• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/94

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

94 Cards in this Set

  • Front
  • Back
"Select Project Manager" belongs in what process group?
Initiating
"Determine company culture and existing systems" belongs in what process group?
Initiating
"Collect processes, procedures and historical information" belongs in what process group?
Initiating
"Divide large projects into phases" belongs in what process group?
Initiating
"Identify Stakeholders" belongs in what process group?
Initiating
"Document business needs" belongs in what process group?
Initiating
"Determine project objectives" belongs in what process group?
Initiating
"Document assumptions and constraints" belongs in what process group?
Initiating
"Develop project charter" belongs in what process group?
Initiating
"Develop preliminary project scope statement" belongs in what process group?
Initiating
"Determine how you will do planning-part of management plans" is part of what Process Group?
Planning
"Create project scope statement" is part of what Process Group?
Planning
"Determine Team" is part of what Process Group?
Planning
"Create WBS and WBS dictionary" is part of what Process Group?
Planning
"Create activity list" is part of what Process Group?
Planning
"Create network diagram" is part of what Process Group?
Planning
"Estimate resource requirements" is part of what Process Group?
Planning
"Estimate time and cost" is part of what Process Group?
Planning
"Determine critical path" is part of what Process Group?
Planning
"Develop schedule" is part of what Process Group?
Planning
"Develop budget" is part of what Process Group?
Planning
"Determine quality standards, processes and metrics" is part of what Process Group?
Planning
"Determine roles and responsiblities" is part of what Process Group?
Planning
"Determine communications requirements" is part of what Process Group?
Planning
"Risk identification, qualitative and quantitative risk analysis and response planning" is part of what Process Group?
Planning
"Iterations - Go Back" is part of what Process Group?
Planning
"Determine what to purchase" is part of what Process Group?
Planning
"Prepare procurement documents" is part of what Process Group?
Planning
"Finalize the 'how to execute and control' aspects of all management plans" is part of what Process Group?
Planning
"Create process improvement plan" is part of what Process Group?
Planning
"Develop final PM plan and performance measurement baselines" is part of what Process Group?
Planning
"Gain formal approval for plan" is part of what Process Group?
Planning
"Hold kickoff meeting" is part of what Process Group?
Planning
"Acquire final team" is part of what Process Group?
Executing
"Execute the PM plan" is part of what Process Group?
Executing
"Work to produce product scope" is part of what process?
Executing
"Recommend changes and corrective actions" is part of what process?
Executing
"Send and receive information" is part of what process?
Executing
"Implement approved changes, defect repair, preventive and corrective actions" is part of what process?
Executing
"Continuous improvement" is part of what process?
Executing
"Follow processes" is part of what process?
Executing
"Team building" is part of what process?
Executing
"Give recognition rewards" is part of what process?
Executing
"Hold progress meetings" is part of what process?
Executing
"Use work authorization system" is part of what process?
Executing
"Request seller responses" is part of what process?
Executing
"Select sellers" is part of what process?
Executing
"Measure against the performance measurement baslines" is part of what process?
Monitoring and Controlling
"Measure according to the management plan" is part of what process?
Monitoring and Controlling
"Determine variances and if they warrant corrective action or a change" is part of what process?
Monitoring and Controlling
"Scope Verification" is part of what process?
Monitoring and Controlling
"Configuration management" is part of what process?
Monitoring and Controlling
"Recommend changes, defect repair, preventive and corrective actions" is part of what process?
Monitoring and Controlling
"Integrated change control" is part of what process?
Monitoring and Controlling
"Approve changes, defect repair, preventive and corrective actions" is part of what process?
Monitoring and Controlling
"Risk audits" is part of what process?
Monitoring and Controlling
"Manage reserves" is part of what process?
Monitoring and Controlling
"Use issue logs" is part of what process?
Monitoring and Controlling
"Facilitate conflict resolution" is part of what process?
Monitoring and Controlling
"Measure team member performance" is part of what process?
Monitoring and Controlling
"Report on performance" is part of what process?
Monitoring and Controlling
"Create forecasts" is part of what process?
Monitoring and Controlling
"Administer contracts" is part of what process?
Monitoring and Controlling
"Develop closure procedures" is part of what process?
Closing
"Complete contract closure" is part of what process?
Closing
"Confirm work is done to requirements" is part of what process group?
Closing
"Gain formal acceptance of the product" is part of what process group?
Closing
"Final performance reporting" is part of what process group?
Closing
"Index archive records" is part of what process group?
Closing
"Update lessons learned knowledge base" is part of what process group?
Closing
"Hand off completed product" is part of what process group?
Closing
"Release resources" is part of what process group?
Closing
You just determined how you will do planning. What is the next best thing to do?
Create project scope statement
You just created the project scope statement. What is the next best thing to do?
Determine team
You just created the team. What is the next best thing to do?
Create WBS and WBS dictionary
You just created the WBS and WBS dictionary. What is the next best thing to do?
Create activity list
You just created the activity list. What is the next best thing to do?
Create network diagram
You just created a network diagram. What is the next best thing to do?
Estimate resource requirements.
You just estimated resource requirements. What is the next best thing to do?
Estimate time and cost
You just estimated time and cost. What is the next best thing to do?
Determine critical path
You just developed the schedule. What is the next best thing to do?
Develop budget
You just developed the budget. What is the next best thing to do?
Determine quality standards, processes and metrics
You just determined quality standards, processes and metrics. What is the next best thing to do?
Determine roles and responsiblities
You just determined roles and responsibilities. What is the next best thing to do?
Determine communications requirements
You just determined communication requirements. What is the next best thing to do?
Risk identification, qualitative and quantitative risk analysis and response planning
You just completed risk identification, qualitative and quantitative risk analysis and response planning. What is the next best thing to do?
Iterations - Go back
You just went back and did iterations. What is the next best thing to do?
Determine what to purchase
You just determined what to purchase. What is the next best thing to do?
Prepare procurement documnets
You just finalized "how to execute and control" aspects of all management plans. What is the next best thing to do?
Create process improvement plan
You just created the process improvement plan. What is the next best thing to do?
Develop final PM plan and performance measurement baselines
You just developed the final PM plan and performance measurement baseline. What is the next best thing to do?
Gain formal approval for plan
You just gained formal approval for your plan. What is the next best thing to do?
Hold kickoff meeting
You just held your kickoff meeting. What is the next best thing to do?
Acquire final team
You just developed your preliminary project scope statement. What is the next best thing to do?
Determine how you will do planning - part of management plans.