Pert expected activity duration(EAD)
|
(P+4m+o)/3
|
|
Activity standard deviation
|
P
|
|
Activity variance
|
((p-o)/6)2
|
|
Activity duration
|
EAD-SD to EAD+SD
|
|
FLOAT
SLACK |
Free float
Project float Total float |
|
project float
|
Amount of
|
|
Free float
|
Amount of time project can be delayed without delaying the predecessor activity
|
|
total float
|
Amount of time project can be delayed without delaying the date imposed by the customer
|
|
Float
|
Late start-early start
Late finish -early finish |
|
FLOAT
|
formula has a start and finish and it always start late
|
|
EV -Earned value
PV-Planned value AC -Acyual Cost |
EV-whats the estimated value of the work actually accomplished.
PV-Estimated value of work planned |
|
All the formulas start with EV
For variance you ahve to subtract from EV For index EV is divided by something |
Schedule Variance SV=EV-PV
Cost Variance CV=EV-AC SPI(Schedule Perfomance Index)=EV/PV CPI(COst Perfomance Index)=EV/AC |
|
EAC=Estimated cost at completion EAC=AC+ETC
ETC=Estimated cost to completion ETC=EAC-AC VAC =Variance at completion VAC =BAC-EAC |
EAC=AC+ETC
ETC=EAC-AC VAC =BAC-EAC |
|
TCPI To Complete Perfomance Index
|
TCPI= BAC-EV/BAC-AC
|