What is the formula for estimate at completion ?
|
BAC/CPI (Cumulative)
|
|
What estimating method would use optimistic time estimates ?
|
Three-point estimate
|
|
"How much work should be done" has what earned value name ?
|
Planned value
|
|
The is the critical path?
|
The longest duration path in the network; The shortest time to complete the project
|
|
The types and quantities of resources required are calculated in what part of time management ?
|
Estimate Activity Resources
|
|
What does the schedule variance tell you ?
|
How far you are behind or ahead of schedule.
|
|
What schedule analysis technique involves crashing ?
|
Schedule compression
|
|
What does a finish-to-start relationship mean ?
|
One activity must finish before the next can start
|
|
What does estimate at completion tell you ?
|
What we now expect the total project to cost.
|
|
Why would you want to crash a project ?
|
To shorten the project duration
|
|
The "what-if" scenario method of schedule network analysis primarily makes use of what technique ?
|
Monte Carlo analysis
|
|
What are sunk costs ?
|
Expended costs
|
|
What does a milestone chart show ?
|
Dates of significant events on the project
|
|
What is the duration of a milestone ?
|
Zero
|
|
What is analogous estimating ?
|
Top-down estimating
|
|
What are fixed costs ?
|
Costs that do not change with project activity
|
|
What are direct costs ?
|
Costs incurred directly by the project
|
|
What is the earned value name for "how much you have spent to date ?"
|
Actual cost
|
|
What is value analysis ?
|
Finding a less costly way to complete the work without affecting quality
|
|
What is a management reserve ?
|
An amount of time or money set aside to cover unforeseen risks
|
|
What is the cost variance formula ?
|
EV - AC
|
|
Cost risk is greater for the buyer in what type of contract ?
|
Cost reimbursable
|
|
What schedule network analysis technique uses buffers ?
|
Critical chain
|
|
What does present value mean ?
|
The value today of future cash flows
|
|
What is the formula for total float ?
|
LS - ES, or LF - EF
The amount of time an activity can be delayed without delaying the project |
|
Why would a project manager want to use resource leveling ?
|
To smooth the peaks and valleys of monthly resource usage consumed by the project
|
|
What does a benefit cost ratio of 2.5 mean ?
|
The benefits are 2.5 times the costs
|
|
A critical path activity will generally have how much float ?
|
Zero
|
|
What is parametric estimating ?
|
Using mathematical relationships found in historical information to create estimates (e.g., dollars per foot)
|
|
What is the range of accuracy with a definitive estimate ?
|
-5 percent to +10 percent
|