine if it is feasible for a project to exist
determine if it is feasible for a project to exist
Determine project objectives
7. Initiating
Determine quality standards, processes and metrics
12. Planning
Determine roles and responsibilities
13. Planning
Determine team
3. Planning
Determine variances and if they warrant corrective action or a change
3. Monitoring & Controlling
Determine what to purchase
17. Planning
Determining Vendor Source
In most projects, vendors are involved at some point. Part of the executing process is to solicit vendors should they need to be involved with the project. Adequate timing is required for the procurement process to allow the vendors to provide adequate, appropriate information for the project—and to allow the project manager to make an educated decision on which should be selected. Vendor solicitation includes obtaining quotations, bids, and proposals for the services or the goods to be
Develop budget
11. Planning
Develop closure procedures
1. Closure
Develop final PM plan and performance measurement baselines
21. Planning
Develop preliminary project scope statement
10. Initating
Develop Preliminary Project Scope Statement [Process]
The process of developing the preliminary project scope statement that provides a high level scope narrative.
Develop project charter
9. Initiating
Develop Project Charter [Process]
The process of developing the project charter that formally authorizes a project.
Develop Project Management Plan [Process]
The process of documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans into a project management plan.
Develop Project Team [Process]
The process of improving the competencies and interaction of team members to enhance project performance.
Develop schedule
10. Planning
Direct and Manage Project Execution [Process]
The process of executing the work defined in the project management plain to achieve the project's requirements defined in the project scope statement.
direct costs
costs incurred by the project in order for it to exist
Discipline
A field of work requiring specific knowledge and that has a set of rules governing work conduct (e.g., mechanical engineering, computer programming, cost estimating, etc.).
Discrete Effort
Work effort that is separate, distinct, and related to the completion of specific work breakdown structure components and deliverables, and that can be directly planned and measured. Contrast with apportioned effort.
discretionary dependencies
soft logic
Dispersing Project Information
Information must be disseminated according to the communications plan. Stakeholders will need to be kept abreast of the project status. Management may want milestone reports, variance reports, and status reports. Customers will have specific communications requirements. All of these demands, from any stakeholder, should be documented within the communications plan—and then followed through in the execution process.
Divide large projects into phases
4. Initiating
Document
A medium and the information recorded thereon, that generally has permanence and can be read by a person or a machine. Examples include project management plans, specifications, procedures, studies, and manuals.
Document assumptions and contraints
8. Initiating
Document business need
6. Initiating
Documented Procedure
A formalized written description of how to carry out an activity, process, technique, or methodology.
EAC
Estimate At Completion.

EAC = BAC/CPI = ETC + AC
Dummy Activity
A schedule activity of zero duration used to show a logical relationship in the arrow diagramming method. Dummy activities are used when logical relationships cannot be completely or correctly described with schedule activity arrows. Dummy activities are generally shown graphically as a clashed line headed by an arrow.
Duration (DU or DUR)
The total number of work periods (not including holidays or other nonworking periods) required to complete a schedule activity or work breakdown structure component. Usually expressed as workdays or workweeks. Sometimes incorrectly equated with elapsed time. Contrast with effort. See also original duration, remaining duration, and actual duration.
EAC
BAC/CPI = use if spending rate will continue
AC + BAC - EV = use if variances not typical
Each phase within the preceding project has logical activities that dictate the point of the
phase, the goal of each, and what the deliverables of each phase likely will be.
Early Finish Date (EF)
In the critical path method, the earliest possible point in time on which the uncompleted portions of a schedule activity (or the project) can finish, based on the schedule network logic, the data date, and any schedule constraints. Early finish dates can change as the project progresses and as changes are made to the project management plan.
Early Start Date (ES)
In the critical path method, the earliest possible point in time on which the uncompleted portions of a schedule activity (or the project) can start, based on the schedule network logic, the data date, and any schedule constraints. Early start dates can change as the project progresses and as changes are made to the project management plan.
Earned Value (Budgeted Cost of Work Performed)
Actual planned complete * BAC
Earned Value (EV)
The value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure component. Also referred to as the budgeted cost of work performed (BCWP).
Earned Value (EV)
EV = %Complete * BAC

The work that has been accomplished withint the project plus the authorized budget for the work that has been accomplished.
Earned Value Management
EVM integrates scope, schedule and cost to give a scalable point-in-time assessment of the project.
Earned Value Management (EVM)
A management methodology for integrating scope, schedule, and resources, and for objectively measuring project performance and
Earned Value Technique (EVT) [Technique]
A specific technique for measuring the performance of work and used to establish the pelformcnlce measurement baseline (PMB). Also referred to as the earning rules and crediting method.
EF
Early Finish date
effective listening
listener is involved by paying attention
Effort
The number of labor units required to complete a schedule activity or work breakdown structure component. Usually expressed as staff hours. staff days, or staff weeks. Contrast with duration,
EMV
Expected Monetary Value
Enforcing Schedule Control
Schedule control requires constant monitoring of the project’s progress, approval of phase deliverables, and task completion. Slippage must be analyzed early in the project to determine the root cause of the problem. Activities that slip may indicate inaccurate estimates, hidden work, or a poor WBS. Quality issues can also throw the project schedule when the time to redo project activities is taken into consideration, as shown in the following illustration. Finally, the project manager must also consider outside influences and their affect on the project—for example, weather, market conditions, cultural issues, and so on.
Ensuring Performance Reporting
The project manager and the project team must work together to report and record accurate completions of work. Performance reporting stems from accurate measurement by the project team, proof of work completion, and factual estimates. The project manager then churns the reported projects through earned value management, schedule baselines, cost baselines, and milestone targets. The status reports to management are reflective of where the project has been, where it stands now, and where it’s heading
Ensuring Quality Control
Quality control (QC) measures work results to determine if they are in alignment with quality standards. If the work results are not of quality, QC uses methods to determine why the results are inadequate and how to eliminate the causes of the quality deficiencies.
Ensuring Team Development
The project manager must work with the project team members to ensure that their level of proficiency is in agreement with their obligations on the project. This may involve classroom learning, shadowing between project team members, or on-the-job training. The success of the project work is dependent on the project team’s ability. Should the team or team members be lagging in required knowledge to complete the project work, additional education and development is necessitated
Enterprise
A company, business, firm, partnership, corporation, or governmental agency.
Enterprise Environmental Factors [Output/Input]
Any or all external environmental factors and internal organizational environmental factors that surround or influence the project's success. These factors are from any or all of the enterprises involved in the project, and include organizational culture and structure, infrastructure, existing resources, commercial databases, market conditions, and project management software.
ES
Early Start date
Estimate [Output/Input]
A quantitative assessment of the likely amount or outcome. Usually applied to project costs, resources, effort, and durations and is usually preceded by a modifier (i.e., preliminary, conceptual, feasibility, order-of-magnitude, definitive). It should always include some indication of accuracy (e.g., ±x percent).
Estimate at Completion
BAC / CPI

(Projecting the total cost at completion based on project performance)
Estimate at Completion (EAC) [OutputlInput]
The expected total cost of a schedule activity, a work breakdown structure component, or the project when the defined scope of work will be completed. EAC is equal to the actual cost (AC) plus the estimate to complete (ETC) for all of the remaining work. EAC = AC plus ETC. The EAC may be calculated based on performance to date or estimated by the project team based on other factors, in which case it is often referred to as the latest revised estimate. See also earned value technique and estimate to complete.
Estimate resource requirements
7. Planning
Estimate time and cost
8. Planning
Estimate to Complete (ETC) [Output/Input]
The expected cost needed to complete all the remaining work for a schedule activity, }cork breakdown structure component, or the project. See also earned value technique and estimate at completion.
Estimate to Completion
EAC - AC

(Projecting total cost at completion based on project performance at a given point in time)
estimating publications
commerical reference to help the PM confirm and predict accuracy of estimates
estimations start at zero, with each expense accounted for until a grand total is reached.
traditional bottom-up estimations
ETC
Estimate To Completion

ETC = EAC-AC
EV
Earned Value
evaluation criteria
used to rate and score proposals from sellers
Event
Something that happens, an occurrence, an outcome.
EVM
Earned Value Management
EVT
Earned Value Technique
Exception Report
Document that includes only major variations from the plan (rather than all variations).
Execute
Directing. managing, performing, and accomplishing the project work, providing the deliverables, and providing work performance information.
Execute the PM Plan
2. Executing
Executing
This process allows the project team and vendors to move toward completing the work outlined in the Planning process. The project team moves forward with completing the project work.
Executing Processes [Process Group]
Those processes performed to complete the work defined in the project management plan to accomplish the project's objectives defined in the project scope statement.
Exit criteria are typically
inspection-specific and are scheduled events in the project schedule
Exit criteria can include many different activities, such as:
Sign-offs from the customer

Regulatory inspections and audits

Quality metrics

Performance metrics

Security audits

The end of a project phase
Exit criterion are
activities or evidence that allow a project to move forward. Stakeholder expectations are universal to the entire project, not just to one project phase.
Expectancy theory
theory that people will work in relation to the expected reward
Expected Monetary Value (EMV) Analysis
A statistical technique that calculates the average outcome when the future includes scenarios that may or may not happen. A common use of this technique is within decision tree analysis. Modeling and simulation are recommended for cost and schedule risk analysis because it is more powerful and less subject to misapplication than expected monetary value analysis.
Expected Monetary Value (Ex$V)
Ex$V = Probability * Value

Value - cost is neg, benefit is positive
Expert Judgment [Technique]
Judgment provided based upon expertise in an application area, knowledge area, discipline, industry, etc. as appropriate for the activity being performed. Such expertise may be provided by any group or person with specialized education. knowledge, skill, experience, or training, and is available from many sources, including: other units within the performing organization; consultants; stakeholders. including customers; professional and technical associations; and industry groups.
expert power
Authority of PM comes from experience
External customers are not key stakeholders in this instance as they are not actively involved in
an internal project
Facilitate conflict resolution
12. Monitoring & Controlling
facillitating processes
Done as needed throughout projects:
quality planning
communications planning
organizational planning
staff acquisition
risk identification
qualitative risk analysis
quantitative risk analysis
risk response planning
procurement planning
solicitation planning
Failure Mode and Effect Analysis (FMEA) [Technique]
An analytical procedure in which each potential failure mode in every component of a product is analyzed to determine its effect on the reliability of that component and, by itself or in combination with other possible failure modes, on the reliability of the product or system and on the required function of the component; or the examination of a product (at the system andlor- lower levels) for all ways that a failure may occur. For each potential failure, an estimate is made of its effect on the total system and of its impact. In addition, a review is undertaken of the action planned to minimize the probability of failure and to minimize its effects.
Failure to adhere to the quality assurance program may result in
rework, penalties, and project delays
fast tracking
doing activities in parallel that are normally done in sequence
A specific project schedule compression technique that changes network logic to overlap phases that would normally be done in sequence, such as the design phase and construction phase, or to perform schedule activities in parallel. See schedule compression and see also crashing.
feedback
a response, or question of clarification, confirmation of having received message
FF
Finish-to-Finish
or
Free Float
FFP
Firm-Fixed-Price
Final build
The prototype of the camera went fairly well. The project team has documented any flaws, and adjustments are being made. The project team is also working with the manufacturer to complete the requirements for materials and packaging. The project is nearing completion.
Final performance reporting
5. Closure
Finalize the "how to execute and control" aspects of all management plans
19. Planning
Finish Date
A point in time associated with a schedule activity's completion. Usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, baseline, target, or current.
Finish-to-Finish (FF)
The logical relationship where completion of work of the successor activity cannot finish until the completion of work of the predecessor activity. See also logical relationship.
Finish-to-Start (FS)
The logical relationship where initiation of work of the successor activity depends upon the completion of work of the predecessor activity. See also logical relationship.
Firm-Fixed-Price (FFP) Contract
A type of fixed price contract where the hover pays the seller a set amount (as defined by the contract), regardless of the seller's costs.
First build
Management loves the positive information you’ve discovered in the proof-of-concept phase—they’ve set a budget for your project to continue into development. Now you’ll lead your project team through the process of designing and building a video camera according to the specifications from the stakeholders and management. Once the camera is built, your team will test, document, and adjust your camera for usability and feature-support.
fishbone diagram
Ishihawa chart. Cause and effect.
five processes
initiation, planning, execution, control, and closure, are not a series of events, but rather an integrated process, the activities within one process may coincide with an activity within another. For example, a project manager may be working through the execution process to administer the contracts of a vendor while simultaneously working with the vendor through scope verification.
fixed-price contracts
can include an incentive for the seller
Fixed-Price or Lump-Sum Contract
A type of contract involving a fixed total price for a well-defined product. Fixed-price contracts may also include incentives for meeting or exceeding selected project objectives, such as schedule targets. The simplest form of a fixed price contract is a purchase order.
Fixed-Price-Incentive-Fee (FPIF) Contract
A type of' contract where the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria.
Float
Also called slack. See total float and see also free float.
free: time activity can be delayed without affecting the next
total: time activity can be delayed without affecting the project
project: time activity can be delayed without affecting the customer's expected completion date
flowcharting
chart that illustrates how parts of a system occur in sequence
Flowcharting [Technique]
The depiction in a diagram format of the inputs, process actions, and outputs of one or more processes within a system.
FMEA
Failure Mode and Effect Analysis
FNET, SNET
Finish No Earlier Than, Start No Earlier Than
Follow processes
8. Executing
forcing
conflict resolution method where one person forces their point of view or solution to a conflict
Forecasts
Estimates or predictions of conditions and events in the project s future based on information and knowledge available at the time of the forecast. Forecasts are updated and reissued based on work performance information provided as the project is executed. The information is based on the project's past performance and expected future performance, and includes information that could impact the project in the future, such as estimate at completion and estimate to complete.
formal power
PM has been assigned by senior management
formally imposed documents
Requirements include the quantified and documented needs, wants, and expectations of the sponsor, customer, and other stakeholders.
Forward Pass
The calculation of the early start and early finish dates for the uncompleted portions of all network activities. See also schedule network analysis and backward pass.
FPIF
Fixed-Price-Incentive-Fee
fragnets (subnets)
portions of a network diagram that branch off and are not part of the critical path
Free Float (FF)
The amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities. See also total float.
FS
Finish-to-Start
Functional
Ideal for organizations with recurring projects, such as manufacturing. Everyone on the project knows who is in charge: the functional manager.
functional environment
A company that organizes itself by job activity, such as sales, accounting, information technology, and other departmental entities is a
Functional Manager
Someone with management authority over an organizational unit within a frntctional organization. The manager of any group that actually makes a product or performs a service. Sometimes called a line manager.
Functional Organization
A hierarchical organization where each employee has one clear superior, staff are grouped by areas of specialization, and managed by a person with expertise in that area.
Functional organizations are entities
that have a clear division regarding business units and their associated responsibility
functional structure
have a clear division regarding business units. Weakest project structure. (Hanley Wood)
Funds
A supply of money or pecuniary resources immediately available. Gantt Chart. See bar chart.
Gain formal acceptance of the product
4. Closure
Gain formal approval
22. Planning
GERT
Graphical Evaluation and Review Technique. Allows for looping.
Give recognition and rewards
10. Executing
Grade
A category or rank used to distinguish items that have the same functional use (e.g., "hammer"), but do not share the sane requirements for quality (e.g., different hammers may need to withstand different amounts of force).
Ground Rules [Tool]
A list of acceptable and unacceptable behaviors adopted by a project team to improve working relationships, effectiveness, and commwiication.
halo effect
assumption that if person is good at technology, they will be good at managing that technology
Hammock Activity
See sw marv activity.
Hand off completed product
8. Closure
Here are some common application areas you may encounter
Legal issues such as contracts, statements of work, regulatory permits, and lawsuits

Technical issues such as IT management, software development, electrical engineering

Engineering requirements such as experience with pharmaceutical companies, civic engineering, or chemical engineering

Manufacturing issues such as product development, automotive, plastics, and others
Here are some general guidelines to know about customizing project processes:
Facilitating processes may be shifted in sequence to meet the demands of the project (such as the timing of the procurement processes).

All processes may not be needed on all projects, but the absence of a project doesn’t mean it wasn’t needed. The project manager and the project team should identify all of the processes required to make the project a successful one.

Projects that are resource dependent may define roles and responsibilities prior to scope creation. This is because the scope of the project may be limited by the availability of the resources to complete the scope.

The processes may be governed by a project constraint. Consider a predetermined deadline, budget, or project scope. The project constraint, such as a deadline, will determine the activity sequencing, the need for resources, risk management, and other processes.

Larger projects require more detail. Remember that projects fail at the beginning, not the end.

Subprojects and smaller projects have more flexibility with the processes based on the process usefulness. For example, a project with a relatively small team may not benefit from an in-depth communications plan the same as a large project with 35 project team members would.
Here are some other examples of management by projects:
Training employees for a new application or business method

Marketing campaigns

The entire sales cycle from product or service introduction, proposal, and sales close

Work completed for a client outside of the organization

Work completed internally for an organization
Hertzberg's Theory of Motivation
Two catalysts: hygiene (lack of presence de-motivational)and motivating agents
heuristic
rule-of-thumb
Historical Information
Documents and data on prior projects including project files, records, correspondence, closed contracts, and closed projects.
Hold kickoff meeting
23. Planning
Hold progress meetings
11. Executing
Identify stakeholders
5. Initiating
Identifying Closing Processes
Closing a project is a wonderful feeling. Project closure has many requirements for it to be successful, however. Project closure requires a final, complete effort by the project manager, the project team, the project stakeholders, and management to officially close the project and move onto other opportunities. The activities in this process are typically associated with the end of a project, but most may also be completed within project phases, as shown in Figure 3-4.
If the deliverables of the phase, or stage, met the predefined metrics
The process of identifying and documenting project roles, responsibilities and reporting relationships, as well as creating the staffing m anagentent plan.
Implement approved changes, defect repair, preventive and corrective actions
6. Executing
Implementing Scope Change Control
The project manager must follow the change management plan to ensure unneeded changes to the project scope do not occur. This includes scope creep that the project team may be completing on its own accord. For example, the project team members may be making additional adjustments to the equipment they are installing in a project, even through the project scope does not call for the additional adjustments. Scope change control ensures that the documented procedures to permit changes to scope are followed
Implementing Scope Change Control
Implementing Scope Change Control
Imposed Date
A fixed elate imposed on a schedule activity or schedule milestone, usually in the form of a "start no earlier than" and "finish no later than" date.
In a functional matrix environment
the project team may fluctuate at phases or milestones as they complete their assignments and then move onto other activities within the organization
In most organizations, however, projects may begin
with a feasibility study
In other words, the launch, series of phases, and project completion
comprise the project life cycle
In weak matrix organizations, the project manager has the following attributes:
Limited authority

Management of a part-time project team

Project role is part-time

May be known as a project coordinator or team leader

May have part-time administrative staff to help expedite the project
Index and archive records
6. Closure
indirect costs
costs attributed to costs of doing business. e.g., electricity, overhead
influence diagram
charts out a decision problem
Influence Diagram [Tool]
Graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes.
Influencer
Persons or groups that are not directly related to the acquisition or use of the project's product, but, due to their position in the customer organization*, can influence, positively or negatively, the course of the project.
Information distribution
To follow the details of the communications management plan; specifically to disperse the required information to the correct parties according to their identified needs and modalities.
Information Distribution [Process]
The process of making needed information available to project stakeholders in a timely manner.
initial risk assessment allows the project manager
the project team to determine what high-level risks may influence the feasibility, resources, and requirements to complete the project
Initiating
This process launches the project, or phase. The needs of the organization are identified and alternative solutions are researched. The power to launch the project or phase is given through a project charter, and when initiating the project, the wonderful project manager is selected.
Initiating Processes [Process Group]
Those processes performed to authorize and define the scope of a new phase or project or that can result in the continuation of halted project work. A large number of the initiating processes are typically done outside the project's scope of control by the organization, program, or portfolio processes and those processes provide input to the project's initiating processes group.
Initiating, planning, controlling, executing, and closing
is the correct order of the processes presented
Initiator
A person or organization that has both the ability and authority to start a project.
Input [Process Input]
Any item, whether internal or external to the project that is required by a process before that process proceeds. May be an output from a predecessor process.
Inspect
Before the home owners moved into their new home, they’d want to inspect the house for the quality of the building and confirm its functionality
Inspection [Technique]
Examining or measuring to verify whether an activity, component, product, result or service conforms to specified requirements.
Integral
Essential to completeness: requisite; constituent with; formed as a unit with another component.
Integrated
Interrelated, interconnected, interlocked, or meshed components blended and unified into a functioning or unified whole.
Integrated change control
7. Monitoring & Controlling
To manage change across all facets of the project
Integrated Change Control [Process]
The process of reviewing all change requests, approving changes and controlling changes to deliverables and organizational process assets.
Invitation for Bid (IFB)
Generally, this term is equivalent to request jor proposal. However, in some application areas, it may have a narrower or more specific meaning.
Involving the stakeholders in the planning processes
Involving the stakeholders in the planning processes
ISO 9000
method of following procedures by an organization. NOT a quality system
Companies document what they do and do what they document.
Issue
A point or matter in question or in dispute, or a point or matter that is not settled and is under discussion or over which there are opposing views or disagreements.
It has been said that 90 percent of a project manager’s time is
is spent communicating
Iterations - Go Back
16. Planning
JIT
Just-In-Time decreases the inventory investment
Kaizen technologies
small process improvements carried out on a continuous basis
Key Project Stakeholders
Project manager
Project customer
Performing organization
Project team
kill point
like phase gates, are preset times placed in the project when it may, based on conditions and discovery within the phase, be “killed.”
A kill point does not mean the project is killed, just that the potential for termination exists.
Know that each phase
creates a deliverable of some sort and allows the project to move forward if the deliverables meet preset metrics.
Knowledge
Knowing something with the familiarity gained through experience, education, observation, or investigation, it is understanding a process, practice, or technique, or how to use a tool.
Knowledge Area Process
An identifiable project management process within a knowledge area.
known as IPECC
initiation, planning, execution, control, and closure
lag
positive time added to an activity to move it away from the project start date; adding time between activities
A modification of a logical relationship that directs a delay in the successor activity. For example, in a finish-to-start dependency with a ten-day lag, the successor activity cannot start until ten days alter the predecessor activity has finished. See also lead.
Larger projects require more
detail than smaller projects
largest activity a project manager will undertake
Communication, informal and formal, is
Late Finish Date (LF)
In the critical path method, the latest possible point in time that a schedule activity may be completed based upon the schedule network logic, the project completion date, and any constraints assigned to the schedule activities without violating a schedule constraint or delaying the project completion date. The late finish dates are determined (luring the backward pass calculation of the project schedule network.
Late Start Date (LS)
In the critical path method, the latest possible point in time that a schedule activity may begin based upon the schedule network logic, the project completion date, and any constraints assigned to the schedule activities without violating a schedule constraint or delaying the project completion date. The late start dates are determined during the backward pass calculation of the project schedule network.
Latest Revised Estimate
See estimate at completion.
lead
negative time added to an activity to move it closer to project start date; subtracting time between activities
Lead ['technique]
A modification of a logical relationship that allows an acceleration of the successor activity. For example, in a finish-to-start dependency with a ten-day lead, the successor activity can start ten days before the predecessor activity has finished. See also lag. A negative lead is equivalent to a positive lag.
Leading Configuration Management
This process ensures the description of the project’s product is precise, complete, and that it meets the demands of the stakeholder requirements. In addition, configuration management serves as a control agent for changes to the project deliverables. It monitors, guards, and documents changes to the scope. In some projects, configuration management may be the change control system. In other projects, it is part of the change control system.
lessons learned
An ongoing documentation of thing the PM and team have learned throughout the project.
Lessons Learned [Output/Input]
The learning gained from the process of performing the project. Lessons learned may be identified at any point. Also considered a project record, to be included in the lessons learned knowledge base.
Lessons Learned Knowledge Base
A store of historical information and lessons learned about both the outcomes of previous project selection decisions and previous project performance.
Letter of Intent
expresses intent of buyer to procure from seller. not a contract
Level of Effort (LOE)
Support-type activity (e.g., seller or customer liaison, project cost accounting, project management, etc.), which does not produce definitive end products. It is generally characterized by a uniform rate of work performance over a period of time determined by the activities supported.
Leveling
See resource leveling. Life Cycle. See project life cycle.
LF
Late Finish date
lines of communications
=n(n-1)
------
2
n = number of stakeholders
LOE
Level of Effort
Log
A document used to record and describe or denote selected items identified during execution of a process or activity. Usually used with a modifier, such as issue, quality control, action, or defect.
Logical Relationship
A dependency between two project schedule activities, or between a project schedule activity and a schedule milestone. See also precedence relationship. The four possible types of logical relationships are: Finish-to-Start: Finish-to-Finish; Start­to-Start; and Start-lo-Finish.
look to your company’s quality assurance policy or quality program
such as ISO 9000 or Six Sigma
LS
Late Start date
main sources of conflict (7)
1. Schedule
2. Project priority
3. Resources
4. Techinical opinions
5. Administrative processes
6. Cost
7. Personality
Manage Project Team [Process]
The process of tracking team member performance, providing feedback, resolving issues, and coordinating changes to enhance project performance.
Manage reserves
10. Monitoring & Controlling
Manage Stakeholders [Process]
The process of managing communications to satisfy the requirements of, and resolve issues with, project stakeholders.
management by projects
Organizations that manage operations as projects.
An organization that uses projects to move the company forward is
Managing Cost Control
Controlling the project’s cost requires accurate estimates and then a check and balance against those estimates. Procurement management, cash flow, and fundamental accounting practices are required. Though cost control is dependent on project expenses, it also hinges on hidden and fluctuating expenses such as shipping, exchange rates for international projects, travel, and incidentals. Thus, accurate and thorough record keeping is imperative.
Managing has to do with consistently producing key results
that are expected by stakeholders
Managing project procurement includes
Planning for project procurement

Planning for solicitation

Management Project solicitation

Selecting vendors

Managing and creating procurement documents

Administering and closing project contracts
Mapping to Quality Assurance
As the project work continues, the project team and the project manager will need to verify that the project work results are mapping to the organization’s quality assurance program as described in the quality management plan. Failure to adhere to the quality assurance program may result in rework, penalties, and project delays, as shown in the following illustration
Maslow's Hierarchy of Needs
1. Physiological
2. Safety
3. Social
4. Esteem
5. Self-actualization
Master Schedule [Tool]
A summary-level project schedule that identifies the major deliverables and work breakdown structure components and key schedule milestones. See also milestone schedule.
Materiel
The aggregate of things used by an organization in any undertaking, such as equipment, apparatus, tools, machinery, gear, material, and supplies.
Matrix Organization
Any organizational structure in which the project manager shares responsibility with the fimctional managers for assigning priorities and for directing the work of persons assigned to the project.
Matrix structures are
organizations that have a blend of departmental duties and employees together on a common project. Matrix structures allow for project team members to be from multiple departments working toward the project completion. In these instances, the project team members have more than one boss. Depending on the number of projects a team member is participating in, they may have to report to multiple project managers as well as their functional manager.
McGregor's Theory of X & Y
X = lazy, need to be micromanaged "Gen X"
Y = motivated, self-led
Measure according to the management plans
2. Monitoring & Controlling
Measure against the performance measurement baselines
1. Monitoring & Controlling
Measure team member performance
13. Monitoring & Controlling
Media selection
There are multiple choices when it comes to sending a message. Which one is appropriate? Based on the audience and the message being sent, the media should be in alignment. In other words, an ad-hoc hallway meeting is probably not the best communication avenue to explain a large variance in the project schedule
Meeting management
Meetings are forms of communication. How the meeting is led, managed, and controlled all influence the message being delivered. Agendas, minutes, and order are mandatory for effective communications within a meeting.
Methodology
A system of practices, techniques. procedures, and rules used by those who work in a discipline.
milestone
A significant point in the schedule that allows stakeholders to see progress. Deliverables are often called milestones.
A summary-level schedule that identifies the major schedule milestones. See also master schedule.
Milestones are not completed by the project manager
but by the project team. In addition, milestones are the results of activities, not activities themselves.
mitigation
reducing probability or impact of a risk
Money already spent on a project is called
sunk costs
Monitor
Collect project performance data with respect to a plan, produce performance measures, and report and disseminate performance information.
Monitor and Control Project Work [Process]
The process of monitoring and controlling the processes required to initiate, plan, execute, and close a project to meet the performance objectives defined in the project management plan and project scope statement.
Monitoring Risk Response
Risk management requires risk ownership and monitoring by the project team members. As activities in the PND are completed, the project manager and the risk owners must pay special attention to the possible risks and the mitigation plans that may come into play. Risk responses, should they be acted on, may cause secondary risks, cost increases, and schedule delays. Risk response must be rapid and thorough—and their outcomes well-documented for historical reference for downstream activities and other projects.

On the Job Risk response may also include risk impact statements that detail project risk, its possible impact on the project, and its probability. The project manager and management sign the risk impact statement for each identified risk beyond a predetermined score.
Monte Carlo analysis
predicts how scenarios may work out given any number of variables
A technique that computes, or iterates, the project cost or project schedule many times using input values selected at random from probability distributions of possible costs or durations, to calculate a distribution of possible total project cost or completion dates.
Near-Critical Activity
A schedule activity that has low total float. The concept of near-critical is equally applicable to a schedule activity or schedule network path. The limit below which total float is considered near critical is subject to expert judgment and varies from project to project.
Negotiating Project Terms and Conditions
Project managers must negotiate for the good of the project. In any project, the project manager, the project sponsor, and the project team will have to negotiate with stakeholders, vendors, and customers to reach a level of agreement acceptable to all parties involved in the negotiation process. In some instances, typically in less than pleasant circumstances, negotiations may have to proceed with assistance. Specifically, mediation and arbitration are examples of assisted negotiations. Negotiation proceedings typically center on:
Negotiation proceedings typically center on
Priorities

Technical approach

Project scope

Schedule

Cost

Changes to the project scope, schedule, or budget

Vendor terms and conditions

Project team member assignments and schedules

Resource constraints, such as facilities, travel issues, and team members with highly specialized skills

Exam Watch
net present value (NPV)
NPV > 1 is good
Network Logic
The collection of schedule activit}:' dependencies that makes up a project schedule network diagram.
Network Loop
A schedule network path that passes the same node twice. Network loops cannot be analyzed using traditional schedule network analysis techniques such as critical path method.
Network Open End
A schedule activity without any predecessor activities or successor activities creating an unintended break in a schedule network path. Network open ends are usually caused by missing logical relationships.
Network Path
Any continuous series of schedule activities connected with logical relationships in a project schedule network diagram.
Networking [Technique]
Developing relationships with persons who may be able to assist in the achievement of objectives and responsibilities.
Node
One of the defining points of a schedule network; a junction point joined to some or all of the other dependency lines. See also arrow diagramming method and precedence diagramming method.
Objective
Something toward which work is to be directed, a strategic position to be attained, or a purpose to be achieved, a result to be obtained, a product to be produced, or a service to be performed.
OBS
Organizational Breakdown Structure
OD
Original Duration
of all of the project phases within a project
determine if it is feasible for a project to exist
On large or high-profile projects, the project manager may be working with a Change Control Board (CCB
to determine if changes should be approved and factored into a project scope
On the Job
Every industry has some standards and regulations. Knowing which ones affect your project before you begin your work will not only help the project to unfold smoothly, but will also allow for effective risk analysis. In some instances, the requirements of regulations can afford the project manager additional time and monies to complete a project.
On the Job
Stakeholder analysis allows the project manager and the project team to determine the expectations of the customer. If the customer doesn’t know what their expectations are, the project manager cannot decide for them. The project manager and the customer must be in agreement with what the project should create before the creation begins.
On the Job
Business reasons for why a project is created depend on your business objectives. If you’re pitching a project to management, address the most prevalent business needs first. So first, from a business perspective, answer the following question: “Why is this important to my organization?”
On the Job
Being able to recognize your organizational structure in regard to project management will allow you to leverage and position your role as a project manager effectively
On the Job
In high-profile projects, where stakeholders will be in conflict over the project purpose, deliverables, cost, and schedule, the project manager may want to use the Delphi Technique to gain anonymous consensus among stakeholders. The Delphi Technique allows stakeholders to offer opinions and input without fear of retribution from management.
Once the need has been identified
a feasibility study is called for to determine if the need can realistically be met.
operational definitions
quantifiable terms and values used to measure something
Operational transfer
The project is complete. Your team has successfully designed, built, and moved into production, a wonderful, affordable video camera. Each phase of the project allowed the camera to move towards completion. As the project came closer and closer to moving into operations, risk and project fluctuation waned
Operations
An organizational function performing the ongoing execution of activities that produce the same product or provide a repetitive service. Examples are: production operations, manufacturing operations, and accounting operations.
Opportunity
A condition or situation favorable to the project, a positive set of circumstances, a positive set of events, a risk that will have a positive impact on project objectives, or a possibility for positive changes. Contrast with threat.
order of magnitude estimate
used during Initiating process and in top-down estimates. Variance -25 to +75
Ordinal scales
descriptive value
low to high
Organization
A group of persons organized for some purpose or to perform some type of 't'o'k within an enterprise.
Organization Chart [Tool]
A method for depicting interrelationships among a group of persons working together toward a common objective.
Organizational Breakdown Structure (OHS) [Tool]
A hierarchically organized depiction of the project organization arranged so as to relate the work packages to the perfor fining organizational units, (Sometimes OBS is written as Organization Breakdown Structure with the same definition.)
Organizational culture includes
Purpose

Values

Organization policies and procedures

Type of business

Maturity of business
organizational interfaces
most difficult to work with
Organizational planning
To determine the project roles and responsibility. This also determines the reporting structure between the project manager, the project team, and management.
Organizational planning is the facilitating planning process
which defines roles and responsibilities—and the reporting structure within the project.
Organizational Process Assets [Outputllnput]
Any or all process related assets, from any or all of the organizations involved iii the project that are or can be used to influence the project's success. These process assets include formal and informal plans, policies, procedures, and guidelines. The process assets also include the organizations' knowledge bases such as lessons learned and historical irrfirrrrrcrtiorr.
Organizational structures
control how the project manager can obtain resources, the level of authority the project manager can expect, and the participation of the project team
Original Duration (OD)
The activity duration originally assigned to a schedule activity and not updated as progress is reported on the activity. Typically used for comparison with actual duration and remaining duration when reporting schedule progress.
Ouchi's Theory Z
Workers will work if they are challenged and motivated
Output [Process Output]
A product, result, or service generated by a process. May be an input to a successor process.
Overseeing Change Control
The project manager must protect the project scope from unneeded change. Needed changes must be proven, documented, and analyzed for impacts on cost, schedule, and risks. The project manager must work within the confines of the change control plan and follow its guidelines regarding change requests, change approval or denials, and documentation. Overseeing change control may involve a Change Control Board that reviews, approves, or rejects the proposed changes for the project
paralingual
the pitch, tone, and inflection in the sender's voice affect message being sent
Parametric Estimating [Technique]
An estimating technique that uses a statistical relationship between historical data and other variables (e.g.. square footage in construction, lines of code in software development) to calculate an estimate for activityparameters, such as scope. cost, budget, and duration. This technique can produce higher levels of accuracy depending upon the sophistication and the underlying data built into the model. An example for the cost parameter is multiplying the planned quantity of work to be performed by the historical cost per unit to obtain the estimated cost.
parametric modeling
This formula works well with price per unit, like cost per square foot, cost per metric, and so on. In many instances, the proposed project may have widely different costs, and aspects that have never been completed before.
Pareto Chart [Tool]
A histogram, ordered by frequency of occurrence, that shows how many results were generated by each identified cause.
Pareto diagrams
80/20 rule: 80% of problems come from 20% of issues. Histogram. Illustrates problems by cause, from smallest to largest.
Parkinson's Law
"Work expends to fill the time alloted."
Path Convergence
The merging or joining of parallel schedule network paths into the same node in a project schedule network diagram. Path convergence is characterized by a schedule activity with more than one predecessor activity.
Path Divergence
Extending or generating parallel schedule network paths from the same node in a project schedule network diagram. Path divergence is characterized by a schedule activity with more than one successor activity.
PC or PCT
Percent Complete
An estimate, expressed as a percent, of the amount of work that has been completed on an activity or a stork breakdown structure component.
PDM: Precedence Diagramming Method
most common method of arranging project work
Perform Quality Assurance (QA) [Process]
The process of applying the planned, systematic quality activities (such as audits or peer reviews) to ensure that the project employs all processes needed to meet requirements
Perform Quality Control (QC) [Process]
The process of monitoring specific project results* to determine whether they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance.
Performance Measurement Baseline
An approved integrated scope-schedule-cost* plan for the project work against which project execution is compared to measure and manage performance. Technical and quality parameters may also be included.
Perform Quality Assurance (QA) [Process]
The process of applying the planned, systematic quality activities (such as audits or peer reviews) to ensure that the project employs all processes needed to meet requirements
Perform Quality Control (QC) [Process]
The process of monitoring specific project results* to determine whether they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance.
Performance Measurement Baseline
An approved integrated scope-schedule-cost* plan for the project work against which project execution is compared to measure and manage performance. Technical and quality parameters may also be included.
Performance reporting
To determine variances, project performance, and forecasting of project outcome.
The process of collecting and distributing performance information. This includes status reporting, progress measurement, and forecasting.
Performance Reports [Output/Input]
Documents and presentations that provide organized and summarized work performance information, earned value management parameters and calculations, and analyses of project work progress and status. Common formats for performance reports include bar charts, S-curves, histograms, tables, and project schedule network diagram showing current schedule status.
Performing Organization
The enterprise whose personnel are most directly involved in doing the work of the project.
On your project, you’ll have a project team. Who do the team members work for? The performing organization is the entity that employs the people responsible for completing the prject work. In some instances, the performing organization can be a vendor whose project team is completing the project work for another entity, the customer.
PERT
Program Evaluation and Review Technique -- scheduling tool using weighted averages.

O + 4ML + P / 6, where

O = Optimistic
P = Pessimistic
ML = Most Likely
PF
Planned Finish date
Plan Contracting [Process]
The process of documenting the products, services, and results requirements and identifying potential sellers.
Plan Purchases and Acquisitions [Process]
The process of determining what to purchase or acquire, and determining when and how to do so.
Planned Finish Date (PF)
See scheduled finish date. Planned Start Date (PS). See scheduled start date.
Planned Value (Budgetd Cost of Work Scheduled)
Percent planned complete * BAC
Planned Value (PV)
The authorized budget assigned to the scheduled work to be accomplished for a schedule activity or work breakdown structure component. Also referred to as the budgeted cost of work scheduled (BCWS).
Planning
Can you guess what this process is all about? The planning process requires the project manager and the project team to develop the various core and subsidiary management plans necessary for project completion. This process is one of the most important pieces of project management
Planning
Project objectives are determined, as well as how to reach those objectives with the given constraints
Planning is
iterative.
Planning is the iterative process evident
throughout the project
Planning Package
A WBS component below the control account with known work content but without detailed schedule activities. See also control account.
Planning Processes [Process Group]
Those processes performed to define and mature the project scope, develop the project management plan. and identify and schedule the project activities* that occur within the project.
Planning, executing, and controlling are
tightly integrated
PM
Project Management
PM
Project Manager
PMBOK
Project Management Body of Knowledge
PMBOK Guide
Includes all the knowledge and practices for project management.
PMIS
Project Management Information System. E.g., MS Project
PMIS
Project Management Information System
PMO
Project Management Office
PMO
Program Management Office
PMP
Project Management Professional
PO
unilateral form of contract
Portfolio
A collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives. The projects or programs of the portfolio may not necessarily be interdependent or directly related.
Portfolio Management [Technique]
The centralized management of one or more portfolios, which includes identifying, prioritizing, authorizing, managing, and controlling projects, programs, and other related work, to achieve specific strategic business objectives,
Position Description [Tool]
An explanation of a project team member's roles and responsibilities.
powers of PM (5)
formal -- based on authority, reward, penalty, expert -- being knowledgable, referent -- inferred to PM by team members.
None
Expert & reward are best; penalty worst
Practice
A specific type of professional or management activity that contributes to the execution of a process and that may employ one or more techniques and tools.
Precedence Diagramming Method (PDM) [Technique]
A schedule network diagramming technique in which schedule activities are represented by boxes (or nodes). Schedule activities are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
Precedence Relationship
The term used in the precedence diagramming method for a logical relationship. In cut-rent usage, however, precedence relationship, logical relationship, and dependency are widely used interchangeably, regardless of the diagramming method used.
Predecessor Activity
The schedule activity that determines when the logical successor activity can begin or end.
Prepare procurement documents
18. Planning
Presentation
When it comes to formal presentations, the presenter’s oral and body language, visual aids, and handouts all influence the message being delivered.
Preventive Action
Documented direction to perform an activity that can reduce the probability of negative consequences associated with project risks*.
Probability and Impact Matrix [fool]
A common way to determine whether a risk is considered low, moderate, or high by combining the two dimensions of a risk: its probability of occurrence, and its impact on objectives if it occurs.
Procedure
A series of steps followed in a regular definitive order to accomplish something.
Process
A set of interrelated actions and activities performed to achieve a specified set of products, results, or services.
Process Group
See Project ]Management Process Groups.
process groups
5 IPECC: Initiating, Planning, Executing, Controlling, Closing
None
Processes are activities
are completed by people, not things.
Processes are activities
Processes are activities
Procurement Documents [Output/Input]
Those documents utilized in bid and proposal activities, which include buyer's Invitation for Bid. Invitation for Negotiations, Request for Information, Request for Quotation, Request for Proposal and seller's responses.
Procurement involves administering
the contracts between the buyer and the seller
Procurement Management Plan [Output/Input]
The document that describes how procurement processes from developing procurement documentation through contract closure will be managed.
Procurement planning
To determine what goods and services must be procured and when the goods and services will need to be procured in the project life cycle.
Product
An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item. Additional words for products are materiel and goods. Contrast with result and service. See also deliverable.
Product Life Cycle
A collection of generally sequential, non-overlapping product phases* whose name and number are determined by the manufacturing and control needs of the organ/eat/on. The last product life cycle phase for a product is generally the product's deterioration and death. Generally, a project life cycle is contained within one or more product life cycles
product life cycle
The parent of projects. Can also be a program -- several projects used to create a product.
Product Scope
The features and functions that characterize a product, service or result. Product Scope Description. The documented narrative description of the product scope.
product scope
features and functions of the product of the project
Product-orientated processes
These processes are the activities that complete a project’s phase and life cycle. Recall that the project’s life cycle is comprised of the completion of the phases. In other words, the product-orientated processes within a project complete phases, which in turn complete the project. The processes within a project are unique to each project. The concept of project life cycles was discussed thoroughly in Chapter 2.
Product-orientated processes
on the other hand, are unique to the organization creating the product.
Product-orientated processes are
unique to the product the project is creating
product-oriented processes
the activities that complete a project's phase and life cycle. Unique to each project.
Program
A group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually. Programs may include elements of related work outside of the scope of the discrete projects in the program.
Program Management
The centralized coordinated management of a program to achieve the program's strategic objectives and benefits.
Program management is
the management of multiple projects all working in unison toward a common cause
Program Management Office (PMO)
The centralized management of a particular program or programs such that corporate benefit is realized by the sharing of resources, methodologies, tools, and techniques, and related high-level project management focus.See also project management office.
programs
multiple projects working towards a common cause
progress
Performance is measured by determining the budgeted cost of work performed (i.e., earned value) and comparing it to the actual cost of work performed (i.e., actual cost). Progress is measured by comparing the earned value to the planned value.
progressive elaboration
process of discovering or providing greater levels of detail as project moves to completion
Progressive Elaboration [Technique]
Continuously improving and detailing a plan as more detailed and specific information and more accurate estimates become available as the project progresses, and thereby producing more accurate and complete plans that result from the successive iterations of the planning process.
Progressive elaboration is the process of
taking a project concept through to the project plan. As the planning and research activities continue, the more detailed and focused the concept becomes. Progressive elaboration happens throughout the project. It is the process of elements within the project becoming more and more exact as additional information and details become available.
Project
A temporary endeavor undertaken to create a unique product, service, or result.
project
A temporary endeavor to create a unique product or service.
project baselines
the accepted plans against which actual results are compared to identify variances
Project Calendar
A calendar of working days or shifts that establishes those dates on which schedule activities are worked and nonworking days that determine those dates on which schedule activities are idle. Typically defines holidays, weekends and shift hours. See also resource calendar.
project calendar
calendar that defines the working times for the project
project charter
Authorizes the project, PM, and resources to complete project work (I)
Project Charter [Output/Input]
A document issued by the project initiator or sponsor that formally authorizes the existence of a project, and provides the project manager with the authority to apply organizational resources to project activities.
Project charters authorize. When you think of the project charter
think authority for the project manager
Project Communication can be summed up
as “who needs what information and when
Project communication management includes
Planning effective communications
Designing information retrieval systems
Reporting on the project team and on the project performance
Following the Communications Management Plan to close out the project
None
Project Communications Management
The majority of a project manager’s time is spent communicating. This knowledge area details how communications can improve
Project Communications Management [Knowledge Area]
See Appendix F. Project Cost Management [Knowledge Areal. See Appendix F.
Project constraints influence
practically all areas of the project process. Consider constraints as a ruling requirement over the project. Common constraints you’ll encounter are time constraints in the form of deadlines and the availability of resources
Project Cost Management
Cost is always a constraint in project management. This knowledge area is concerned with the planning, estimating, budgeting, and control of costs
Project customer
The customer is the person or group that will use the project deliverable. In some instances, a project may have many different customers. Consider a book publisher for children. The bookstores distribute the children’s book. The adults pay for the book. The children read the book. There is also some consideration given to the user versus the customer. The user uses the product; the customer pays for it. A stakeholder can be both a user and a customer.
project framework
The structure and fundamentals of project management. Composed of the 9 knowledge areas and 5 process areas.
Project Human Resource Management
This knowledge area focuses on organizational planning, staff acquisition, and team development.
Project Human Resource Management [Knowledge Areal
See Appendix F.
Project Human Resource Management includes
Developing a project organizational structure consistent with the organization’s own structure.
Fulfilling staff acquisitions
Developing the project team
None
Project Human Resource Management is
the process of successfully applying the right resource to the project work in the most effective way to accomplish the project goals while maintaining cost and schedule
Project Initiation
Launching a process that can result in the authorization and scope definition of a new project.
Project initiation, while simple on the surface
admits that there is some problem that a solution should solve
Project Integration Management
This knowledge area focuses on project plan develop and execution
project Integration management
Day-to-day actions of the PM to ensure all parts of the project work together.
Includes: project plan development
project plan execution
integrated change control
None
Project Integration Management [Knowledge Area]
See Appendix F.
Project Integration Management includes
The creation and approval of the project plan
Executing the project plan
Managing, controlling, and documenting changes to the project plan
None
Project Life Cycle
A collection of generally sequential project phases whose name and number are determined by the control needs of the organization or organizations involved in the project. A life cycle can be documented with a methodology-.
project lifecycle corresponds to the project management framework and provides several benefits
Each phase results in some type of deliverable.
Phase completion shows accomplishment and progression.
Phase completion allows time for review to determine if the project should move forward.
Phases allow the project to be progressively elaborated
None
Project management
the ability to get things done, must support the higher vision of the organization the project management activities are occurring in.
Project Management (PM)
The application of knowledge, skills, tools, and techniques to project activities* to meet the project requirements.
Project Management Body of Knowledge (PMBOKR`)
An inclusive term that describes the sum of knowledge within the profession of project management. As with other professions such as law, medicine, and accounting, the body of knowledge rests with the practitioners and academics that apply and advance it. The complete project management body of knowledge includes proven traditional practices that are widely applied and innovative practices that are emerging in the profession. The body of knowledge includes both published and unpublished material. The PMBOK is constantly evolving.
project management framework
is the skeleton of projects
Project Management Information System (Pil'IIS) [Tool]
An information system consisting of the tools and techniques used to gather, integrate, and disseminate the outputs of project management processes. It is used to support all aspects of the project from initiating through closing, and can include both manual and automated
Project management is
the management of activities to change the current state of an organization to a desired future state of the organization.
Project Management Knowledge Area
An identified area of project management defined by its knowledge requirements and described in terms of its component processes, practices, inputs, outputs, tools, and techniques.
Project Management Office (PMO)
An organizational body or entity assigned various responsibilities related to the centralized and coordinated management of those projects under its domain. The responsibilities of a PMO can range from providing project management support functions to actually being responsible for the direct management of a project. See also program management office.
Project Management Plan [Outputllnput]
A formal, approved document that defines how the projected is executed, monitored and controlled. It may be summary or detailed and may be composed of' one or more subsidiary management plans and other planning documents.
Project Management Process
One of the 44 processes, unique to project management and described in the PPIBOK" Guide.
project scope
the work needed to create the product of the project
Project Scope
The work that must be performed to deliver a product, service, or result with the specified features and functions.
Project Scope
The scope of the project constitutes the parameters of what the project will, and will not, include. As the project progresses, the stakeholders may try to change the project scope to include more requirements than what was originally planned for (commonly called scope creep). Of course, if you change the project scope to include more deliverables, the project will likely need more time and/or money to be completed. We will talk about scope in Chapter 5
Project Scope Management
This knowledge area deals with the planning, creation, protection, and fulfillment of the project
Project Management Process Group
A logical grouping of the project management processes described in the .PMI3OK" Guide. The project management process groups include initiating processes, planning processes, executing processes, monitoring and controlling processes, and closing processes. Collectively, these five groups are required for any project, have clear internal dependencies, and must be performed in the same sequence on each project, independent of the application area or the specifics of the applied project life cycle. Project management process groups are not project phases.
Project management processes
These processes are the activities that are universal to all projects. These activities comprise the bulk of the project management body of knowledge and will be discussed in detail in Chapters 4 through 12. These processes are common to all projects from construction to technology.
project management processes
Activities universal to all projects.
Project management processes are
the processes you’ll want to study
Project Management Professional (PM")
A person certified as a PMP7 by the Project Management Institute (PMI).
Project Management Sofhvarc [Wool]
A class of computer software applications specifically designed to aid the project management teen with planning, monitoring, and controlling the project, including: cost estimating, scheduling, communications, collaboration. configuration management, document control. records management, and risk analysis.
Project Management System [Tool]
The aggregation of the processes, tools, techniques, methodologies, resources, and procedures to manage a project. The system is documented in the project management plan and its content will vary depending upon the application area, organizational influence, complexity of the project, and the availability of existing systems. A project management system, which can be formal or informal, aids a project manager in effectively guiding a project to completion. A project management system is a set of processes and the related monitoring and control functions that are consolidated and combined into a functioning, unified whole.
Project Management Team
The members of the project team who are directly involved in project management activities. On some smaller projects, the project management team may include virtually all of the project team members.
project manager
schedules, monitors, and controls the various project tasks
project manager
Person accountable for all aspects of a project.
Project Manager (PM)
The person assigned by the petfornring organization to achieve the project objectives*.
project manager and the project team should create a change control plan
that will specify how the project scope may be changed, what the procedure to change the scope is, and what the requirements are to make a change
project manager in a functional organization
will have relatively low authority
project manager will need to know the expectations of his role
in the type of organizational structure he is participating in (functional, matrix, projectized, or composite)
Project managers in a projectized structure enjoy a high level of autonomy over their projects, but also have a higher level of responsibility regarding the project’s success
Projectized Structure
Project managers in a projectized structure have the following attributes
High to complete authority over the project team.
Works full-time on the project with his team (though there may be some slight variation). Has a full-time administrative staff to help expedite the project
None
Project managers in functional organizations have the following attributes:
Little power, Little autonomy, Report directly to a functional manager, The project manager may be known as a Project Coordinator or Team Leader, The project manager’s role is part-time, The project manager may have little or no administrative staff to expedite the project management activities.
None
Project managers must recognize the role of the project as
as a component within an organization
Project managers must scan the project for
hidden stakeholders
Project managers should scan the project outcome in order
to identify all of the stakeholders and collect and record their expectations, concerns, and input regarding the project processes
Project managers spend the bulk of their time
communicating information—not doing other activities
Project Network Diagram (PND
illustrates the flow of activities to complete the project and/or the project phase. It identifies the sequencing of activities identified within the WBS and determines which activities may be scheduled sequentially versus in tandem.
project office
The central source for project management support within an organization. Templates, training, software, etc.
Project Organization Chart [Output/Input]
A document that graphically depicts the project team members and their interrelationships for a specific project.
Project Phase
A collection of logically related project activities*, usually culminating in the completion of a major deliverable. Project phases (also called phases) are mainly completed sequentially, but can overlap in some project situations. Phases can be subdivided into subphases and then components, this hierarchy. if the project or portions of the project are divided into phases, is contained in the work breakdown structure. A project phase is a component of a project life cycle. A project phase is not a project management process group*.
Project phases are also known
stage gates
project plan
Collection of documents developed by project team, stakeholders, and management to guide how the project should flow, how it should be manageed, and what values and priorities are thereof.
Project plan development
Creating a coherent compilation of the other planning processes to guide the project execution.
Project plan execution
To complete the project according to plan. The project plan may also be adjusted based on the outcome of the facilitating processes.
Project plans, like project deliverables
pass through progressive elaboration
Project Portfolio Management is
a management process to select the projects that should be invested in
Project Portfolio Management is specifically, the selection process based on
the need, profitability, and affordability of the proposed projects
Project Portfolio Management is the process
of choosing and prioritizing projects within an organization. An excellent project idea can still be denied if there are not enough resources to complete the project work
project portfolio manager
A management process to select projects to invest in.
project postmortem
Project closure is also known as
Project Process Groups
The five process groups required for any project that have clear dependencies and that are required to be performed in the same sequence on each project, independent of the application area or the specifics of the applied project Ii i' cycle. The process groups are initiating, planning, executing, monitoring and controlling, and closing.
Project Procurement Management
This knowledge area involves planning, solicitation, contract administration, and contract closeout.
Project Procurement Management [Knowledge Area]
See Appendix F.
Project Quality Management
This knowledge area centers on quality planning, assurance, and control
Project Quality Management [Knowledge Area]
See Appendix F. Project Risk Management [Knowledge Area]. See Appendix F.
Project quality management includes
Planning for project quality, Adhering to quality assurance, Enforcing set quality control systems.
None
Project Risk Management
Every project has risks. This knowledge area focuses on risk planning, analysis, monitoring, and control.
Project risk management includes
Planning for Risk Management, Identifying risks, Using qualitative risk analysis, Using quantitative risk analysis, Creating project risk response plans, Actively monitoring and reacting to project risks.
None
Project Schedule [Output/Input]
The planned dates for performing schedule activities and the planned dates for meeting schedule milestones.
Project Schedule Network Diagram [Output/Input]
Any schematic display of the logical relationships among the project schedule activities. Always drawn from left to right to reflect project work chronology.
project scope management
the processes the ensure that the project includes all the work required (and only the work required) to complete the project successfully.
Project Scope Management [Knowledge Area]
See Appendix F.
Project Scope Management includes
Initiating the project, Planning the project scope, Defining the exact project scope, Verifying the project scope, Controlling project scope.
None
Project Scope Management Plan [Output/Input]
The document that describes how the project scope will be defined, developed, and verified and how the work breakdown structure will be created and defined, and that provides guidance on how the project snipe will be managed and controlled by the project management team. It is contained in or is a subsidiary plan of the project management plan. The project scope management plan can be informal and broadly framed, or formal and highly detailed, based on the needs of the project.
Project Scope Statement [Outputllnput]
The narrative description of the project scope, including major deliverables, project objectives, project assumptions, project constraints, and a statement of work. that provides a documented basis for making future project decisions and for confirming or developing a common understanding of project scope among the stakeholders. The definition of the project scope - what needs to be accomplished.
Project Sponsor
See .sponsor.
Project sponsor
The sponsor authorizes the project. This person or group ensures that the project manager has the necessary resources, including monies, to get the work done. The project sponsor is someone within the performing organization that has the power to authorize and sanction the project work, and is ultimately responsible for the project’s success
Project Stakeholder
See stakeholder.
Project stakeholders have a
vested interest in the outcome of the project.
Project Summary Work Breakdown Structure (PSWBS) [Tool]
A work breakdown structure for the project that is only developed down to the subproject level of detail within some legs of the WBS, and where the detail of those subprojects are provided by use of contract work breakdown structures.
project team
responsible for quality of deliverables
Project Team
All the project team members, including the project management team, the project manager and, for some projects, the project sponsor.
Project team
The project team is the collection of individuals that will, hopefully, work together to ensure the success of the project. The project manager works with the project team to guide, schedule, and oversee the project work. The project team completes the project work.
Project Team Directory
A documented list of project team members, their project roles and communication information.
Project Team Members
The persons who report either directly or indirectly to the project manager, and who are responsible for perforating project work as a regular part of their assigned duties.
Project Time Management
Time management is crucial to project success. This knowledge area covers activities, their characteristics, and how they fit into the project schedule
Project Time Management [Knowledge Area]
See Appendix F. Project Work. See work.
project will have similar project management activities,
but the characteristics of the project life cycle will vary from project to project
Projectized
The project manager has autonomy of the project decisions. Improves communication as teams focus on current project work.
Projectized Organization
Any organizational structure in which the project manager has full authority to assign priorities, apply resources, and direct the work of persons assigned to the project.
projectized structure
Organizational structure where the PM has the most power. Staff works full-time on projects.
Projectized structures often
have project team members assigned to the project on a full-time basis
Projects are
temporary endeavors to create a unique product or service
Projects are like snowflakes
no two are alike. Sure, sure, some may be similar, but when you get down to it—each project has its own unique attributes, activities, and requirements from stakeholders
Projects fail at the beginning
not the end
Projects fail at the beginning
not the end. A poor requirements document, inadequate needs assessments, unfulfilled planning, and more early processes can contribute to project failure
Projects must be in alignment with the organization’s
vision, strategy, tactics, and goals
Projects typically have low costs and low demand for resources early in
their life cycle
Projects with much risk and reward are most likely to be accepted within an
entrepreneurial organization
Proof-of-concept
In this phase, you’ll work with business analysts, electrical engineers, customers, and manufacturing experts to confirm that such a camera is feasible to make
Prototype manufacturing
Things are going remarkably well with your video camera project. The project stakeholders loved the first-build and have made some refinements to the design. Your project team builds a working model, thereby moving into prototyping the video camera’s manufacture, testing its cost effectiveness and ease of mass production. The vision of the project is becoming a reality.
Providing Scope Verification
Scope verification is the process of verifying that the work results are within the expectations of the scope. It is typically done at project phase completion with the customer to formally accept the product of the project work. Should scope verification fail, the project scope must be compared against the work results. If the scope has not been met, the project may be halted, reworked, or delayed during a decision making process by the customer.
PS
Planned Start date
PSWBS
Project Summary Work Breakdown Structure
PV
Planned Value
QA
quality assurance is overall performance is evaluated to ensure project meets quality standards
QA
Quality Assurance
QC
Quality Control
QC
work results are monitors to ensure they meet quality standards
qualitative estimating
ranking of risks
Qualitative risk analysis
calls for a probability and impact matrix
Qualitative risk analysis
To prioritize the impact of the risks on the project (typically in a high, medium, and low ranking).
Qualitative Risk Analysis [Process]
The process of prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact.
qualitative risk anaylsis
an examination and ranking of risks based on their probability and impact. Ordinal.
Quality
The degree to which a set of inherent characteristics fulfills requirements.
Quality assurance
To meet the organization’s quality standards. QA is an ongoing process that measures the quality of the work results against the demands of the quality standards of the performing organization
Quality control
To conform to the required organizational quality standards and to remove or improve faulty, below quality, performance.
quality is...
prevention driven
quality management plan
describes how the PM and team will fulfill the quality policy
Quality Management Plan [Outputllnput]
The quality management plan describes how the project management team will implement the performing organization's quality policy. The quality management plan is a component or a subsidiary plan of the project management plan. The quality management plan may be formal or informal, highly detailed, or broadly framed, based on the requirements of the project.
Quality planning
To determine the quality assurance standards used by the organization. The quality assurance standards that are relevant to the project must be planned into the project.
Quality Planning [Process]
The process of identifying which quality standards are relevant to the project and determining how to satisfy them.
Quality Planning is the
only facilitating process listed.
quality policy
formal document that organization follows to achieve preset standar of quality. Can be ISO 9000, Six Sigma, TQM.
Quantitative analysis
also uses simulations and decision tree models
quantitative estimating
mathematical formulas to predict length or cost of activities
Quantitative risk analysis
To measure and consider the probability and associated impact of the risks on the project.
Quantitative risk analysis
is a more in-depth study of the identified risks.
Quantitative Risk Analysis [Process]
The process of numerically analyzing the effect on overall project objectives of identified risks.
quantitative risk anaylsis
mathematical assessment of probabiliy and impact of risks
RAM
Responsibility Assignment Matrix. Shows who is responsible to do work, but not when
RBS
Risk Breakdown Structure
RBS
Resource Breakdown Structure
RD
Remaining Duration
Reassigning project team members is of utmost importance in
projectized organization where project team members are with a project full-time through completion.
Recall that projects are
Recall that projects are
Recall that stage gates
allow a project to continue (after performance and deliverable review) against a set of predefined metrics.
Recommend changes and corrective actions
4. Executing
REcommend changes, defect repair, preventive and corrective actions
6. Monitoring & Controlling
referent power
present when team wants to work with PM, or when PM references a more powerful person (e.g., CEO)
Regulation
Requirements imposed by a governmental body. These requirements can establish product, process or service characteristics
regulations are
rules that must be followed—otherwise, fines, penalties, or even criminal charges may result
Release resources
9. Closure
Reliability
The probability of a product performing its intended function under specific conditions for a given period of time
Remaining Duration (RD)
The time in calendar units, between the data date of the project schedule and the finish date of a schedule activity that has an actual start date. This represents the time needed to complete a schedule activity where the work is in progress.
Report on performance
14. Monitoring & Controlling
Request for Information
A type of procurement document whereby the buyer requests a potential seller to provide various pieces of information related to a product or service or seller capability.
Request for Proposal (REP)
A type of procurement document used to request proposals from prospective sellers of products or services. In some application areas, it may have a narrower or more specific meaning.
Request for Quotation (RFQ)
A type of procurement document used to request price quotations from prospective sellers of common or standard products or services. Sometimes used in place of request for proposal and in some application areas, it may have a narrower or more specific meaning.
Request seller responses
13. Executing
Request Seller Responses [Process]
The process of obtaining information, quotations, bids, offers, or proposals, as appropriate.
Requested Change [Output/Input]
A formally documented change request that is submitted for approval to the integrated change control process. Contrast with approved change request.
Requirement
A condition or capability that must be met or possessed by a sti.stem, product, service, result, or component to satisfy a contract, standard, specification, or other
Requirements
What type of house are you building? What are the characteristics of the house? What are the expectations from the people that will be living in the home?
Reserve
A provision in the project management pkm to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated. The specific meaning of the modified term varies by application area.
Reserve Analysis [Technique]
An analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration. budget, estimated cost, or,ftmds for a project.
Residual Risk
A risk that remains after risk responses have been implemented.
residual risks
leftover after mitigation, transference, avoidance
Resource
Skilled human resources (specific disciplines either individually or in crews or teams), equipment, services, supplies, commodities, materiel, budgets, or funds.
Resource Breakdown Structure (RBS)
A hierarchical structure of resources by resource category and resource type used in resource leveling schedules and to develop resource-limited schedules, and which may be used to identify and analyze project human resource assignments.
Resource Calendar
A calendar of working days and nonworking days that determines those dates on which each specific resource is idle or can be active, Typically defines resource specific holidays and resource availability periods. See also project calendar.
resource calendar
calendar that defines the working times for the resource
Resource Histogram
A bar chart showing the amount of time that a resource is scheduled to work over a series of time periods. Resource availability may be depicted as a line for comparison purposes. Contrasting bars may show actual amounts of resource used as the project progresses.
Resource Leveling [Technique]
Any form of schedule network analysis in which scheduling decisions (start and finish dates) are driven by resource constraints (e.g., limited resource availability or difficult-to-manage changes in resource availability levels).
Resource Planning
See activity resource estimating.
Resource-Constrained Schedule
See resource-limited schedule.
Resource-Limited Schedule
A project schedule whose schedule activity, scheduled start dates and scheduled finish dates reflect expected resource availability. A resource-limited schedule does not have any early or late start or finish dates. The resource-limited schedule total float is determined by calculating the difference between the critical path method late finish date` and the resource-limited scheduled finish date. Sometimes called resource-constrained schedule. See also resource leveling.
responsibility
who DECIDES what on a project
Responsibility Assignment Matrix (RAM) [Tool]
A structure that relates the project organizational breakdown structure to the work breakdown structure to help ensure that each component of the project's scope of work is assigned to a responsible person/team.
Result
An output from performing project management processes and activities. Results include outcomes (e.g., integrated systems, revised process, restructured organi_ation, tests, trained personnel, etc.) and documents (e.g., policies, plans, studies, procedures, specifications, reports, etc.). Contrast with product and service. See also deliverable.
Retainage
A portion of a contract payment that is withheld until contract completion to ensure full performance of the contract terms.
reward power
PM's ability to reward team members
rewards and incentives to move the project team towards completion
The project manager should use approved
Rework
Action taken to bring a defective or nonconforming component into compliance with requirements or specifications.
RFP
from buyer to seller requesting proposal on work
RFQ
from buyer to seller requesting quote price
Risk
An uncertain event or condition that, if it occurs, has a positive or negative effect on a project's objectives. See also risk category and risk breakdown structure.
risk
an unplanned event that can have a positive or negative influence on the project success
Risk Acceptance [Technique]
A risk response planning teclnniquue* that indicates that the project team has decided not to change the project management plan to deal with a risk. or is unable to identify any other suitable response strategy.
Risk assessment is an
in-depth analysis of the project risks through qualitative and quantitative analysis
Risk audits
9. Monitoring & Controlling
Risk Avoidance [Technique]
A risk response planning technique* for a threat that creates changes to the project management plan that are meant to either eliminate the risk or to protect the project objectives from its impact. Generally, risk avoidance involves relaxing the time, cost, scope, or quality objectives.
Risk Breakdown Structure (RBS) [Tool]
A hierarchically organized depiction of the identified project risks* arranged by risk category and subcategory that identifies the various areas and causes of potential risks. The risk breakdown structure is often tailored to specific project types.
Risk Category
A group of potential causes of risk. Risk causes may be grouped into categories such as technical, external, organizational, environmental. or project management. A category may include subcategories such as technical maturity, weather, or aggressive estimating. See also risk breakdown structure.
Risk Database
A repository that provides for collection, maintenance, and analysis of data gathered and used in the risk management processes.
Risk identification
To identify the risks, rewards, and penalties associated with the project
Risk Identification [Process]
The process of determining which risks might affect the project and documenting their characteristics.
Risk identification, qualitative and quantitative risk analysis and response planning
15. Planning
risk management plan
describes planning and analysis, but does not address responses to risks
Risk Management Plan [Output/Input]
The document describing how project risk management will be structured and performed on the project. It is contained in or is a subsidiary plan of the project management plan. The risk management plan can be informal and broadly framed, or formal and highly detailed, based on the needs of the project. Information in the risk management plan varies by application area and project size. The risk management plan is different from the risk register that contains the list of project risks, the results of risk analysis, and the risk responses.
Risk management planning
To determine the risks within the project and how to react to the identified risks
Risk Management Planning [Process]
The process of deciding how to approach, plan, and execute risk management activities for a project.
Risk Mitigation [Technique]
A risk response planning technique* associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold.
Risk monitoring and control
To monitor and maintain risks, responses to risk, introduction of new and secondary risks. In addition, allows for control of currently identified risks and the planned responses to the identified risks.
Risk Monitoring and Control [Process]
The process of tracking identified risks, monitoring residual risks', identifying new risks, executing risk response plans, and evaluating their effectiveness throughout the project life cycle.
risk owners
those responsible for a risk's response
Risk Register [Output/Input]
The document containing the results of' the qualitative risk analysis, quantitative risk analysis, and risk response planning. The risk register details all identified risks, including description, category, cause, probability of occurring, impact(s) on objectives, proposed responses, owners, and current status. The risk register is a component of the project management plan.
Risk response planning
To avoid, eliminate, reduce, or create a planned reaction to the identified risks within the project
Risk Response Planning [Process]
The process of developing options and actions to enhance opportunities and to reduce threats to project objectives.
risk response strategies (4)
avoidance -- avoid risk by eliminating cause, mitigation -- reduce probability of risk occuring, acceptance -- accept consequences of risk, transference -- transfer to 3rd party.
None
Risk Transference [Technique]
A risk response planning technique* that shifts the impact of a threat to a third party, together with ownership of the response.
Risks are also assigned to
risk owners who will monitor thresholds and triggers.
Risks are typically categorized
as high, medium, and low
Risks may be
accepted, avoided, mitigated, countered, or planned for through contingency
Role
A defined function to be performed by a project team member, such as testing, filing, inspecting, coding.
Rolling Wave Planning [Technique]
A form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail at a low level of the work breakdown structure, while the work far in the future is planned at a relatively high level of the work breakdown structure, but the detailed planning of the work to be performed within another one or two periods in the near future is done as work is being completed during the current period.
Rolling wave planning is
description of the planning process in most large projects. It requires the project manager and the project team to revisit the planning process to address the next phase, implementation, or piece of the project
Rolling wave planning is an
acceptable planning solution for long projects whose late activities in the project schedule are unknown or will be determined based on the results of early project phases
Root Cause Analysis [Technique]
An analytical technique used to determine the basic underlying reason that causes a variance or a defect or a risk. A root cause may underlie more than one variance or defect or risk.
rule of 7
project is considered out of control if seven data points in a row are above or below median
Rumors and gossip can sabotage a project
This is an example of cultural achievability
S-Curve
Graphic display of cumulative costs, labor hours, percentage of work, or other quantities, plotted against time. Used to depict planned value, earned value, and actual cost of project work. The name derives from the S-like shape of the curve (flatter at the beginning and end, steeper in the middle) produced on a project that starts slowly, accelerates, and then tails off. Also a term for the cumulative likelihood distribution that is a result of a sunu/ation, a tool of quantitative risk analysis.
Schedule
This is the expected time when the project will be completed. Realistic schedules don’t come easily. You’ll learn all about scheduling and estimating time in Chapter 6. As you may have experienced, some projects require a definite end date rather than, or in addition to, a definite budget. For example, imagine a manufacturer creating a new product for a tradeshow. The tradeshow is not going to change the start date of the show just because the manufacturer is running late with their production schedule.
Schedule Activity
A discrete scheduled component of work performed during the course of a project. A schedule activity normally has an estimated duration, an estimated cost, and estimated resource requirements. Schedule activities are connected to other schedule activities or schedule milestones with logical relationships, and are decomposed from work packages.
Schedule Analysis
See schedule network analysis.
Schedule Compression [Technique
Shortening the project schedule duration without reducing the project scope. See also crashing and first tracking.
schedule control
3 processes:1)PM confirms any schedule changes are agreed upon. 2)PM examines the work results and conditions to know if schedule has changed. 3)PM manages the actual schedule. Part of Integration Management.
None
Schedule Control [Process]
The process of controlling changes to the project schedule.
Schedule development
To determine the project schedule based on the sequence of activities, the required resources, and the required monies. The schedule development process reveals an estimated reflection of when all of the required work can be completed with the given resources.
Schedule Development [Process]
The process of analyzing schedule activity sequences, schedule activity durations, resource requirements, and schedule constraints to create the project schedule.
schedule management plan
has procedures that control how changes to PP can be proposed, accounted, implemented. Subsidiary of PP.
Schedule Management Plan [Output/Input]
The document that establishes criteria and the activities for developing and controlling the project schedule. It is contained in, or is a subsidiary plan of, the project management plan. The schedule management plan may be formal or informal, highly detailed or broadly framed. based on the needs of the project.
Schedule Milestone
A significant event in the project schedule, such as an event restraining future work or marking the completion of a major deliverable. A schedule milestone has zero duration. Sometimes called a milestone activity. See also milestone.
Schedule Model [Tool]
A model used in conjunction with manual methods or project management softurare to perform schedule network analysis to generate the project schedule for use in managing the execution of a project. See also project schedule.
Schedule Network Analysis [Technique]
The technique of identifying early and late start dates*, as well as early and late finish dates*, for the uncompleted portions of project schedule activities. See also critical path method, critical chain method what-if analysis, and resource leveling.
Schedule Performance Index
EV / PV.
(Rate at which the project performance is meeting schedule expectations)
None
Schedule Performance Index (SPI)
A measure of schedule efficiency on a project. It is the ratio of earned value (EV) to planned value (PV). The SPI = EV divided by PV. An SPI equal to or greater than one indicates a favorable condition and a value of less than one indicates an unfavorable condition. See also earned value management.
Schedule Variance
EV - PV
(Difference between were we planned to be and where we are)
None
Schedule Variance (SV)
A measure of schedule performance on a project. It is the algebraic difference between the earned value (EV) and the planned value (PV). SV = EV minus PV. See also earned value management.
Scheduled Finish Date (SF)
The point in time that work was scheduled to finish on a schedule activity. The scheduled finish date is normally within the range of dates delimited by the early finish date and the late finish date. it may reflect resource leveling of scarce resources. Sometimes called planned finish date.
Scheduled Start Date (SS)
The point in time that work was scheduled to start on a schedule activity. The scheduled start date is normally within the range of dates delimited by the early start date and the late start date. It may reflect resource leveling of scarce resources. Sometimes called planned start date.
Scope
The sum of the products, services, and results to be provided as a project. See also project scope and product scope.
Scope Change
Any change to the project scope. A scope change almost always requires an adjustment to the project cost or schedule.
Scope Control [Process]
The process of controlling changes to the project scope.
Scope Creep
Adding features and functionality (project scope) without addressing the effects on time, costs, and resources, or without customer approval.
Scope definition
To breakdown the project deliverables into manageable elements. The sum of the smaller elements equate to the project scope.
Scope Definition [Process]
The process of developing a detailed project scope statement as the basis for future project decisions.
scope management plan
provides details about how the scope may be changed
Scope Planning [Process
The process of creating a project scope management plan.
scope statement
Document that describes the work to meet project objectives. Establishes a common vision. Used as a baseline against all future project decisions.
Scope verification
To verify that phase and project deliverables are in alignment with customer expectations. Scope verification formalizes the acceptance.
Scope verification
4. Monitoring & Controlling
scope verification
the process of the customer accepting the project deliverables. Also, the process of ensuring the deliverables are in alignment with project scope. Occurs at end of project and each project phase.
Scope Verification [Process]
The process of formalizing acceptance of the completed project deliverables.
Scope verification is the proof
that the project manager has completed the project
scoring models
used for all projects up for selection to determine which has higher priority
Secondary Risk
A risk that arises as a direct result of implementing a risk response.
secondary risks
risks that stem from risk responses
Select Project Manager
1. Initiating
Select sellers
14. Executing
Select Sellers [Process]
The process of reviewing offers, choosing from among potential sellers, and negotiating a written contract with a seller.
Seller
A provider or supplier of products, services, or results to an organization.
Send and receive information
5. Executing
Sender-receiver models
Communication requires a sender and receiver. Within this model, there may be multiple avenues to complete the flow of communication, but there may also be barriers to effective communication. Other variables within this model include recipient feedbacks, surveys, checklists, and confirmation of the sent message
Sensitivity Analysis
A quantitative risk analysis and modeling technique used to help determine which risks have the most potential impact on the project. It examines the extent to which the uncertainty of each project element affects the objective being examined when all other uncertain elements are held at their baseline values. The typical display of results is in the form of a tornado diagram.
sensitivity risk
examines each risk on its own value to assess impact to project
Service
Useful work performed that does not produce a tangible product or result, such as performing any of the business functions supporting production or distribution. Contrast with product and result. See also deliverable.
SF
Scheduled Finish date
SF
Start-to-Finish
Should the deliverable not meet the metrics
the project may not be allowed to pass through the gate to move forward
Should-Cost Estimate
An estimate of the cost of a product or service used to provide an assessment of the reasonableness of a prospective seller's proposed cost.
Simulation
A simulation uses a project model that translates the uncertainties specified at a detailed level into their potential impact on objectives that are expressed at the level of the total project. Project simulations use computer models and estimates of risk, usually expressed as a probability distribution of possible costs or durations at a detailed work level, and are typically performed using Monte Carlo analysis.
single source
preferred seller (not only one)
Skill
Ability to use kno'irledge, a developed aptitude, and/or a capability to effectively and readily execute or perform an activity%.
Slack
See total float and f •ee float.
smoothing
conflict resolution method that minimizes perceived size of problem
So what can a project manager expect from the project office? How about:
Project management software, Training and mentoring, HR and project manager support, Guidance, Templates, Administrative help, Project oversight, Access to knowledge repository.
None
So what is a project?
defines a project as “a temporary endeavor undertaken to create a unique product or service.” Temporary means that the project, thankfully, has an end date.(ask designed by PMBOK)
sole source
only qualified seller in market
Solicitation
To accept quotes, bids, proposals, and offers to complete the solicited work as defined through solicitation planning
Solicitation planning
To determine the possible vendors to provide the goods and services for the project.
Some examples of projects include
Designing a new product or service, Converting from one computer application to another, Building a new warehouse, Moving from one building to another, Organizing a political campaign, Designing and building a new airplane.
None
Source selection
To determine which source (vendor) will fulfill the procured good or service
SOW
Statement of Work: fully describes work to be completed. Becomes part of the contract
None
Special Cause
A source of variation that is not inherent in the system, is not predictable, and is intermittent. It can be assigned to a defect in the system. On a control chart, points beyond the control limits, or non-random patterns within the control limits, indicate it. Also referred to as assignable cause. Contrast with common cause.
Specification
A document that specifies, in a complete, precise, verifiable manner, the requirements, design, behavior, or other characteristics of a system, component, product, result, or service and. often, the procedures for determining whether these provisions have been satisfied. Examples are: requirement specification, design specification, product specification, and test specification.
Specification Limits
The area, on either side of the centerline, or mean, of data plotted on a control chart that meets the customer's requirements for a product or service. This area may be greater than or less than the area defined by the control limits. See also control limits.
SPI
Schedule Performance Index
Sponsor
The person or group that provides the financial resources, in cash or in kind, for the project.
SS
Start-to-Start. Scheduled Start date
None
Staff acquisition
To acquire the needed people to complete the determined project work
Staffing management plan
subsidiary plan that shows how project team members will be brought into and excused from project
Staffing Management Plan [Process]
The document that describes when and how human resource requirements will be met. It is contained in, or is a subsidiary plan of, the project management plan. The staffing management plan can be informal and broadly framed, or formal and highly detailed, based on the needs of the project. Information in the staffing management plan varies by application area and project size.
Stage gates are used often in
manufacturing and product development
Stages of Team Development
1. Forming - team first assembles
2. Storming - authority and roles are tested
3. Norming - more normalized
4. Performing - team functions as unit
None
Stakeholder
Person or organization (e.g., customer, sponsor, peiforming organization, or the public) that is actively involved in the project, or whose interests may be positively or negatively affected by execution or completion of the project. A stakeholder may also exert influence over the project and its deliverables.
Stakeholders are those fine folks and organizations
who are actively involved in the project, or will be affected by its outcome—in other words, people, groups, businesses, customers, and communities that have a vested interest in the project
Stakeholders can go by many different names
internal and external customers, project owners, financiers, contractors, family members, government regulatory agencies, communities, cities, citizens and more. The classification of stakeholders into categories is not as important as realizing and understanding stakeholders’ concerns and expectations. The identification and classification of stakeholders does allow, however, the project manager to deliver effective and timely communications to the appropriate stakeholders.
Stakeholders, especially those not in favor of the project deliverable, may try to influence the project itself. This can be attempted in many ways, such as through:
Political capital leveraged to change the project deliverable. Change requests to alter the project deliverable. Scope addendums to add to the project deliverable. Sabotage, through physical acts or rumors, gossip, and negative influence.
None
Standard
A document established by consensus and approved by a recognized body that provides, for common and repeated use, rules, guidelines or characteristics for activities or their results, aimed at the achievement of the optimum degree of order in a given context.
Standards are
accepted practices that are not necessarily mandatory
Start Date
A point in time associated with a schedule activity's start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline. or current.
Start-to-Finish (SF)
The logical relationship where completion of the successor schedule activity is dependent upon the initiation of the predecessor schedule activity. See also logical relationship.
Start-to-Start (SS)
The logical relationship where initiation of the work of the successor schedule activity depends upon the initiation of the work of the predecessor schedule activity. See also logical relationship.
Statement of Work (SOW)
A narrative description of products, services, or results to be supplied.
statistical sampling
choosing data at random for inspection. Can reduce costs of quality control
Strengths, Weaknesses, Opportunities, and Threats (SWOT) Analysis
This information gathering technique examines the project from the perspective of each project's strengths, weaknesses, opportunities, and threats to increase the breadth of the risks considered by risk management.
Strong matrix
Project team may be assigned to a project from 50 to 90 percent of its duration. The project manager has a high level of authority. This model also provides good communication.
Style
The tone, structure, and formality of the message being sent should be in alignment with the audience and the content of the message.
Submitting Final Reports
Once the project documentation has been completed, the project manager will submit the final reports to the appropriate parties as outlined in the communications management plan. The final reports will include variance reports, status reports, cost and schedule accountability, and team member performance reviews, as required by the performing organization
Subnetwork
A subdivision (fragment) of a project schedule network diagram, usually representing a subproject or a work package. Often used to illustrate or study some potential or proposed schedule condition, such as changes in preferential schedule logic or project scope.
Subphase
A subdivision of a phase.
Subproject
A smaller portion of the overall project created when a project is subdivided into more manageable components or pieces. Subprojects are usually represented in the work breakdown structure. A subproject can be referred to as a project, managed as a project, and acquired from a seller. May be referred to as a subnetwork in a project schedule network diagram.
subprojects
Alternatives to programs, subprojects exist under parent projects but follow their own schedule.
Successor
See successor activity.
Successor Activity
The schedule activity that follows a predecessor activity, as determined by their logical relationship.
Summary Activity
A group of related schedule activities aggregated at some summary level. and displayed/reported as a single activity at that summary level. See also subproject and subnetwork.
supercedes all other work-related documents
The contract between the organization and the vendor
SV
Schedule Variance
SV, CV
Cost variance = EV - AC
SPI, CPI
Sched. var = EV - PV. + = good, - = bad,
Sched. Perf. Ind. = EV / PV
Cost Perf. Ind. = EV / AC, > 1 = good, < 1 = bad.
None
SWOT
Strengths, Weaknesses, Opportunities, and Threats
System
An integrated set of regularly interacting or interdependent components created to accomplish a defined objective, with defined and maintained relationships among its components, and the whole producing or operating better than the simple sum of its components. Systems may be either physically process based or management process based, or more commonly a combination of both. Systems for project mcmagenrent are composed of project management processes, techniques, methodologies, and tools operated by the project management team.
T&M
Time and Material
Target Completion Date (TC)
An imposed date that constrains or otherwise modifies the schedule network analysis.
Target Finish Date (TF)
The date that work is planned (targeted) to finish on a schedule activity.
Target Schedule
A schedule adopted for comparison purposes during schedule network analysis, which can be different from the baseline schedule. See also baseline.
Target Start Date (TS)
The date that work is planned (targeted) to start on a schedule activity.
Task
A term for work whose meaning and placement within a structured plan for project work varies by the application area, industry, and brand of project management software.
TC
Target Completion date
TEam building
9. Executing
Team development
To develop the competencies of the project team as a whole and the individual members on the project team.
Team Members
See project team members.
Technical Performance Measurement [Technique]
A performance measurement technique that compares technical accomplishments during project execution to the project management plan's schedule of planned technical achievements. It may use key technical parameters of the product produced by the project as a quality metric. The achieved metric values are part of the work perfbrmance information.
Technique
A defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service, and that may employ one or more tools.
Template
A partially complete document in a predefined format that provides a defined structure for collecting, organizing and presenting information and data. Templates are often based upon documents created during prior projects. Templates can reduce the effort needed to perform work and increase the consistency of results.
TF
Total Float
TF
Target Finish date
The communications plan determines
who needs what information, how they need it, and when it will be delivered
The completion of a phase may also be known as
a phase exit
The completion of a project phase may also be known
a kill point
The correct order is
scope planning, scope definition, activity definition, activity sequencing (Table 3-1 shows the order of these core planning processes).
The cost baseline is an output of the cost budgeting process
it is not an input to schedule development
The cost budgeting process creates
the cost baseline.
the cost of the work to complete is
one of the elements that should be taken into consideration when considering to kill a project.
The deliverables
typically allow the project to move forward to the next phase—or allow the project to be terminated based on the quality, outcome, or condition of the phase deliverable
The detail design document is an output of the requirements
gathering phase
The Executive Layer
sets the vision and strategy of the organization. The business layer asks, “Why is the project important to our organization? Our vision? Our strategy?”
The five process groups can be remembered
IPECC.
The five processes of a project are
initiation, planning, execution, control, and closure
The following are the five project management process groups and what occurs under each
Initiating The project is authorized. Planning Project objectives are determined, as well as how to reach those objectives with the given constraints. Executing The project is executed utilizing acquired resources. Controlling Project performance is monitored and measured to ensure the project plan is being implemented to design specifications and requirements. Closing The project and its various phases are brought to a formal end.
None
The Functional Management Layer
of the pyramid must support the Executive Layer’s objectives. Specifically, the Functional Management Layer is concerned with tactics to accomplish the vision and strategy as set by upper management. The Functional Management Layer asks, “What is the project purpose? What business processes are affected?”
The initiating processes serve as a direct input
to the planning processes
The management of a project, the day-to-day activities
is the bones of successful project management
The needs of the current state are then answered by the deliverables of the proposed project. These needs might have to do with:
Reducing costs, Increasing revenues, Eliminating waste, Increasing productivity and efficiency, Solving a business or functional problem, Taking advantage of market opportunities.
None
The nine formulas comprise Earned Value Management.
Managing project cost includes, Planning for resource allocation, Providing accurate cost estimates, Creating the project budget, Using project management cost control techniques, Proving project financial accountability.
None
The Operational Layer
of the pyramid supports the Executive and the Functional Management layers. This layer is concerned with the specifics of getting the work done. The Operational Layer asks, “How can the work be accomplished? How can we reach the desired future state with these requirements
The organizational structures we’ll discuss include
Functional, Weak matrix, Balanced matrix, Strong matrix, Projectized, Composite.
None
The outcome of the feasibility study may tell management several things
Whether the concept should be mapped into a project or not, If the project concept is worth moving forward with, The expected cost and time needed to complete the concept, The benefits and costs to implement the project concept, A report on the needs of the organization and how the project concept can satisfy these needs.
None
The outputs of the planning phase are a direct input to
the executing processes
The PMP exam will test your knowledge on the outcome of project phases
rather than the idealistic outputs of a project phase.
The project budget is
the cost of the project, cash flow projections, and how the monies will be spent. The project budget should cover the cost of the team’s time, facilities, and all foreseeable expenses
The project charter authorizes
the project, officially naming the project manager and authorizing the project work. Such documents come from Senior Management and allow the project manager to begin the project work with the support, permission, and trust of management.
The project life cycle
comprised of the logical phases within the project itself
the project life cycle determines
not only the start of the project, but also when the project should be completed. All that stuff packed in between starting and ending? Those are the different phases of the project.
The project life cycle is
is comprised of phases
The project life cycle is comprised
of all of the project phases within a project
The Project Management Body of Knowledge is
the wealth of information relevant to the project management profession and what will be covered in the PMP exam.
The project management framework holds up the project
and allows it to operate in the environment within which it was created.
The project management framework is like the skeleton of any project
It makes up the bones that support the project and provides strength and rigidity.
The project manager and the stakeholders work together
The project manager and the stakeholders work together
The project manager is officially named
in the project charter, but the involvement of the project manager in the project will likely come early on in this process group.
The project manager must work with stakeholders to
balance these three constraints or the project will run out of time, cost more than what was planned, or produce poor quality deliverables—or combinations of the three
The project manager should investigate all parties affected by the project to
identify all of the stakeholders—not just the obvious ones. Hidden stakeholders can influence the outcome of the project. They can also add cost, schedule requirements, or risk to a project.
The project manager will be accountable for several things at the end of a project phase
The performance of the project to date, The performance of the project team to date, Proof of deliverables in the project phase, Verification of deliverables in alignment with the project scope
None
The project office is the best choice since its role is to support
the project manager
The project office supports
the project manager
The project records should be archived so that other
project managers can use the information on their projects
The project schedule is dependent on
the creation of the WBS, the PND, and the availability of the resources
The project scope is the description of
the required work, and only the required work, to complete the project
The project team completes the project work. The project manager relies on the project team to do several tasks, including
Complete the project work, Provide information on the work needed to complete the project scope, Provide accuracy in project estimating, Report on project progress.
None
The project’s feasibility is part of
The project’s feasibility is part of
The purpose of negotiations is
to reach a fair agreement among both parties
The quality management plan
details how the project will map to the organizational quality policy; for example, ISO 9000 or Six Sigma specifics
The risk management plan is the output of the
risk management planning process
the scope has been completed
the scope has been completed
The sum of the project phases comprises
the project life cycle.
The work breakdown structure (WBS) is an
organized collection of the project-deliverable components to be created by project work. The project manager cannot complete this activity alone
There are five organizational structures
There are five organizational structures
There are how many lifecycles
five
There are several communication avenues
Listening and speaking, Written and oral, Internal to the project, such as project team member to team member, External to the project, such as the project manager to an external customer, Formal communications, such as reports and presentations,
None
There are several methods you can use to predict project expenses, depending on the project type
For example, if you’ve done a similar project, you could rely on your historical information to predict the costs of the current project. Another method you can use is a mathematical formula called parametric modeling.
There are two types of processes:
Product-orientated processes
None
They Are Demanding
The stakeholders, the people with a vested interested in the project, are all going to have different expectations, needs, and requests of the project deliverables. No doubt there will be conflict between the stakeholders.
They Come with Assumptions
Projects also have assumptions. Assumptions are beliefs held to be true, but that haven’t been proven. For example, the project may be operating under the assumption that the project team will have access to do the work at any time during the workday, rather than only in the evenings or weekends
They Have Clear Requirements
Projects should have a clearly defined set of requirements. These requirements will set the bar for the actual product or service created by the project, the quality of the project, and the timeliness of the project’s completion
Threat
A condition or situation unfavorable to the project, a negative set of circumstances, a negative set of events, a risk that Nvill have a negative impact on a project objective if it occurs, or a possibility for negative changes. Contrast with opporvunity.
Three-Point Estimate [Technique]
An analytical technique that uses three cost or duration estimates to represent the optimistic. most likely, and pessimistic scenarios. This technique is applied to improve the accuracy of the estimates of cost or duration when the underlying activity or cost component is uncertain.
Threshold
A cost, time, quality, technical, or resource value used as a parameter, and which may be included in product specifications. Crossing the threshold should trigger some action, such as generating an exception report.
Time and Material (T&M) Contract
A type of contract that is a hybrid contractual arrangement containing aspects of both cost-reimbursable and fixed price contracts. Time and material contracts resemble cost-reimbursable type arrangements in that they have no definitive end, because the full value of the arrangement is not defined at the time of the award. Thus, time and material contracts can grow in contract value as if they were cost-reimbursable-type arrangements. Conversely, time and material arrangements can also resemble fixed-price arrangements. For example, the unit rates are preset by the buyer and seller, when both parties agree on the rates for the category of senior engineers.
time value of money (TVM)
an economic model to predict the future value of current monies.
n
FV = PV (1 + I)
None
Time-Now Date
See data date.
Time-Scaled Schedule Network Diagram [Tool]
Any project schedule network diagram drawn in such a way that the positioning and length of the schedule activity represents its duration. Essentially, it is a har chart that includes schedule network logic.
To ascertain the required resources to achieve the defined activities to complete the project work. Resources include people, equipment, and materials
Resource planning
To influence an organization (in order to get things done),
a project manager must understand the explicit and implied organizational structures within an organization.
to reach a fair agreement among both parties
the ability to discern between the cause and effect of the problem.
Tool
Something tangible, such as a template or software program. used in performing an activity to produce a product or result.
Total Float (TF)
The total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish (cite, or violating a schedule constraint. Calculated using the critical path method technique and determining the difference between the early finish dates and late finish dates. See also free float.
Total Quality Management (TQNT) [Technique]
A common approach to implementing a quality improvement program within an organization.
TQM
Total Quality Management: a business philosophy to find methods to continuously improve products, services, business practices
None
Tracey will most likely have a low amount of authority in a
functional organization structure
Trend Analysis [Technique]
An analytical technique that uses mathematical models to forecast future outcomes based on historical results. It is a method of determining the variance from a baseline of a budget, cost, schedule, or scope parameter by using prior progress reporting periods' data and projecting how much that parameter's variance from baseline might be at some future point in the project if no changes are made in executing the project.
Triggers
Indications that a risk has occurred or is about to occur. Triggers may be discovered in the risk identification process and watched in the risk monitoring and control process. Triggers are sometimes called risk symptoms or warning signs.
Triple Constraint
A framework for evaluating competing demands. The triple constraint is often depicted as a triangle where one of the sides or one of the corners represent one of the parameters being managed by the project team.
TS
Target Start date
Typically, the product description describes
the solution or realized opportunity that the project will accomplish.
Update lessons learned knowledge base
7. Closure
Use issue logs
11. Monitoring & Controlling
Use work authorization system
12. Executing
User
The person or organization that will use the project's product or service. See also customer.
utility function
a person's willingness to accept risk
Validation [Technique]
The technique of evaluating a component or product during or at the end of a phase or project to ensure it complies with the specified requirements. Contrast with verification.
Value Engineering (ATE)
A creative approach used to optimize project life cycle costs, save time, increase profits, improve quality. expand market share, solve problems. and/or use resources more effectively.
value-added change
causes most change requests
Variance
A quantifiable deviation, departure, or divergence away from a known baseline or expected value.
Variance Analysis [Technique]
A method for resolving the total variance in the set of scope, cost, and schedule variables into specific component variances that are associated with defined factors affecting the scope, cost, and schedule variables.
Variance At Completion
BAC - EAC
(Difference between budgeted and will actually be spent)
None
VE
Value Engineering
Vendor solicitation includes
obtaining quotations, bids, and proposals for the services or the goods to be purchased for the project completion.
Verification [Technique]
The technique of evaluating a component or product at the end of a phase or project to assure or confirm it satisfies the conditions imposed. Contrast with validation.
Virtual Team
A group of persons with a shared objective who fulfill their roles with little or no time spent meeting face to face. Various forms of technology are often used to facilitate communication among team members. Virtual teams can be comprised of persons separated by great distances.
Voice of the Customer
A planning technique used to provide products, services, and results that truly reflect customer requirements by translating those customer requirements into the appropriate technical requirements for each phase of project product development.
War Room
A room used for project conferences and planning, often displaying charts of cost, schedule status, and other key project data.
WBS
Work Breakdown Structure
Weak matrix
The project team may come from different departments, but the project manager reports directly to a specific functional manager
Weak matrix
The project manager has little project authority and acts as a project coordinator.
What are lessons learned?
Lessons learned are documents focused on variances created at the end of each process that detail whate lessons were learned that should be share with future projects. (Emphashis on planned versus variance!)
What are processes comprised of?
Input, Tools and Techniques, and Outputs
What are quantitatively based durations?
Quantity of work to be performed is multipled by a know unit rate.
What are some of the project selection methods used by companies?
Benefits Cost Ratio, Internal Rate of Return, NPV, Opportunity Cost, Payback Period, PV, and ROI
What are the elements of a good wbs?
Detailed down to a low level, graphical and hierarchical, numbered, template driven, created by team, defines responsibilities
What are the nine knowledge areas?
Integration, Scope, Time, Cost, Quality, Risk, HR, Communications, Procurement
What are the outputs of Scope Planning?
Scope Statement, Supporting Detail, Scope Management Plan.
None
What are the steps in the Project Management Life Cycle
Initiating, Planning, Executing, Controlling, Closing.
None
What are the three types of organizations?
Functional, Projectized, and Blended
What are the two techniques of duration compression?
Crashing and Fast-Tracking.
What is a backward pass?
Moving backward through the network daigram to figure out slide.
What is a baseline?
The baseline is the original plan PLUS and approved changes.
What is a functional manager?
A functional manager is the deparmental manager in most organizational structures. The functional manager owns the resources loaned to the project and HR responsibilities for them. (Also function as SME)
What is a Gantt chart?
a chart that show activities represented as horizontal bars and typically have a calendar along the horizontal axis.
What is a milestone chart?
A chart that show significant deliverables. Used for high level project debriefings.
What is a phase?
A phase is a process or group of process that produces a deliverabe(s).
What is a portfolio?
A company's project portfolio represents the entire investment in project and programs. Project portfolios should be aligned to strategic goals.
What is a process?
A package of inputs, tools, and outputs used together to do something on a project.
What is a program?
A program is a larger effor that a project, because it is a group of related projects coordinated together.
What is a project coordinator?
A project coordinator is weaker than a project manager. The pc does not control the budget or make project decision but they do reassign resources.
What is a project expeditor?
An expiditor is a staff assistant who has little or no formal authority. The primary responsibility is to make sure things arrive on time and tasks are completed on time.
What is a Project Network Diagram
Graphical tool that provides a view of the dependencies and sequenceis of each activity.
What is a project?
A project is a temporary group of related tasks undertaken to create a unique product, service, or result.
What is a stakeholder?
A stakeholder is an individual who is involved in the project or whose interest may be affected as a result of the execution of the project.
What is a standard?
A standard is a document approved by a recognize body that provides guidelines.
What is a system?
A system incorporates all the formal procedures and tools put in place to manage something.
What is activity duration estimating?
Analysing and determinign how long it will take to complete and activity.
What is activity sequencing?
Network logic diagram is a picture in which each activity is drawn in the order it must be performed.
What is an activity list?
An activitity list is a further decomposition of the WBS and lists individual activities.
What is an Ishikawa diagram?
A fishbone or cause and effect that shows how different factors relate together and are tied to potential problems.
What is analagous estimationg?
Basing the estimates on prior projects.
What is crashing?
A duration compression technique that adds resources to activities to complete them faster.
What is decomposition?
Decomposition is a tool used in scope definition that helps create the WBS/
What is early finish?
The early finish date is the early start date plus the duration minus one unit.
What is expert judgement.
Knowledge and background of the PM and team members.
What is fast tracking?
A duration compression technique the resequences activites to finish activites quicker. (Increases risk!)
What is float?
Float is how much time an actiivty can slip bfore its path changes the critical path?
What is heuristic?
Rules for which no formula exists. Derived by trial and error.
What is JIT
Manufacturing metothd to bring inventory down to zero
What is Kaizen?
continuous improvement
What is late finish?
Late start plus the duration minus one unit.
What is late start?
Late start dade for an activityis the absolute latest date the activity can start and not impact the finish date. It is calculate by adding the float to the early start.
What is Monte Carlo Analysis?
Predicts likley outcomes for a prject and identifies the areas of the schdule with the highest risk..
What is mutually exclusive?
By choosing one you cannot choose the other.
What is NPV?
Net Present Value is the same as Present value minus costs. The higher the better. Time value of money.
What is pareto's law?
80/20 rule
What is PERT?
A scheduling technique (Program Evaluation and Review Technique) use by taking Pess + 4XReal + Opt and dividing result by 6.
What is progressive elaboration?
Progressive elaboration means that you do not know all of the caharacteristics about a product when you begin a project. Instead, they may be revisted often and refined.
What is project management?
Project management is using skills, knowledg,e and resources to satisfy project requirements.
What is project office?
Project office is a department that can support pms with methodologies, tools, training or even control all of a companies projects.
What is PV?
Time value of money theory that does not factor costs into the equation. The bigger the better.
what is QA?
The sum of all of the quality activities performed in the project to meet quailty standards
What is quality?
Every characteristic that influences satisfaction.
What is reserve time?
A buffer built into the estimates to allow for delays.
What is resource leveling?
Modifying the schedule so that resources are consistent throught the project.
What is ROI?
Return on investment is a percentage that show what return you make by investing in something. The bigger the better.
What is scope change control?
SCC is the process that evaulates and tracks changes to the producs scope.
What is statisically independent?
When two process are not linked together or dependent on each other.
What is the Benefits Cost Ratio?
BCR is the ratio of benefits to cost. The higher the better.
What is the critical path?
Tool used to show where the most schedule risk exists.
What is the Delphi technique?
a means of gathering expert judgement where the participants do not know who the oters are and therefore cannot influence the group.
What is the difference between float and free float?
Float affects the critical path, free float affects other activities.
What is the early start?
Early start date for an activity is the ealiest date an activity can start when you factor in other dependencies.
What is the forward pass technique?
Moving forwar therough the network diagram to perform calculations.
What is the IRR?
Internal Rate of return is a finance term expressing the project's returns versus an interest rate. the higher the better.
What is the largest process group?
Planning
What is the output of Scope Change Control
Changes to Scope, Corrective Action
What is the output of Scope Definition?
WBS
What is the output of Scope Initiation?
Project Charter
What is the output of Scope Verification?
Formal Acceptance
What is the payback period?
The payback period is how long it will take to recoup and investment in a project. The shorter the better.
What is the project charter?
The project charter is created during initiation base on a business need, customer need, or market force. It is signed by senior management and names the pm. It is a HIGH level document that does not describe project details but does include a product description.
What is the role of the project manager?
The pm is repsonsible for the outcome of the project. The pm is empowered to uses org resources, in control of the project, spend the budget, make decisions for the project.
What is the Scope Management Plan?
SMP is created during the Scope Planning Process. It describes how the scope will be defined and managed and also how changes to the scope will be handles.
What is the Scope Statement?
Scope statement is an output of scope planning that outlines a coomon understanding of the project among stakeholders. It provides all deliverables, objectives, and a description of the product.
What is the standard deviation?
Pess - Opt / 6. Tells us how diverse or estimates are. The higher they are the worse.
What is the standard deviation?
Average all data points to get the mean then calculate the difference from the mean. Normal distribution is 68,95,99.7,99.99
What is the Triplle Constraint?
Time, Cost, and Scope
What is the WBS?
Work Breakdown Structure contains a detailed description of all project's deliverables. it is created during Scope Definition.
What iss scope verification?
Scope verification is a controlling process in which the project manager verifies the product of the project is acceptable. (Customes, Stakeholders, Sponsor)
What work will be completed in each phase of the project?
Project life cycles allow a project manager to determine several things about the project, such as:
What resources, people, equipment, and facilities will be needed withineach phase?
What are the expected deliverables of each phase?
What is the expected cost to complete a project phase?
Which phases contain the highest amount of risk?
When it comes to project communications management know this
it’s all about who needs what and when
When it comes to project management, organizations fall into one of three models
Completing projects for others, Completing projects internally through a system, Completing projects as needed.
None
When it comes to stakeholder expectations
nothing beats documentation
Which process group involvess the most work?
Execution
Which process is performed first?
Initiations is usually performed first.
While projects differ, there are also other common traits from project to project. The following lists a few examples
Cost and resource requirements are lower at the beginning of a project, but grow as the project progresses. Once the project moves into the final closing process, costs and resource requirements taper off dramatically.
Projects fail at the beginning, not at the end. Projects are more likely to fail near their beginning—and more likely to succeed near the end of their life cycle. In other words, the odds of completing are low at launch and high at completion.
The further the project is from completing, the higher the risk and uncertainty. Risk and doubt decrease as the project moves closer to fulfilling the project vision.
Changes are easier and more likely at the early phases of the project life cycle than at the completion. Stakeholders can have a greater influence on the outcome of the project deliverables in the early phases, but in the final phases of the project life cycle, their influence on change diminishes. Thankfully. Changes at the beginning of the project generally cost less and have lower risk than changes at the end of a project.
None
Who is a sponsor?
A sponsor is the person paying for the project. (Project Champion)
Who is responsible for TQM?
Everone in the company is responsible for quality and can make a difference.
Who is Senior Management?
Senior management is anyone more senior than project management. They prioritize projects and make sure the pm has authority and access to resources. (Conflict resolution as well)
who needs what information, how they need it, and when it will be delivered
team meetings, reports, expectations for reports, and expectations of communication among team members. The communications plan must account for all needed communications within the project.
Why is historical information important?
Historical information is always used as an input to processes whenever found. Historical information is used to help predict trends for the current project and to evaluate the project's feasibility.
withdrawl
conflict resolution method where issue is not considered important or PM is overruled. Considered a yield-lose scenario
Within each process, there are three common components:
Inputs Documented conditions, values, and expectations that start the given process.
Tools and techniques The actions to evaluate and act upon the inputs to create the outputs.
Outputs The documented results of a process that may serve as an input to another process.
None
Within each project, one attribute that typically varies from project to project is
the project life cycle
Within large or highly technical projects, planning can also be known as
as rolling wave planning
Work
Sustained physical or mental effort, exertion, or exercise of skill to overcome obstacles and achieve an objective.
Work Authorization [Technique]
A permission and direction, typically written, to begin work on a specific schedule activity or work package or control account. It is a method for sanctioning project work to ensure that the work is done by the identified organization, at the right time, and in the proper sequence.
Work Authorization System [Tool]
A subsystem of the overall project management system. It is a collection of formal documented procedures that defines how project work will be authorized (committed) to ensure that the work is done by the identified organization, at the right time, and in the proper sequence. It includes the steps, documents, tracking system, and defined approval levels needed to issue work authorizations.
Work Breakdown Structure
Work that isn't in the WBS isn't in the project -- the WBS organizes and defines the project scope.
Work Breakdown Structure (WBS) [Output/Input]
A deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project. Each descending level represents an increasingly detailed definition of the project work. The WBS is decomposed into work packages. The deliverable orientation of the hierarchy includes both internal and external deliverables. See also work package, control account, contract work breakdown structure, and project summary work breakdown structure.
Work Breakdown Structure Component
An entry in the work breakdown structure that can be at any level.
Work Breakdown Structure Dictionary [Output/Input]
A document that describes each component in the work breakdown structure (WBS). For each WBS component, the WBS dictionary includes a brief definition of the scope or statement of work, defined deliverable(s), a list of associated activities, and a list of milestones. Other information may include: responsible organization, start and end dates, resources required, an estimate of cast, charge number, contract information, quality requirements, and technical references to facilitate performance of the work.
Work Item
Term no longer in common usage. See activity and schedule activity.
Work Package
A deliverable or project work component at the lowest level of each branch of the work breakdown structure. The work package includes the schedule activities and schedule milestones required to complete the work package deliverable or project work component. See also control account.
Work Performance Information [Output/Input]
Information and data, on the status of the project schedule activities being performed to accomplish the project work, collected as part of the direct and numage project execution processes*. Information includes: status of deliverables: implementation status for change requests, corrective actions, preventive actions, and defect repairs; forecasted estimates to complete; reported percent of work physically completed; achieved value of' technical performance measures; start and finish dates of schedule activities.
Workaround [Technique]
A response to a negative risk that has occurred. Distinguished from contingency plan in that a workaround is not planned in advance of the occurrence of the risk event.
workarounds
unplanned risk responses (not planned or accepted)
Your role as the project manager is to
identify, align, and ascertain stakeholders and their expectations of the project. Stakeholder identification is not always as clear-cut as in the preceding example. Because stakeholders are identified as people that are affected by the outcome of your project, external customers may be stakeholders in your project, too