14 Cards in this Set

  • Front
  • Back
Pert expected activity duration(EAD)
(P+4m+o)/3
Activity standard deviation
P
Activity variance
((p-o)/6)2
Activity duration
EAD-SD to EAD+SD
FLOAT
SLACK
Free float
Project float
Total float
project float
Amount of
Free float
Amount of time project can be delayed without delaying the predecessor activity
total float
Amount of time project can be delayed without delaying the date imposed by the customer
Float
Late start-early start
Late finish -early finish
FLOAT
formula has a start and finish and it always start late
EV -Earned value

PV-Planned value

AC -Acyual Cost
EV-whats the estimated value of the work actually accomplished.
PV-Estimated value of work planned
All the formulas start with EV
For variance you ahve to subtract from EV
For index EV is divided by something
Schedule Variance SV=EV-PV
Cost Variance CV=EV-AC

SPI(Schedule Perfomance Index)=EV/PV
CPI(COst Perfomance Index)=EV/AC
EAC=Estimated cost at completion EAC=AC+ETC

ETC=Estimated cost to completion ETC=EAC-AC

VAC =Variance at completion VAC =BAC-EAC
EAC=AC+ETC

ETC=EAC-AC

VAC =BAC-EAC
TCPI To Complete Perfomance Index
TCPI= BAC-EV/BAC-AC