• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/18

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

18 Cards in this Set

  • Front
  • Back
Administer Procurements Process
Inputs?
Procurement documents
Project management plan
Contract
Performance reports
Approved change requests
Work performance information
Administer Procurements Process
Tools and Techniques?
Contract change control system
Procurement performance reviews
Inspections and audits
Performance reporting
Payment systems
Claims administration
Record management system
Administer Procurements Process
Outputs?
Procurement documentation
Organizational process assets updates
Change requests
Project Management plan updates
What are the OPA updates in Administer Procurements Process?
Correspondence
Payment Schedules and Requests
Seller Performance Eval
What process in Procurement is preparing SOW and determing source selection criteria?
Plan
What process in Procurement is obtaining bids and proposals and evaluating them?
Conduct
What process in Procurement that monitors vendor performance to ensure that the contract requirements are met?
Administer
What are the three forecasting methods?
Time Series
Causal/Econometric
Judgmental
What involves identifying the physical characteristics of the product, service or result?
Configuration Management
What are the elements of a performance report?
Analysis of past performance
Current status of risks and issues
Work completed during the reporting period
Summary of approved changes
Variance analysis results
Forecasted completion
How does change occur?
Indirect change due to execution process,
-Team member suggestions
-Market conditions
-Production issues
Shareholder requests
Risk
Is Configuration Management a subset of PMIS?
Yes.
What are the three activities associated with Configuration Management.
Configuration identification
Description of product: accurate and complete
Used to verify when changes are made and how they are managed
Configuration status accounting
Process of documenting any changes
Configuration verification and auditing
Determine if performance and functional requirements are met
Change Control Board (CCB) is sometimes called ?
configuration control board (CCB), technical assessment board (TAB), engineering review board (ERB)‏
What are the two requirements for Change?
Always in writing
Always through the formal change control system
Perform Integrated Change Control Process
Inputs?
Project management plan
Work performance information
Change requests
Enterprise environmental factors
Organizational process assets
Perform Integrated Change Control Process
Tools and Techniques?
Expert judgment
Change control meetings
Perform Integrated Change Control Process
Outputs?
Change request status updates
Project management plan update
Project document updates